National Presto Industries, Inc. v. The United States

338 F.2d 99, 167 Ct. Cl. 749, 1964 U.S. Ct. Cl. LEXIS 138
CourtUnited States Court of Claims
DecidedOctober 16, 1964
Docket370-58
StatusPublished
Cited by73 cases

This text of 338 F.2d 99 (National Presto Industries, Inc. v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Presto Industries, Inc. v. The United States, 338 F.2d 99, 167 Ct. Cl. 749, 1964 U.S. Ct. Cl. LEXIS 138 (cc 1964).

Opinions

DAVIS, Judge.

Toward the close of the Korean hostilities, in the late fall of 1952, the Ordnance Department of the Army sought proposals for the commercial production of 105-millimeter artillery shells. Along with other firms, plaintiff, a fabricator of pressure cookers which had turned to the manufacture of cartridge cases and shells during and after World War II, submitted a plan for the production of the shells (at its plant at Eau Claire, Wisconsin) by the conventional hot forge method — involving considerable heat twice applied, and two turning steps at which large amounts of excess steel are removed from the shell. While the proposals were under consideration, Ordnance mulled over a change in the procurement from the conventional method to the new hot cup-cold draw process. The central advantage of this mode is that the steel is heated only once and there is much less excess metal to be removed. The plaintiff already had an Ordnance contract for making 105-millimeter shells by the older method at its factory at Menomonie, Wisconsin, and its initial response to the Army’s suggestion of a further contract was based on that system. However, plaintiff then considered conforming its proposal for Eau Claire manufacture to the newer process. In June 1953 the parties entered into two letter contracts, one for establishing lines to produce shells at Eau Claire and the other for the production there of one million 105-mm. shells. It was shortly agreed that the Eau Claire plant was to use the hot cup-cold draw method. After production of the shells immediately needed, the plant was to be retained in stand-by condition for the Army’s use.

Under these letter contracts, which were preliminary to formal agreements, the plaintiff was to propose the equipment (and facilities) it believed to be needed for production. The defendant was to pay for the items upon which agreement was reached; in that sense the equipment was to be government-furnished property. Some months were consumed in plaintiff’s preparation of its proposed equipment-schedule, and of a suggested fixed-price for making the shells by the new method. There were some tentative discussions. On November 10, 1953, the parties met to consider the final schedule to be incorporated in the formal facilities contract which would supersede the letter contract on facilities. Of concern to us was the discussion of the need for plunge grinders— devices mainly used to remove surface imperfections in steel. Plaintiff felt that the six new shell lines at Eau Claire should include 24 plunge grinders, four to each line. Ordnance thought them unnecessary; its principal representative informed plaintiff that he would not approve a facilities schedule which included plunge grinders; he also said that, if the grinders proved necessary in the course of performance, he would sanction their acquisition.1 The plaintiff [102]*102thereupon submitted its new price and a schedule omitting the grinders; that equipment was not included in the formal contracts which were executed in early December 1953. Production of the shells was to commence, after installation of the facilities yet to be acquired, in July 1954.

Plaintiff then began the detailed process leading to the acquisition and installation of the necessary equipment. In March 1954, before completion of the contractor’s engineering studies and its placement of orders, the defendant told plaintiff that it was drastically curtailing its procurement of 105-mm. shells and that both plaintiff’s Eau Claire and Menomonie contracts were terminated for all production scheduled for delivery after April 30, 1954. Following negotiations for a decrease rather than elimination of production, the defendant rescinded its notice of termination of the Eau Claire contract and, on June 30, 1954, the parties entered into a supplemental agreement (to that contract) providing that plaintiff should produce a new total of 1,100,000 105-mm. shells (in place of the former totals of the shells to be made at Menomonie and at Eau Claire), at a fixed price of $5.2499 per shell, to be manufactured at either plant as plaintiff wished. Production at Menomonie would follow the conventional hot forge method while the new hot cup-cold draw system would be used at Eau Claire.

Because the Menomonie plant was already operational, plaintiff began to supply the new total of 1,100,000 shells from that factory. By the end of August 1955, over 800,000 shells had been shipped from there. Since preliminary operations at Eau Claire did not begin until the summer of 1955, it appeared that the full quota of shells would be produced at Menomonie by the conventional process before the new method could be fairly sampled at Eau Claire. The Government was anxious to test the hot cup-cold draw system. Early in September 1955, the parties agreed that the conventional operations should be reduced so that some 180,000 shells would be left to be manufactured (by March 1956) under the new process.

Plaintiff suffered difficulties of various kinds in making the hot cup-cold draw system fully functional at Eau Claire. Only one of these problems is now alleged to be the defendant’s responsibility • — the need for turning equipment to shave excess metal. The first batch of shells, produced relatively slowly and using only one of the six lines at Eau Claire, did not require any such turning. But as production increased there, in the fall of 1955, it became doubtful that good shells could be made without a turning step; the shells were not concentric when they came out of the hot forge and some shaving (but still less than in the conventional method) was necessary. A final decision on this point was put off until April 1956 when it was decided by the parties to purchase a number of new lathes for this purpose (plunge grinders were never considered). Meanwhile, plaintiff, with the consent of Ordnance, transferred some older lathes from the Menomonie plant to perform this turning function. The remainder of the contract shells were produced at Eau Claire, using these Me[103]*103nomonie lathes. Production of the 180,-000 shells to be made by the hot cup-cold draw process was not completed until September 1956. The defendant paid for the additional equipment and also remitted the full contract price. Nevertheless, plaintiff lost considerably over $700,000 on its production at Eau Claire. It attributes some $743,000.00 of this loss to the lack of turning equipment, timely furnished and adequate; plaintiff’s claim is that it expended large sums (on labor, overhead, and materials) in trying for a long time to produce the shells without turning, and thereafter in using the Menomonie lathes. These expenses plaintiff charges directly to defendant’s refusal to include plunge grinders in the original schedule of equipment and facilities.

I

The case has been wholly tried in this court2 and we must decide whether the Government should assume all (or part) of the loss plaintiff incurred or whether that loss must stay with the contractor which has thus far shouldered it. The first subdivision of the claim is that the defendant broke its contractual obligation by refusing to authorize the acquisition and use of turning equipment at the outset of the contract. The theory is that, since the Government was to furnish the facilities for the production lines at Eau Claire, it was required to supply adequate devices to make the 105-mm. shells by the new hot cup-cold draw method.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

DynCorp International LLC
Armed Services Board of Contract Appeals, 2019
Park Properties Associates, L.P. v. United States
128 Fed. Cl. 493 (Federal Claims, 2016)
River Ridge Development Authority
Armed Services Board of Contract Appeals, 2016
Lakeshore Engineering Services, Inc. v. United States
748 F.3d 1341 (Federal Circuit, 2014)
P & K Contracting, Inc. v. United States
108 Fed. Cl. 380 (Federal Claims, 2012)
URS Group, Inc. v. Tetra Tech FW, Inc.
181 P.3d 380 (Colorado Court of Appeals, 2008)
Yankee Atomic Electric Co. v. United States
73 Fed. Cl. 249 (Federal Claims, 2006)
George Sollitt Construction Co. v. United States
64 Fed. Cl. 229 (Federal Claims, 2005)
Smelser v. United States
53 Fed. Cl. 530 (Federal Claims, 2002)
Northrop Grumman Corp. v. United States
47 Fed. Cl. 20 (Federal Claims, 2000)
Unihealth v. U.S. Healthcare, Inc.
14 F. Supp. 2d 623 (D. New Jersey, 1998)
Westinghouse Electric Corp. v. United States
42 Cont. Cas. Fed. 77,332 (Federal Claims, 1998)
Knieper v. United States
38 Fed. Cl. 128 (Federal Claims, 1997)
Peterson Builders, Inc. v. United States
40 Cont. Cas. Fed. 76,853 (Federal Claims, 1995)
T.L. Roof & Associates Construction Co. v. United States
38 Cont. Cas. Fed. 76,534 (Federal Claims, 1993)
Dairyland Power Cooperative v. United States
38 Cont. Cas. Fed. 76,492 (Federal Claims, 1993)
Big Chief Drilling Co. v. United States
38 Cont. Cas. Fed. 76,418 (Court of Claims, 1992)
G.C. Murphy Co. v. M. Goldfarb-My Florist Inc.
11 Pa. D. & C.4th 614 (Alleghany County Court of Common Pleas, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
338 F.2d 99, 167 Ct. Cl. 749, 1964 U.S. Ct. Cl. LEXIS 138, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-presto-industries-inc-v-the-united-states-cc-1964.