URS Group, Inc. v. Tetra Tech FW, Inc.

181 P.3d 380, 2008 Colo. App. LEXIS 159, 2008 WL 323767
CourtColorado Court of Appeals
DecidedFebruary 7, 2008
Docket06CA1243, 06CA2220
StatusPublished
Cited by9 cases

This text of 181 P.3d 380 (URS Group, Inc. v. Tetra Tech FW, Inc.) is published on Counsel Stack Legal Research, covering Colorado Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
URS Group, Inc. v. Tetra Tech FW, Inc., 181 P.3d 380, 2008 Colo. App. LEXIS 159, 2008 WL 323767 (Colo. Ct. App. 2008).

Opinion

*384 Opinion by

Judge VOGT.

In this dispute concerning compensation for remediation work at the Rocky Mountain Arsenal, plaintiff, URS Group, Inc., appeals the trial court judgment awarding it only a portion of the relief requested in its complaint against defendants, Tetra Tech FW, Inc. and Foster Wheeler Environmental Corporation (collectively, TTFW). URS also appeals the court's order awarding costs to TTFW. We affirm the judgment in part and reverse it in part, reverse the order awarding costs, and remand for further proceedings.

TTFW was the program management contractor for the arsenal remediation project under a contract with the United States Army. In 2001, TTFW issued a request for proposal (RFP) seeking bids for a soil remediation project with attendant foundation demolition work. URS submitted a bid of $10,857,570 and was awarded the subcontract.

After demolition began, URS encountered problems removing the foundations. Claiming that the concrete footings and structures it encountered did not conform to the information contained in the RFP materials, URS submitted contract change notification (CCN) 21, which sought reformation of the subcontract to increase the price by $9,166,925, the amount of URS's additional costs attributable to the subsurface conditions it encountered. URS claimed entitlement to such additional compensation under the contract's differing site conditions (DSC) clause, which provided for an equitable adjustment if subsurface conditions differed materially from those indicated in the contract.

When TTFW refused to pay additional compensation, URS brought this action. In addition to asserting other claims that are not at issue in this appeal, URS sought relief on its CCN 21 differing site conditions claim on theories of breach of contract, breach of the duty of good faith and fair dealing, mutual mistake, equitable adjustment, and negligent misrepresentation. Following a bench trial, the court found in favor of TTFW on all the CCN 21 claims. After offsetting certain sums to which TTFW was entitled on its counterelaim, the court awarded URS $1,149,610.50 on its other claims.

TTFW subsequently moved for costs pursuant to section 18-17-202, C.R.8.2007, on the basis that URS's recovery at trial was less than the offer of settlement TTFW had made. The trial court agreed and awarded TTFW costs in the amount of $168,628.54.

I. CCN 21 Differing Site Conditions Claims

URS contends that the trial court erred in denying any recovery on its CCN 21 claims relating to the subsurface conditions at the arsenal. We agree in part.

A. Governing Law and Standard of Review

The parties' contract provides that "[tlhis Subcontract shall be governed by the laws of the State of New Jersey." It is undisputed that such a choice of law provision is enforceable. See TerraMatrix, Inc. v. U.S. Fire Insurance Co., 939 P.2d 483, 490 (Colo.App.1997); Kramer v. Ciba-Geigy Corp., 371 N.J.Super. 580, 854 A.2d 948, 959 (App.Div.2004). We therefore apply New Jersey law in analyzing the contract claims in this case. In so doing, we recognize that New Jersey courts rely on federal case law addressing government contract issues when there are no applicable New Jersey state court decisions. See M.J. Paguet, Inc. v. N.J. Dep't of Transportation, 171 N.J. 378, 794 A2d 141, 149 (2002); P.T. & L. Construction Co. v. State, 108 N.J. 589, 581 A.2d 1330, 1334 (1987).

Additionally, as in Colorado, a trial court's interpretation of a contract is reviewed de novo. See M.J. Paquet, 794 A.2d at 152; Hutnick v. ARI Mutual Insurance Co., 391 N.J.Super. 524, 918 A.2d 729, 732 (App.Div.2007). The trial court's findings of fact are reviewed to determine "whether there is sufficient credible evidence in the record to support [them]." PT. & L. Construction, 581 A.2d at 1341.

B. Assumption of Risk

The trial court found that TTFW had information about subsurface conditions at the arsenal that it did not disclose to bidders *385 during the bid solicitation period, and it further found that neither of the parties to this action had apparently anticipated the difficulties that would be encountered in removing the foundations. The court nevertheless concluded that URS was not entitled to compensation on its CCN 21 claims because, by entering into a fixed price contract, URS had assumed the risk of encountering unknown subsurface conditions. The court stated:

The demolition portion of the contract was a fixed price contract and the risks associated with unknown subsurface quantities and configurations of concrete were assumed by [URS]. ... [URS's] mutual mistake and differing site conditions claims are based upon the presence of large and irregularly shaped foundations. The risk of such a contingency was assumed by [URS] under the terms of the contract.

URS contends that this ruling "ignored the fundamental risk-allocation function of the subcontract's differing site conditions clause." We agree.

1. DSC Clause in Fixed Price Contracts

A contractor who enters into a fixed price services contract with no DSC clause assumes the risk that its cost of performance will be higher than the contract price. Dalton v. Cessna Aircraft Co., 98 F.8d 1298, 1304-05 (Fed.Cir.1996) ("Because fixed-price contracts do not contain a method for varying the price of the contract in the event of unforeseen cireumstances, they assign the risk to the contractor that the actual cost of performance will be higher than the price of the contract."). If URS had assumed such a risk, it would not have been entitled to recovery on its breach of contract or mutual mistake claims. See National Presto Industries, Inc. v. United States, 167 Ct.Cl. 749, 338 F.2d 99, 105-08 (1964).

However, the fixed price subcontract between URS and TTFW incorporated by reference the standard federal DSC clause. That clause provides, in relevant part:

(a) The Contractor shall promptly, and before conditions are disturbed, give written notice to the Contracting Officer of (1) subsurface or latent physical conditions at the site which differ materially from those indicated in this contract....
(b). ... If the conditions do materially so differ and cause an increase or decrease in the Contractor's cost of, or the time required for, performing any part of the work under this contract ... an equitable adjustment shall be made under this clause and the contract modified in writing accordingly.

48 CFR. § 52.236-2 (2007) see also 48 C.F.R. § 36.502 (2007) (requiring insertion of DSC clause in certain fixed price contracts and permitting its insertion in others).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Montalla, LLC V. Commonwealth of Virginia
Court of Appeals of Virginia, 2023
y Centerra v. Poag & McEwen
2021 COA 2 (Colorado Court of Appeals, 2021)
Danko v. Conyers
2018 COA 14 (Colorado Court of Appeals, 2018)
30 Taylor Morrison of Colorado, Inc. v. Terracon Consultants, Inc
2017 COA 64 (Colorado Court of Appeals, 2017)
P & K Contracting, Inc. v. United States
108 Fed. Cl. 380 (Federal Claims, 2012)
Strunk v. Goldberg
258 P.3d 334 (Colorado Court of Appeals, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
181 P.3d 380, 2008 Colo. App. LEXIS 159, 2008 WL 323767, Counsel Stack Legal Research, https://law.counselstack.com/opinion/urs-group-inc-v-tetra-tech-fw-inc-coloctapp-2008.