Northrop Grumman Corp. v. United States

47 Fed. Cl. 20, 2000 U.S. Claims LEXIS 125, 2000 WL 863025
United States Court of Federal Claims·Decided June 16, 2000·No. No. 97-276C·Published·Cited by 44 cases

Opinion

OPINION

MILLER, Judge.

This contract action, before the court after trial, juxtaposes the military’s evolving requirements and a contractor’s over-ambitious assessment of its capabilities to meet them. In the circumstances the contractor questions the military’s choice of a fixed-price incentive contract and the mushrooming of labor hours expended in responding to fluid requirements. The military defends the choice of contract type, disputes the charge of illegality, and blames the contractor for spending $34 million on a $22 million contract. The court concludes that Congress precluded this type of contract during three years of its performance, but that damages shall be determined under the contract. Plaintiff is entitled to an award on some of its claims; with respect to constructive changes, which dominated trial, plaintiff has failed to establish that the Government ordered most of the constructive changes and, even if so, to prove its damages with the requisite certainty-

FACTS

In the mid-1980s, the military identified a need to upgrade its Vietnam-era Tactical Air Command Central (“TACC”). This objective to advance the command and control of Marine Corps operations gave birth to the Advanced Tactical Air Command Central (the “ATACC”). From this nascent concept, the Navy and the Marine Corps commenced the development of the ATACC, the subject matter of the instant case.1

The ATACC was to be a set of four modular shelters that could be transported onto the battlefield to provide local command and control. Each shelter was to house sufficient hardware (including desktop terminals, operator consoles, and communications equipment) and software (including software for various military communications protocols, message generation, and database management) for the Marine Corps operators to plan and implement airborne strikes. This portable command and control center was to replace the TACC, which contained outmoded equipment and software and was housed in an inflatable bubble.

[27] On February 7,1986, the Government prepared the Software Baseline Estimate. It estimated the lines of code (“LOC”) to be developed by the eventual ATACC contractor to be between 52,200 and 121,200. The estimate concluded that a total of 182,000 to 240,000 LOC would be required. The difference between the two estimates entailed code furnished by the Government or already in existence.

On November 17, 1986, United States Navy Space and Naval Warfare Systems Command (“SPAWAR”) finalized the ATACC Acquisition Plan 86-16 (the “Acquisition Plan”). The Acquisition Plan calls for, among other items, a standardized Navy computer — the AN/UYK-14/43/44 — which can use the CMS-2 compiler, Tactical Digital Information Link (“TADIL”)2 software to be government-furnished information (“GFI”), and developmental items (“DI”) to be mainly software in the information-management area of the ATACC program. The Acquisition Plan labels the software risk as “moderate and manageable.”

In August 1986 SPAWAR opened the ATACC request-for-proposal (“RFP”) library at Calculon Corporation, a government contractor providing support for the ATACC program. The library contained almost all of the information required to bid on the RFP; some limited information related to tracking capabilities was classified and not in the library. Grumman Data Systems, Inc. (“GDS”), became interested in the project. GDS was a division of Grumman Aerospace Corporation (“Grumman”). (Northrop Corporation acquired Grumman on May 18,1994, forming Northrop Grumman Corporation (“plaintiff”)). The types of documents that GDS personnel could have reviewed (or copied) at the library included the first draft Statement of Work (“SOW”), operational documents, TACC documents, military standards (“MIL-STD”), and Data Item Descriptions (“DIDs”). GDS used the Calculon library, copied a complete Marine Tactical System (“MTS”) protocol and encountered no banders to review of all the documents in the library. At approximately this time, SPA-WAR held a pre-RFP industry conference for the ATACC program. Before SPAWAR released the ATACC RFP, GDS sent several representatives to SPAWAR to identify the Marine Corps’s needs regarding the ATACC program.

SPAWAR issued the ATACC solicitation on April 30, 1987. Two months later the Marine Corps completed the MTS message specification.

GDS composed a proposal team that included, among others: Richard F. McLean, the ATACC Software Manager; Joseph A. Cotellessa, the Manager of the Battle Management Subsystem for the ATACC; Dr. Joseph H. Kullbaek, Senior Systems Architect; Harold LaWare, Vice President of Technical Operations for GDS; and William T. Bonner, Engineering Manager. Dr. Stuart A. Steele, Vice President of GDS, was responsible for technical solutions, costing, staffing, and personnel for the program.

To generate an LOC estimate, Mr. Cotellessa used the Constructive Cost Model (“COCOMO”), a widely accepted estimating tool. COCOMO is a top-down tool that generates an estimate of man-months of labor based on projected LOC. Because it is a modeling tool, COCOMO must be calibrated properly, usually by use of past results. Dr. Steele testified that Mr. Cotellessa had someone calibrate COCOMO based on three past projects. Dr. Steele believed the LOC estimate generated by COCOMO was reasonable. Mr. Cotellessa supervised the estimates of all GDS software proposed for the ATACC. Mr. Cotellessa used the ATACC specification to generate an architecture. Then, he used the lowest level requirements to determine how many LOC of existing products needed to be modified. For new software Mr. Cotellessa constructed from bottom up a structure to estimate the LOC needed for all new items by asking members of each project group within GDS what they considered their portion of the ATACC software development would require. COCOMO resulted in a more pessimistic schedule than [28] the bottom-up model. GDS used the COCO-MO estimate when it made its proposal because COCOMO was able to be segregated into skill areas.

No confidence interval was assigned to either estimate. Dr. Steele testified that he did not usually assign confidence intervals to LOC estimates.

Concurrent with the generation of its proposal, plaintiff undertook risk assessments regarding the ATACC project. Mr. LaWare personally evaluated the risk and concluded that it was very low because of the amount of non-developmental items (“NDI”) that GDS proposed for the project.

On August 20, 1987, SPAWAR finalized the Source Selection Plan (the “SSP”). Four days later GDS submitted its proposal. GDS proposed an ATACC based predominantly on NDI hardware and software. The GDS NDI software had been developed earlier for other government programs, such as Commander in Chief' Display Support System, Maritime Defense Zone, and the Ocean Surveillance Information System Baseline Upgrade.

Free access — add to your briefcase to read the full text and ask questions with AI

Northrop Grumman Corp. v. United States, 47 Fed. Cl. 20, 2000 U.S. Claims LEXIS 125, 2000 WL 863025 (uscfc 2000).

47 Fed. Cl. 20 (Northrop Grumman Corp. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Shoreline Foundation, Inc.
Armed Services Board of Contract Appeals, 2026
Chugach Federal Solutions, Inc.
Armed Services Board of Contract Appeals, 2023
ACC Construction Co., Inc.
Armed Services Board of Contract Appeals, 2022
Zebel LLC v. United States
Federal Claims, 2017
Seh Ahn Lee v. United States
130 Fed. Cl. 243 (Federal Claims, 2017)
Baistar Mechanical, Inc. v. United States
128 Fed. Cl. 504 (Federal Claims, 2016)
Kenneth Earman v. United States
114 Fed. Cl. 81 (Federal Claims, 2013)
Seven Resorts, Inc. v. United States
112 Fed. Cl. 745 (Federal Claims, 2013)
P & K Contracting, Inc. v. United States
108 Fed. Cl. 380 (Federal Claims, 2012)
Ascom Hasler Mailing Systems, Inc. v. United States Postal Service
885 F. Supp. 2d 156 (District of Columbia, 2012)
Passamaquoddy Tribe v. United States
82 Fed. Cl. 256 (Federal Claims, 2008)
Pacific Gas & Electric Co. v. United States
73 Fed. Cl. 333 (Federal Claims, 2006)
Renda Marine, Inc. v. United States
71 Fed. Cl. 378 (Federal Claims, 2006)
Loving v. United States
62 M.J. 235 (Court of Appeals for the Armed Forces, 2005)