O. Ahlborg & Sons, Inc. v. United States

74 Fed. Cl. 178, 2006 U.S. Claims LEXIS 332, 2006 WL 3094054
CourtUnited States Court of Federal Claims
DecidedOctober 31, 2006
DocketNo. 02-272C
StatusPublished
Cited by12 cases

This text of 74 Fed. Cl. 178 (O. Ahlborg & Sons, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
O. Ahlborg & Sons, Inc. v. United States, 74 Fed. Cl. 178, 2006 U.S. Claims LEXIS 332, 2006 WL 3094054 (uscfc 2006).

Opinion

[180]*180OPINION

WILLIAMS, Judge.

Plaintiff, O. Ahlborg & Sons, Ine. (“Ahl-borg”), seeks $2,199,000 pursuant to an alleged implied-in-fact contract with the Maritime Administration of the United States Department of Transportation (“MARAD”). In the alternative, Plaintiff seeks to recover as a third-party beneficiary under a contract among MARAD, Massachusetts Heavy Industries, Inc. and MHI Shipbuilding, LLC.1 This matter comes before the Court on Plaintiffs Motion for Partial Summary Judgment and Defendant’s Cross-Motion to Dismiss for Lack of Subject Matter Jurisdiction or, in the Alternative, for Partial Summary Judgment.

Because Plaintiff lacks the contractual privity necessary to establish third-party beneficiary status and jurisdiction in this Court, this claim is dismissed. Because Plaintiff fails to establish an implied-in-fact contract with MARAD, the Court grants Defendant’s Motion for Partial Summary Judgment as to this claim.

Background 2

Title XI of the Merchant Marine Act of 1936, 46 App. U.S.C. § 1271 et seq., (“Title XI”) empowered MARAD to issue loan guarantees to private parties seeking private loans to renovate and rebuild shipyards. Id. Pursuant to Title XI, MARAD issued a Letter Commitment on November 1, 1996, to guarantee a loan taken by MHI up to $55,000,000 to finance the planned reactivation of the Quincy Fore River Shipyard, in Quincy and Branch, Massachusetts (“Shipyard”). Defs. Mot. Tab 1. Massachusetts Heavy Industries, Inc. was the owner of the Shipyard. Pl.’s Mot. Tab D § 1.1(b). MHI Shipbuilding, LLC leased the Shipyard from Massachusetts Heavy Industries, Ine. in order to effect the modernization and reactivation and to operate the Shipyard after it returned to commercial use. Id.

The Construction Contract Between Ahl-borg and MHI

MHI Shipbuilding, LLC entered into a construction contract (“Construction Contract”) with Ahlborg on November 24, 1997, for construction services in connection with the renovation and modernization of the Shipyard. Pl.’s Mot. Tab D at 1. MHI Shipbuilding was to lease the Shipyard from Massachusetts Heavy Industries and would be responsible for the construction of the first ships built after the Shipyard returned to commercial status. Pl.’s Mot. Tab D § 1.1. MHI contracted with Ahlborg for “the fabrication, construction and installation of a major new building and its joinder with a retained building to create the main fabrication and assembly facility for Shipbuilding.” Id. § 1.1(c). Ahlborg’s responsibilities under the Construction Contract included, inter alia: coordinating its work with MHI to ensure timely completion of the project, purchasing materials, equipment, goods, acquiring permits, and accepting responsibility for the work completed by all subcontractors. Id. §§ 1.3-1.18, 3.2, 5.1, 6.1, 7.1,16.2.

In exchange for the work performed, MHI was obligated to pay Ahlborg a total of $17,742,995. Pi’s Mot. Tab D § 4.1. Payments were to be made pursuant to procedures set out in the Construction Contract. Id. Ahlborg was required to submit an application by the tenth day of each month requesting payment for the value of the work performed since the previous payment based on the schedule of values in the Construction Contract. Id. § 5.1(b). Each application had to contain:

a certification by the Contractor as to the Work done during the month in question and ... (i) a release and waiver of liens from the Contractor and each Subcontractor for all Work performed prior to the [181]*181date of such Application for Payment ... (n) certification by the Contractor that all amounts due and owing to Subcontractors in accordance with their contracts, purchase orders and other supply arrangements have been paid in full ... (iii) such reasonable additional supporting documentation as the Operator may request in order to satisfy the requirements of the Lender.

Id. § 5.1(c). Within ten days of receiving the application, MHI was to inspect the work and provide Ahlborg with a copy of the request for payment that MHI was submitting to MARAD.3 Id. § 5.1(d). Within twenty days of receiving the application for payment, MHI was obligated to pay Ahlborg “the amount for which payment [was] sought.” Id. § 5.1(e).

MARAD was not a signatory to the Construction Contract. Id. However, MARAD participated in the negotiation process. Affidavit of Richard Lorr, dated February 4, 2004, Def.’s Mot. Tab 2 H 3. As a result, the Construction Contract included numerous provisions that gave MARAD rights. For example, Sections 1.9 and 1.11 required Ahl-borg to allow MARAD and MHI to observe, inspect, and test Plaintiffs work at any time. Pl.’s Mot. Tab D § § 1.9 and 1.11. Section 1.16 required Ahlborg to make its construction records available for MARAD’s inspection. Id. § 1.16. In addition, the Construction Contract listed MARAD’s $55,000,000 guaranty as the primary source of funding for the project. Id. § 1.1(b) (“The major portion of the financing for the Project is being provided through a bank loan of up to $55 million guaranteed by the U.S. Government under the so-called Title XI Program administered by the Maritime Administration.”). Pursuant to Section 16.6 of the Construction Contract, Ahlborg had to obtain a performance bond and a payment bond from the same bonding company. Id. § 16.6. The bonding company had to be satisfactory to both MHI and MARAD, and the bonds had to list both MHI and MARAD as obligees. Id.

The Construction Contract did not allow Ahlborg or MHI to assign the contract to a third party without consent of the other, except that MHI was allowed to “collaterally assign” its interest and obligations under the Construction Contract to MARAD as additional security. Id. § 18.1. MHI, however, remained “fully responsible” for all of its obligations and liabilities under the contract unless and until MARAD substituted another party for MHI. Id.

The Security Agreement

Fleet National Bank (“Fleet”) agreed to lend MHI up to $55 million for the reactivation of the Shipyard. Security Agreement, Pl.’s Mot. Tab A at l.4 MARAD agreed to guarantee this loan under the provisions of Title XI. Id. at 2. The Security Agreement was executed by MHI and MARAD on December 17, 1997, as part of the financial closing. Id. The Security Agreement stated that it was for the sole benefit of MHI, MARAD and their respective successors and assigns. It further specified that “no other Person shall have any right hereunder.” Id., General Provisions at 41. The purpose of the Security Agreement was “to provide security to [MARAD] for the Secretary’s Note.” Id., Special Provisions at 2. The Secretary’s Note was a promissory note to MARAD from MHI in the amount of $55 million, equal to the principal amount of the loan MARAD was guaranteeing. Id. at 7. The security interests granted to MARAD included: (i) any construction contracts relating to construction of the Shipyard; (ii) rights to any money that would become due with respect to the Shipyard assets, not including operating revenues; (iii) all goods, materials, parts, and other tangible property [182]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Greene v. United States
Federal Claims, 2023
Lea v. United States
126 Fed. Cl. 203 (Federal Claims, 2016)
Ogunniyi v. United States
124 Fed. Cl. 525 (Federal Claims, 2015)
Woodruff v. United States
122 Fed. Cl. 761 (Federal Claims, 2015)
New Hampshire Flight Procurement, LLC v. United States
118 Fed. Cl. 203 (Federal Claims, 2014)
Threshold Technologies, Inc. v. United States
117 Fed. Cl. 681 (Federal Claims, 2014)
United States Enrichment Corporation v. United States
117 Fed. Cl. 548 (Federal Claims, 2014)
G4s Technology LLC v. United States
114 Fed. Cl. 662 (Federal Claims, 2014)
Bussie v. United States
96 Fed. Cl. 89 (Federal Claims, 2011)
Arbelaez v. United States
94 Fed. Cl. 753 (Federal Claims, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
74 Fed. Cl. 178, 2006 U.S. Claims LEXIS 332, 2006 WL 3094054, Counsel Stack Legal Research, https://law.counselstack.com/opinion/o-ahlborg-sons-inc-v-united-states-uscfc-2006.