T.L. Roof & Associates Construction Co. v. United States

38 Cont. Cas. Fed. 76,534, 28 Fed. Cl. 572, 1993 U.S. Claims LEXIS 81, 1993 WL 238858
CourtUnited States Court of Federal Claims
DecidedJuly 1, 1993
DocketNo. 90-538C
StatusPublished
Cited by12 cases

This text of 38 Cont. Cas. Fed. 76,534 (T.L. Roof & Associates Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
T.L. Roof & Associates Construction Co. v. United States, 38 Cont. Cas. Fed. 76,534, 28 Fed. Cl. 572, 1993 U.S. Claims LEXIS 81, 1993 WL 238858 (uscfc 1993).

Opinion

OPINION

ANDEWELT, Judge.

In this government contract action filed pursuant to the Contract Disputes Act, 41 U.S.C. § 601 et seq. (CDA), plaintiff, T.L. Roof & Associates Construction Company (T.L. Roof), contracted with the United [574]*574States Army Corps of Engineers (the Corps) to construct a two-story Communications Equipment Facility (CEF) at Fort Huachuca, Arizona. Originally, the date for contract completion was April 5, 1989, but as a result of a series of delays and contract modifications, the project was not completed until October 1989. On March 3, 1989, plaintiff filed a claim with the contracting officer seeking recovery of plaintiff’s costs related to the delay in completing the contract work and to the purchase of material for the “raised-floor system” in the “tempest” area of the CEF. On April 6, 1990, plaintiff submitted a revised claim to the contracting officer. John B. Sneed, one of plaintiff’s two area vice presidents, signed and certified both claims. The contracting officer did not issue a final decision on the revised claim within the time periods set forth in 41 U.S.C. § 605(c), and thus, as authorized thereunder, plaintiff filed the instant action on June 15, 1990. In its complaint, plaintiff seeks an estimated $1.6 million plus interest to cover “delay and disruption damages” that resulted from alleged “acts and omissions” by defendant.

Plaintiff filed a motion for partial summary judgment and defendant responded with a motion to dismiss for lack of jurisdiction or, in the alternative, for partial summary judgment. After oral argument, the court ruled from the bench on certain issues and in a December 15, 1992, order, stated certain of the court’s conclusions. Herein, the court provides some amplification of its prior conclusions and resolves the remaining issues presented in the parties’ motions.1

I.

Under the CDA, this court lacks subject matter jurisdiction over a government contractor’s claim in excess of $50,-000 if the contractor failed to submit a properly certified claim to the contracting officer before seeking relief in this court. Ball, Ball & Brosamer, Inc. v. United States, 878 F.2d 1426, 1428 (Fed.Cir.1989).2 In its motion to dismiss, defendant contends that plaintiff did not submit a properly certified claim to the contracting officer because Sneed was not qualified to certify the claim under the controlling regulation, Federal Acquisition Regulation (FAR) 33.-207(c)(2), 48 C.F.R. § 33.207. FAR 33.-207(c)(2) provides, in pertinent part:

If the contractor is not an individual, the certification shall be executed by—

(i) A senior company official in charge at the contractor’s plant or location involved; or
(ii) An officer or general partner of the contractor having overall responsibility for the conduct of the contractor’s affairs.

Plaintiff contends that Sneed satisfies the requirements of FAR 33.207(c)(2)(i). Defendant acknowledges that Sneed was “[a] senior company official” with T.L. Roof, but argues that Sneed was not “in charge at the contractor’s plant or location involved.”

In United States v. Grumman Aerospace Corp., 927 F.2d 575 (Fed.Cir.1991), cert. denied, — U.S. —, 112 S.Ct. 330, 116 L.Ed.2d 270 (1991), the Court of Appeals for the Federal Circuit interpreted FAR 33.207(c)(2)(i) as requiring a certifying [575]*575senior company official to satisfy two requirements. The “certifying senior company official [must] have ... primary responsibility for the execution of the contract” and the official must have “a physical presence at the location of the primary contract activity.” Id. at 580. This court concludes that Sneed satisfies both of these requirements.

First, the evidence submitted by the parties, including deposition testimony, establishes that Sneed had primary authority and responsibility within T.L. Roof for execution of the CEF contract. For example, Sneed had authority to execute subcontracts with no dollar limitation, submit and present claims to the contracting officer, and enter contract modifications. Lance Alley, the CEF project manager, did much of the day-to-day work at the construction site (i.e., negotiated (but did not sign) certain of the modification agreements and prepared initial drafts (but did not sign) the two claims submitted to the contracting officer). Alley, however, was not a senior company official, was supervised by Sneed, and needed Sneed’s authorization before taking various actions, including submitting a claim to the contracting officer. Sneed exercised his responsibility of managing the CEF contract by supervising Alley both at the job site and in frequent conversations over the telephone.3 Viewed in its entirety, the evidence submitted supports a conclusion that Sneed had primary responsibility for the execution of the contract.

Second, Sneed also had “a physical presence at the location of the primary contract activity.” Between July 1987 and October 1989, Sneed visited the contract site approximately 40-50 times for an estimated two to three hours each visit. Defendant contends that this amount of time is insufficient to constitute the required “physical presence.” There is, however, no requirement in FAR 33.207(c)(2)(i) that the senior official be permanently located at the contract site. Sun Cal. Inc. v. United States, 21 Cl.Ct. 31, 34 (1990). FAR 33.207(e)(2)(i) merely requires that the senior official be “in charge at the contractor’s plant or location involved.” Sneed’s physical presence at the contract site was well beyond de minimis, and he was physically at the contract site with sufficient frequency and regularity to be “in charge” at the site.

Requiring an official certifying a claim to have a greater physical presence at the contract site would significantly restrict the options available to certain contractors. FAR 33.207(c)(2) generally seeks to provide a contractor with an option to have either of two classes of corporate officials certify the contractor’s claims — either the senior company official in charge at the location of primary contract activity, or an officer or general partner with “overall responsibility for the conduct of the contractor’s affairs.” In certain industries, such as the construction industry involved herein, individuals who can be categorized as senior company officials typically will not be located on a permanent or near-permanent basis at the location of primary contract activity. Therefore, for such industries, interpreting FAR 33.207(c)(2)(i) to require a near-permanent presence at the job site typically would eliminate one of the two certification options and thereby effectively require that the officer or general partner with “overall responsibility for the conduct of the contractor’s affairs” certify each and every claim over $50,000.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Yul Lim Construction Co., Ltd.
Armed Services Board of Contract Appeals, 2025
River Ridge Development Authority
Armed Services Board of Contract Appeals, 2016
Axion Corp. v. United States
68 Fed. Cl. 468 (Federal Claims, 2005)
Jackson Construction Co. v. United States
62 Fed. Cl. 84 (Federal Claims, 2004)
CEMS, Inc. v. United States
59 Fed. Cl. 168 (Federal Claims, 2003)
PCL Construction Services, Inc. v. United States
47 Fed. Cl. 745 (Federal Claims, 2000)
M.A. Mortenson Co. v. United States
42 Cont. Cas. Fed. 77,264 (Federal Claims, 1998)
Neal & Co. v. United States
41 Cont. Cas. Fed. 77,003 (Federal Claims, 1996)
C & H Commercial Contractors, Inc. v. United States
35 Fed. Cl. 246 (Federal Claims, 1996)
Ehlers-Noll, GMBH v. United States
40 Cont. Cas. Fed. 76,874 (Federal Claims, 1995)
McLain Plumbing & Electrical Service, Inc. v. United States
39 Cont. Cas. Fed. 76,593 (Federal Claims, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
38 Cont. Cas. Fed. 76,534, 28 Fed. Cl. 572, 1993 U.S. Claims LEXIS 81, 1993 WL 238858, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tl-roof-associates-construction-co-v-united-states-uscfc-1993.