Neal & Co. v. United States

41 Cont. Cas. Fed. 77,003, 36 Fed. Cl. 600, 1996 U.S. Claims LEXIS 174, 1996 WL 558314
CourtUnited States Court of Federal Claims
DecidedSeptember 30, 1996
DocketNo. 93-277C
StatusPublished
Cited by32 cases

This text of 41 Cont. Cas. Fed. 77,003 (Neal & Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Neal & Co. v. United States, 41 Cont. Cas. Fed. 77,003, 36 Fed. Cl. 600, 1996 U.S. Claims LEXIS 174, 1996 WL 558314 (uscfc 1996).

Opinion

OPINION

BRUGGINK, Judge.

This dispute arises out of a construction contract between plaintiff, Neal & Company, Inc. (NCI), and the United States, acting through the United States Coast Guard (CG). The matter is before the court after trial on the contractor’s claim for an equitable adjustment and the recovery of monies withheld by the CG, as well as the CG’s counterclaims based upon allegations of incomplete work. The contract was for the construction of a housing subdivision for personnel stationed at the United States Coast Guard base on Kodiak Island, Alaska. NCI brings this appeal pursuant to 41 U.S.C. § 609(a)(1) (1994) from the Contracting Officer’s (CO) final decision denying its request for relief. After a three week trial on plaintiffs claims, a separate three day trial addressing the Government’s counterclaims, post-trial briefing, and oral argument the court finds that the plain[605]*605tiff partially prevails on a portion of its claims, and that the defendant has failed to establish its counterclaims.

GENERAL FACTUAL BACKGROUND

During 1987 the United States Coast Guard began planning the Lake Louise Housing Project, which is phases 7 and 8 of the CG base housing on Kodiak Island, Alaska (“the project”). The project was for the construction of a subdivision consisting of thirty individual units on a hill overlooking Lake Louise. The project required the demolition of several abandoned houses and an existing roadway, excavation into the side of the hill to make room for the construction of two rows of houses on either side of a new central road, as well as installation of sewer and electrical systems, bus shelters, and a children’s play area.

The project was designed by the CG Facilities Design and Construction Center (FD & CC), located in Seattle, Washington. The CG retained Roger P. Kinney of RPK Associates to perform a geotechnical1 evaluation of the proposed site and Colleen K. Thorpe Associates to provide a concept landscape site plan. The initial geotechnical evaluation (hereafter “the Kinney Report”) was submitted to the CG in October of 1987.2 The report was used, at least in part, to design the project.

Although a geotechnical evaluation is normally conducted during the very early stages of design work, the evaluation on this project was not done until the design was 90% complete. During trial, the court heard from plaintiff’s expert, M.T. Davisson, a civil engineer specializing in geotechnical and structural engineering. According to Davisson, the geotechnical evaluation should have been conducted earlier in the project’s development in order to provide the CG with a greater variety of options, as well as to allow changes to be more readily incorporated. Fred Brown,3 a geotechnical expert retained by defendant, also stated that a geotechnical analysis should be performed in the 30% completion range, and that because the analysis was conducted “near the end of their design, ... they didn’t want to make major changes.” Trial Transcript (“Trial Tr.”) at 162-63. Fred Brown, in reference to his geotechnical evaluation of slope stability, admitted that “[t]his was a very fast project. [The CG] gave me twenty days to do it.” Id. at 187.

The Kinney Report indicated some problems with the site. A large amount of fill material had been placed in a ravine when the site had been developed on an earlier occasion. The report concluded that the fill would not properly support the proposed residential construction. As a result, the Kinney Report suggested several alternatives:

(1) removing and replacing the existing fill;

(2) removing the fill and recontouring the area to compensate for its removal; (3) avoiding the specific areas of excessive fill; or (4) relocating the entire project.

The CG elected not to remove the fill and replace it with more suitable sods. Instead, a “key buttress” was designed by Shannon & Wilson and installed by NCI at the bottom of the slope.4 Although the buttress did rectify [606]*606the unstable condition of the slope, the unre-moved fill was also unsuitable as the base for construction with the result that construction later involved a large amount of “overexcavation.”

The solicitation was sent to prospective bidders on February 4, 1988. Tony Neal, NCI’s president, supervised preparation of the company’s bid.5 The CG issued seven amendments to the solicitation specifications. Bids were submitted on April 7, 1988. NCI was the lowest bidder on the base contract, as well as all the additive work. NCI’s total bid was $8,141,947. After NCI confirmed its bid, an award letter was sent on May 16, 1988. A partial notice to proceed was given on June 1,1988, and NCI began work immediately. The initial completion date of the project was August 3, 1989. This was extended early during construction to November 14,1989.6

NCI’s construction plan for this project was similar to that of an assembly line, except the thirty housing units were stationary and the workers were to move along the two rows of houses. As originally intended, the different trades would follow behind each other from one house to the next, from unit one to thirty, in the order in which the work needed to be done within each unit. In other words, first the foundation was to be laid on unit one, and while that crew moved on to lay the foundation for unit two, the rough framing crew would put up the frame for unit one. Behind rough framing would come roofing, then rough-in electrical and plumbing, then dry wall, and so on. This was possible because the housing units were similar in design, allowing for repetitive tasks.

The contract required the contractor to submit for approval a Network Analysis Schedule (NAS) utilizing the critical path method (CPM).7 Under this contract, as well as established case law, the approved NAS/ CPM schedule is the tool used to monitor performance throughout the construction process and to determine scheduling delay. NCI had difficulty in obtaining the necessary CG approval. After several iterations and corrections by both the CG and NCI personnel, the NAS was finally approved by the CG approximately five weeks after NCI started working on-site, on July 6, 1988. The NAS continued to cause problems however. According to NCI, the CG was unreasonable in its demands regarding the use of the NAS throughout the project. NCI claims that CG personnel required too many updates to the NAS schedule and that this caused delay to the project. According to NCI, the CG unreasonably withheld the payment of funds because NCI had not provided an updated NAS. The CG responds that NCI faded to meet the contract requirements regarding the continuous updating of the NAS, and that any problems NCI encountered with the use [607]*607of its NAS as a scheduling and billing tool were the result of NCI’s own mistakes.

It is clear that the approved schedule contained severe deficiencies. The schedule did not contain manpower limitations, or “crew constraints,” resulting in an unrealistic schedule.8 As the Government’s scheduling expert, Charles Adkins, testified, the lack of crew constraints resulted in the assumption that all the units could be done near the end of the project.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Meltech Corporation, Inc.
Armed Services Board of Contract Appeals, 2025
Skanska USA Civil Southeast, Inc.
Armed Services Board of Contract Appeals, 2025
New York v. United Parcel Service, Inc.
160 F. Supp. 3d 629 (S.D. New York, 2016)
Meridian Engineering Company v. United States
122 Fed. Cl. 381 (Federal Claims, 2015)
Optimum Services, Inc.
Armed Services Board of Contract Appeals, 2015
Delhur Industries, Inc. v. United States
95 Fed. Cl. 446 (Federal Claims, 2010)
North Star Alaska Housing Corp. v. United States
76 Fed. Cl. 158 (Federal Claims, 2007)
Southern Comfort Builders, Inc. v. United States
67 Fed. Cl. 124 (Federal Claims, 2005)
Renda Marine, Inc. v. United States
66 Fed. Cl. 639 (Federal Claims, 2005)
George Sollitt Construction Co. v. United States
64 Fed. Cl. 229 (Federal Claims, 2005)
CEMS, Inc. v. United States
59 Fed. Cl. 168 (Federal Claims, 2003)
Manuel Bros. v. United States
55 Fed. Cl. 8 (Federal Claims, 2002)
Transfair International, Inc. v. United States
54 Fed. Cl. 78 (Federal Claims, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
41 Cont. Cas. Fed. 77,003, 36 Fed. Cl. 600, 1996 U.S. Claims LEXIS 174, 1996 WL 558314, Counsel Stack Legal Research, https://law.counselstack.com/opinion/neal-co-v-united-states-uscfc-1996.