Meridian Engineering Company v. United States

122 Fed. Cl. 381, 2015 U.S. Claims LEXIS 905, 2015 WL 4481247
CourtUnited States Court of Federal Claims
DecidedJuly 22, 2015
Docket11-492 C
StatusPublished
Cited by7 cases

This text of 122 Fed. Cl. 381 (Meridian Engineering Company v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Meridian Engineering Company v. United States, 122 Fed. Cl. 381, 2015 U.S. Claims LEXIS 905, 2015 WL 4481247 (uscfc 2015).

Opinion

Breach of Contract; Cardinal Change; Contract Disputes Act, 41 U.S.C. §§ 601-613; Duty of Good Faith and Fair Dealing; Federal Acquisition Regulations: 31.205-33 (“Professional and Consultant Service Costs”); 52.211-10 (“Commencement, Prosecution, and Completion of Work”); 52.233-1 (“Disputes”); 52.236-2 (“Differing Site Conditions”); 52.242-14 (“Suspension of Work”); 52.243-4 (“Changes”); 52.248-3 (“Value Engineering — Construction”).

MEMORANDUM OPÍNION AND FINAL ORDER

BRADEN, Judge.

Meridian Engineering Company (“Meridian”) is an engineering and construction firm in Tucson, Arizona, specializing in heavy civil, structural, and industrial construction. On September 21, 2007, the Army Corps of Engineers (“USAGE,” “Army Corps,” or “Corps”) awarded Meridian a $5.8 million contract to complete a flood control project in Nogales, Arizona including demolition, excavation, and construction.

After work at that site commenced, numerous problems arose and, on July 29, 2011, Meridian filed a Complaint in the United States Coui’t of Federal Claims alleging a breach of contract seeking damages of $7.6 million. After trial, Meridian filed an Amended and Second Amended Complaint, adding a new breach of contract claim and a claim for the breach of the duty of good faith and fair dealing.

To facilitate review of this Memorandum Opinion And Final Order, the court has provided the following outline:

I. RELEVANT FACTUAL BACKGROUND.

A. In 2007, The United States Army Corps Of Engineers Awarded Plaintiff A Contract To Construct The Chula Vista Project.

B. On January 9, 2008, Construction Commenced.

C. In July 2008, The “Monsoon Season” Began.

D. In October 2008, Structural Failures Impacted The Union Pacific Railroad Track And Construction Was Suspended.

E. In March 2009, The United States Army Corps Of Engineers Began To Scale Back The Chula Vista Project.

II. PROCEDURAL HISTORY.

III. DISCUSSION.

A. Jurisdiction.

B. Contract Disputes Act.

C. Standing.

D. Standard Of Review.

E. Whether Plaintiff Is Entitled To Damages For The Breach Of Contract Claims Alleged In The May 19, 2014 Second Amended Complaint.

1. Whether Plaintiff Is Entitled To Recover Costs To Protect Its Workers From Hazardous Conditions (Count 1).

a. Plaintiffs Argument.

b. The Government’s Response.

c. The Court’s Resolution.

2. Whether Meridian Is Entitled To Costs For Differing Site Conditions *385 In The Channel And At The Sewer Line (Counts 2 and 5).

. a. Plaintiffs Argument.

c. v The Court’s Resolution.

3. Whether Plaintiff Is Entitled To Recover Costs Incurred Because Of The Railroad Right-Of-Way Delay (Count 3).

4. Whether Plaintiff Is Entitled To Recover Costs For Delays Incurred As A Result Of Flood Events (Count 4).

5. Whether Plaintiff Is Entitled To An Adjustment For The Unpaid Contract Quantities (Count 6).

a.' Plaintiffs Argument.

6. Whether Plaintiff Is Entitled To Costs For The To Suspension Of Work (Count 7), Channel Fill (Count 8), And Interim Protection (Count 9).

7. Whether Plaintiff Is Entitled To Costs Regarding The Punchlist (Count 10).

C; The Court’s Resolution.

8. Whether Plaintiff Is Entitled To Recover Costs For The North Bridge VECP (Count 11).

c.The Court’s Resolution.

F. Whether Plaintiff Is Entitled To Recover Preparation Costs For A Request For Equitable Adjustment (Count 12).

G. Whether The Government Violated The Duty Of Good Faith And Fair Dealing (Count 14).

1. Plaintiffs Argument.
2. The Government’s Response.
3. The Court’s Resolution.

IV. CONCLUSION.

I. RELEVANT FACTUAL BACKGROUND. 1

A. In 2007, The United States Army Corps Of Engineers Awarded Plaintiff A Contract To Construct The Chula Vista Project.

In April 1994, the USACE issued a Design Memorandum for a flood control .project in Nogales, Arizona, known as the Chula Vista Pi’oject (“Project”). JX1. In 2004, Congress approved funding for the Project and, on August 22, 2007, the USACE issued a request for proposal. JX17-1.

On May 29, 2007, the USACE issued IFB No. W912PL-07-B-0005 (“Solicitation”). JX2. Next, the USACE solicited bids for a firm fixed-price contract and requested prices for a base bid and three separate options. JX2. These options included: Section 2300(a) concerning earthwork (JX2-339); Section 2130 concerning the standards for dewatering (JX7; JX2-329); and Section 1355 concerning environmental protection issues (JX5-11).

*386 On September 21, 2007, the USACE awarded Contract No. W912PL-07-C-0025 (“Contract”) to Meridian. JX193-1. The Contract was for a “base bid,” but included “options” for potential cost increases and anticipated time extensions. JX193. A map of the Project’s work site, Court Exhibit D, follows.

Court Exhibit D

[[Image here]]

PX375 (Pl. Dem. Ex. B).

On October 27, 2007, Meridian requested electronic copies of drawings and survey files from the USACE, but did not receive them. JX110-3.

On November 13, 2007, the USACE issued a Notice to Proceed. DX15-1; PX386. On the following day, Meridian and the USACE attended 'a preconstruction conference where Meridian was advised that only the contracting officer (“CO”) and the administrative contracting officer were authorized to “commit any money for the [Government.” DX726-3. The USACE also advised Meridian that there may be chromium, a heavy metal, at the Chula Vista site, but more information would be forthcoming. DX726-5,13; PX133. Meridian again asked the USACE to provide the requested electronic drawing and survey files. DX726-4; PX3-4.

By November 19, 2007, Meridian planned to begin staking 2 the site. PX3-3; DX726-3. But, the USACE failed to 'deliver the required surety files by that date. PX134. Nevertheless, Meridian agreed to begin “de-watering and.mobilization.” PX3-3; DX726-3.

On November 26, 2007, Meridian submitted a Water Diversion Plan for the Project that the USACE approved the next day. JX51-1-8.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Meridian Engineering Company v. United States
885 F.3d 1351 (Federal Circuit, 2018)
Meridian Engineering Company v. United States
130 Fed. Cl. 147 (Federal Claims, 2016)
East Coast Repair & Fabrication, LLC v. United States
199 F. Supp. 3d 1006 (E.D. Virginia, 2016)
Horn & Associates, Inc. v. United States
123 Fed. Cl. 728 (Federal Claims, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
122 Fed. Cl. 381, 2015 U.S. Claims LEXIS 905, 2015 WL 4481247, Counsel Stack Legal Research, https://law.counselstack.com/opinion/meridian-engineering-company-v-united-states-uscfc-2015.