Herman Adams, Doing Business as Adams Manufacturing Company v. The United States

358 F.2d 986, 175 Ct. Cl. 288, 1966 U.S. Ct. Cl. LEXIS 211
CourtUnited States Court of Claims
DecidedApril 15, 1966
DocketCong. 5-59
StatusPublished
Cited by41 cases

This text of 358 F.2d 986 (Herman Adams, Doing Business as Adams Manufacturing Company v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Herman Adams, Doing Business as Adams Manufacturing Company v. The United States, 358 F.2d 986, 175 Ct. Cl. 288, 1966 U.S. Ct. Cl. LEXIS 211 (cc 1966).

Opinion

PER CURIAM: *

This is a suit for direct or primary loss in the amount of $172,081.92 caused by delays which occurred in the performance of a contract to produce a large number of wood tent pins for defendant. A claim for so-called “indirect loss” or secondary loss in the amount of $43,061.91 is not deemed to be supported by substantial evidence (and is no longer pressed by plaintiff). Extensive delay is attributed by plaintiff to the arbitrary and unreasonable action of an employee of defendant, Inspector Joseph C. Burkhart, in rejecting as many as 50 per cent of the tent pins produced by plaintiff under his inspection. There is also involved the withholding of information by defendant or failure of Inspector Burkhart to furnish plaintiff with the inspection plan which was used and the Acceptable Quality Level (AQL) required by defendant in performance of the contract. When Inspector Burkhart was replaced by another inspector (Kallen) the percentage of discarded or rejected pins was decreased from over 50 per cent under Inspector Burkhart to about 20 per cent or lower under Inspector Kallen. Although plaintiff did not exhaust his administrative remedies or file a formal complaint concerning the inspection of pins by Inspector Burkhart, he did make complaint and discuss his problems with Burkhart and Burkhart’s supervisor.

By H.Res. 296, 86th Congress, 1st Sess., the House of Representatives has asked the court, pursuant to 28 U.S.C. §§ 1492 and 2509, for a report as to whether plaintiff is legally or equitably entitled to any damages in connection with a contract which he had with the defendant to manufacture tent pins. 1

In response to a request for proposals issued by the Chicago, Illinois, Quartermaster Corps on November 14, 1953, plaintiff submitted a proposal to furnish quantities of 16-inch and 24-inch tent pins for a consideration of $103,177.26, f. o. b. certain destination points. Plaintiff initially computed his net direct material costs at $24,320.46, later increased to $50,140.

Upon opening the bids, defendant’s contracting officer noted that plaintiff’s material cost allocation was substantially *989 lower than the second lowest bidder. A few weeks later a representative of the Chicago Quartermaster advised plaintiff’s plant manager that his bid figures were too low and asked him to recheck them. Subsequently, when a representative of the Quartermaster visited the plant to conduct a pre-award survey, he reminded plaintiff that in his bid he neglected to allow for the cost of manufacturing and shipping crates, and for a rejection factor.

After the pre-award survey was conducted, plaintiff was invited to Chicago to attend a conference to discuss the proposal of November 16, 1953. Prior to the meeting, plaintiff submitted to defendant an informal proposal which amended the initial- proposal by allowing a 20 per cent rejection factor. This increased the bid price on f. o. b.-plant to $103,117.26.

Subsequently, in a conference held on December 18, 1953, defendant’s spokesman advised plaintiff’s representative that their second informal proposal was too high, and as a consequence, the informal proposal was revised downward to a figure of $90,000 f. o. b.-plant. The difference between the second proposal and the one arrived at during the meeting was determined by reducing the rejection factor from 20 per cent to 10 per cent, and making other minor adjustments.

Various other matters pertaining to the contract were discussed. Plaintiff’s representative advised defendant that he anticipated buying mill run lumber and screening from it the No. 1 and No. 2 red oak for use in producing the pins. Plaintiff’s representative attempted to ascertain what inspection procedure would be used. He was told that he would subsequently receive an inspection guide. The guide which was eventually furnished plaintiff covered inspections with respect to quartermaster contracts in general, but did not specifically refer to the procedure to be used in inspecting tent pins.

On the day following the conference, plaintiff submitted a formal bid in the amount of $123,391.51 f. o. b. certain destinations. In the revised formal bid plaintiff increased his materials cost from $24,320.46 to $50,140 while reducing his labor costs from $35,165.63 to $25,200. After making other minor adjustments and adding a 10 per cent profit factor plaintiff’s f. o. b.-plant price amounted to $90,791.17. Plaintiff also increased his delivery costs from $30,215.86 to $52,600.-34.

On December 10, 1953, Contract QM-23755 was awarded to plaintiff. For a consideration of $123,391.51 plaintiff agreed to manufacture and deliver 606,-525 type I 16-ineh wood tent pins and 763,000 type II 24-inch wood tent pins. The contract also contained the usual provisions entitled “Changes”, “Inspections” and “Disputes.” Pins were to be produced in accordance with Military Specifications MÍ1-P-2383A. In addition to delineating the contract specifications, MÜ-P-2383A provided that sampling and inspection would be conducted in accordance with Standard MIL-STD-105A. In determining whether pins were to be accepted by the defendant, MIL-STD-105 A provided for inspection of a certain number of samples based upon the lot size submitted. If the sample contained more than the minimum number of major and minor defective pins, the entire lot was to be rejected. The maximum number of defects which were to be allowed was determined by the Acceptable Quality Level (hereafter called AQL), established by defendant and thus would vary with changes in the AQL. The AQL for contract No. QM-23755 was specified by the defendant, but defendant never revealed to plaintiff the particular AQL established for this contract. Plaintiff insists that the failure of defendant to furnish plaintiff with the AQL it was using constituted a breach of contract. Plaintiff accordingly claims that he is entitled to relief because defendant omitted a specification of the contract! Plaintiff’s contractual obligation was to produce pins according to certain specifications. All details specifying the kind of pins that were to be manufactured were set out in MÜ-P-2383A referred to in the contract. *990 AQL is used to determine whether a sufficient number of defects (as defined in MÜ-P-2383A) are found in the sample group of pins to warrant rejection of the entire lot. Since plaintiff was not advised of the AQL applicable, plaintiff could not anticipate in advance the number of defective pins he could produce without having an entire lot rejected. Inspector Burkhart never told plaintiff the number of major and minor defects which would be allowed in a sample size lot. Although plaintiff was prejudiced by lack of certain information known to defendant, he still had the basic duty under the contract to produce pins free from those defects prohibited by the specifications (MÍ1-P-2383A).

Plaintiff set up an assembly line whereby raw lumber which had been stored in a yard was put through a rip saw which cut it into rough strips. From there it went through the molder which planed it to the proper width and thickness.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Meridian Engineering Company v. United States
122 Fed. Cl. 381 (Federal Claims, 2015)
Jenkins v. United States
101 Fed. Cl. 122 (Federal Claims, 2011)
Cencast Services, L.P. v. United States
94 Fed. Cl. 425 (Federal Claims, 2010)
Buser v. United States
85 Fed. Cl. 248 (Federal Claims, 2009)
Intersport Fashions West, Inc. v. United States
84 Fed. Cl. 454 (Federal Claims, 2008)
United States v. Cowan
535 F. Supp. 2d 1135 (D. Hawaii, 2008)
North Star Alaska Housing Corp. v. United States
76 Fed. Cl. 158 (Federal Claims, 2007)
H & S Manufacturing, Inc. v. United States
66 Fed. Cl. 301 (Federal Claims, 2005)
Cook v. United States
52 Fed. Cl. 62 (Federal Claims, 2002)
Fisher v. United States
61 F. Supp. 2d 621 (E.D. Michigan, 1999)
INSLAW, Inc. v. United States
41 Cont. Cas. Fed. 76,979 (Federal Claims, 1996)
Simmons v. United States
29 Fed. Cl. 136 (Federal Claims, 1993)
Levitsky v. United States
27 Fed. Cl. 235 (Federal Claims, 1992)
Whiteside v. United States
26 Cl. Ct. 564 (Court of Claims, 1992)
C.B.C. Enterprises, Inc. v. United States
24 Cl. Ct. 1 (Court of Claims, 1991)
Paul v. United States
20 Cl. Ct. 236 (Court of Claims, 1990)
Servidone Construction Corp. v. United States
36 Cont. Cas. Fed. 75,797 (Court of Claims, 1990)
United States v. Cope
680 F. Supp. 912 (W.D. Kentucky, 1987)
Pototzky v. United States
8 Cl. Ct. 308 (Court of Claims, 1985)
California Canners & Growers Ass'n v. United States
7 Cl. Ct. 69 (Court of Claims, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
358 F.2d 986, 175 Ct. Cl. 288, 1966 U.S. Ct. Cl. LEXIS 211, Counsel Stack Legal Research, https://law.counselstack.com/opinion/herman-adams-doing-business-as-adams-manufacturing-company-v-the-united-cc-1966.