Jefferson Construction Co. v. United States

168 Ct. Cl. 648, 1964 U.S. Ct. Cl. LEXIS 182, 1964 WL 8576
CourtUnited States Court of Claims
DecidedDecember 11, 1964
DocketCong. No. 1-62
StatusPublished
Cited by3 cases

This text of 168 Ct. Cl. 648 (Jefferson Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jefferson Construction Co. v. United States, 168 Ct. Cl. 648, 1964 U.S. Ct. Cl. LEXIS 182, 1964 WL 8576 (cc 1964).

Opinion

Per Curiam:

Plaintiff, a Massachusetts Corporation, brought this suit pursuant to House Resolution No. 423, 87th Congress, 1st Sess. (1962), which referred H.R. 8585 (a bill for plaintiff’s relief) to this court in accordance with 28 U.S.C. §§ 1492 and 2509.1

Plaintiff, a construction company, was the successful bidder on Contract No. DA-19-016-ENG-5926, dated May 31, 1958. This contract was for the construction of family housing, site work and utilities, at the Otis Air Force Base, Falmouth, Massachusetts. The project covered an area of. approximately 200 acres and consisted of 175 buildings, 72 of which were single family units and 416 row-type units, for a total of 488 housing units. Included in the project were new roads, walks, driveways, carports, and electrical and water distribution systems, and landscaping. During the course of the performance under the contract, directives were issued by the contracting officer requiring that plaintiff perform certain work which the contracting officer considered to be within the terms of the contract but which plaintiff regarded as being beyond the contract requirements. Administrative proceedings were instituted and subsequently suspended when, in the view of the parties, neither the Corps of Engineers Board of Contract Appeals nor the contracting officer had funds available to make payment to the plaintiff. [650]*650The parties thereupon entered into a stipulation, providing, in part, that the Government, while admitting the 10 claims of the plaintiff had merit, did not agree to the dollar amount of the claims. At the trial in this court, the parties stipulated that the amount due plaintiff, in the event there is an equitable right to recover, is the sum of $110,000.

The case is before the court, having been submitted on a report of the trial commissioner, to which defendant filed exceptions, the briefs of the parties, and oral argument of counsel. It is concluded that plaintiff is entitled to recover on its equitable claim in the amount of $110,000 in accordance with the stipulation entered into by the parties.

Defendant’s motion to dismiss for lack of jurisdiction, filed July 14,1964, is denied.

This opinion and the findings of fact incorporated herein will be certified by the Clerk to the House of Representatives pursuant to H.R. No. 423, 87th Congress, 1st Session.

EINDINGS OK FACT

The court, having considered the evidence, the report of Trial Commissioner Herbert N. Maletz, and the briefs and argument of counsel, makes findings of facts as follows:

1. Plaintiff is a corporation duly organized and existing under the laws of the Commonwealth of Massachusetts with its principal office in Cambridge, Massachusetts. It is engaged in general contracting work and has been in that business for about 47 years.

2. (a) This matter was referred to the court by House Resolution 428 which was agreed to by the U.S. Plouse of Representatives on June 5,1962. That Resolution provided:

Resolved, That the bill (H.R. 8585) entitled “A bill for the relief of Jefferson Construction Company”, together with all accompanying papers, is hereby referred to the Court of Claims subject to its rules and pursuant to sections 1492 and 2509 of title 28, United States Code; and the court shall proceed expeditiously with the same and report to the House, at the earliest practicable date, such findings of fact, including facts relating to delay or laches, facts bearing upon the question whether the [651]*651bar or any statute of limitations should be removed, or facts claimed to excuse the claimant for not having resorted to any established legal remedy, and conclusions based on such facts as shall be sufficient to inform Congress whether the demand is a legal or equitable claim or a gratuity, and the amount, if any, legally or equitably due from the United States to the claimant.

(b) The referred bill (H.R. 8585, 87th Congress, 1st Session) provided in part:

A BILL
For the relief of the Jefferson Construction Company.
Be it enacted by the Senate and House of Representatives of the United States of America in Congress assembled, That the Secretary of the Treasury is authorized and directed to pay, out of any money in the Treasury not otherwise appropriated, to the Jefferson Construction Company, of Cambridge, Massachusetts, the sum of $160,166. The payment of such sum shall be in full settlement of all claims of the said Jefferson Construction Company against the United States arising out of extra work orders involving removal and replacement of clapboards, removing and replacing twisted and bowed framing members, installing pressure treated two-by-four blocking at party walls, furnishing and installing two-inch-wide joint reinforcing in cavity block walls, lack of partial access to site due to barricades placed in road, work required to be done because of direction to use and countersink fivepenny box nails, installing construction joints in the foundations of ninety-one row house buildings, filling nail depressions in sheetrock, raising floor girts and installing shims and quarter-inch-round shoe molding, covering beams and boxing in heating pipes, made oy the contracting officer, Corps of Engineers, Department of the Army, in the course of performance by the said Jefferson Construction Company of contract numbered DA-19-016-ENC-5926, dated May 31, 1958, for the construction of family housing units site-work and utilities at Otis Air Force Base, Falmouth, Massachusetts, for which payment has not been made because sufficient funds are not available therefor to the Department of the Army: * * *

3. Plaintiff filed its petition in this court under the above reference on June 27,1962.

[652]*6524. On April 29,1958, the Army Corps of Engineers issued invitations for 'bids for the construction of family housing, site work and utilities at the Otis Air Force Base, Falmouth, Massachusetts. The project covered an area 'of approximately 200 acres and consisted of 175 buildings, 72 of which were single family units and 416 row-type units, for a total of 488 housing units. Included in the project were new roads, walks, driveways, carports, an electrical and water distribution system, and landscaping.

5. Plaintiff was the successful bidder and was awarded Contract No. DA-19-016-ENG-5926, dated May 31, 1958, for an original total estimated amount of $8,484,377, which was increased to $8,801,908.90 by 57 contract modifications that were made by the Corps of Engineers.

6. (a) Section 606 of the Department of Defense Appropriation Act, 1958, approved August 2, 1957 (71 Stat. 312, 323), provided as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Paul v. United States
20 Cl. Ct. 236 (Court of Claims, 1990)
Aurex Corp. v. United States
175 Ct. Cl. 1 (Court of Claims, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
168 Ct. Cl. 648, 1964 U.S. Ct. Cl. LEXIS 182, 1964 WL 8576, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jefferson-construction-co-v-united-states-cc-1964.