INSLAW, Inc. v. United States

41 Cont. Cas. Fed. 76,979, 35 Fed. Cl. 295, 1996 U.S. Claims LEXIS 48, 1996 WL 144373
United States Court of Federal Claims·Decided March 29, 1996·No. No. 95-338X·Published·Cited by 25 cases

Opinion

OPINION

MILLER, Judge.

This congressional reference is before the court on defendant’s motion in limine, or alternatively, for partial summary judgment on the contractual data rights issue. Argument is deemed unnecessary. This case was [298] assigned to the court pursuant to 28 U.S.C. § 1492 (1994), which provides: “Any bill, except a bill for a pension, may be referred by either House of Congress to the chief judge of the United States Court of Federal Claims for a report in conformity with section 2509 of this title.” Section 2509(e) charges the court to proceed “in accordance with the applicable rules to determine the facts____ [The court] shall append to [its] findings of fact conclusions sufficient to inform Congress whether the demand is a legal or equitable claim or a gratuity, and the amount, if any, legally or equitably due from the United States to the claimant.” By its motion defendant seeks a ruling that the Government conclusively possesses all the rights to contractual data that the claimants seek to enforce.

FACTS

The following facts include only those undisputed facts necessary for a determination of the issues presented by defendant’s motion. Considering the long litigation history between the parties before the matter was referred to the United States Court of Federal Claims, the court permitted IN-SLAW, Inc.,1 to “ignore defendant’s reliance on testimony [and evidentiary material in its proposed findings of uncontroverted fact] because those issues, obviously, can be controverted.” Transcript of Proceedings, INSLAW, Inc. v. United States, No. 95-338X, at 8 (Fed.Cl. Jan. 29, 1996). Indeed, much of the evidence that defendant cites to support its proposed findings is excerpted from depositions and trial testimony, the latter pointedly controverted by INSLAW, which prevailed in an earlier trial, although the findings subsequently were vacated. In these circumstances the court is in no position on summary judgment to credit one side’s selected factual scenario over the other’s. The court therefore confines its inquiry to the relevant contractual language and makes legal determinations based on that language in order to resolve the issues that properly can be resolved at this time.

On March 16, 1982, INSLAW entered into a $9.6 million cost plus basis contract, No. JVUSA-82-C-0074, with the Executive Office for United States Attorneys (the “EOU-SA”) of the Department of Justice (“DOJ”), which required INSLAW to prepare and install 1) the computer-based public domain PROMIS software in the EOUSA and in the 20 largest United States Attorneys’ Offices, with an option by which DOJ could require installation of the software in another 10 offices; and 2) a word processor-based case-tracking system in the remaining smaller United States Attorneys’ Offices. PROMIS, the popular name for the “Prosecutor’s Management Information System,” is used for case-tracking purposes. There are two versions of PROMIS at issue. The “VAX” version of PROMIS was made available to DOJ via telephone lines through INSLAW’S own in-house VAX computer. The “PRIME” version of PROMIS was made available to DOJ upon INSLAWs installation of the system on government-furnished computers.2

Clause 74(b)(1) of the contract gave the Government unlimited rights3 in:

(i) technical data and computer software resulting directly from performance of experimental, developmental or research work which was specified as an element of performance in this or any other Government contract or subcontract;
(ii) computer software required to be originated or developed under a Government contract, or generated as a necessary part of performing a contract;
(iii) computer data bases, prepared under a Government contract, consisting of information supplied by the Government, infor[299] mation in which the Government has unlimited rights, or information which is in the public domain;
(iv) technical data necessary to enable manufacture of end-items, components and modifications, or to enable the performance of processes, when the end-items, components, modifications or processes have been, or are being, developed under this or any other Government contract or subcontract in which experimental, developmental or research work is, or was specified as an element of contract performance, except technical data pertaining to items, components, processes, or computer software developed at private expense (but see [clause 74(b) ] (2)(ii) below);
(v) technical data or computer software prepared or required to be delivered under this or any other Government contract or subcontract and constituting corrections or changes to Government-furnished data or computer software;
(vi) technical data pertaining to end-items; components or processes, prepared or required to be delivered under this or any other Government contract or subcontract, for the purpose of identifying sources, size, configuration, mating and attachment characteristics, functional characteristics and performance requirements ...;
(vii) manuals or instructional materials prepared or required to be delivered under this contract or any subcontract hereunder for installation, operation, maintenance or training purposes;
(viii) technical data or computer software which is in the public domain, or has been or is normally furnished without restriction by the Contractor or subcontractor; and
(ix) technical data or computer software listed or described in an agreement incorporated into the schedule of this contract which the parties have predetermined, on the basis of subparagraphs (i) through (viii) above, and agreed will be furnished with unlimited rights.

Clause 74(b)(2) states that the Government shall have Limited Rights4 in:

(i) technical data, listed or described in an agreement incorporated into the Schedule of this contract, which the parties have agreed will be furnished with limited rights; and
(ii) technical data pertaining to items, components or processes developed at private expense, and computer software documentation related to computer software that is acquired with restricted rights, other than such data as may be included in the data referred to in [Clause 74] (b)(l)(i), (v), (vi), (vii), and (viii). [Provided that only the portion or portions of each piece of data to which limited rights are to be asserted pursuant to (2)(i) and (ii) above are identified (for example, by circling, underscoring, or a note), and that the piece of data is marked with the [limited rights] legend below____

The portion of Clause 74(b)(2) of the contract labeled “LIMITED RIGHTS LEGEND” is marked prominently “N/A,” signifying not applicable.

Clause 74(b)(8) is entitled “Restricted Rights”5 and states, in part:

Free access — add to your briefcase to read the full text and ask questions with AI

INSLAW, Inc. v. United States, 41 Cont. Cas. Fed. 76,979, 35 Fed. Cl. 295, 1996 U.S. Claims LEXIS 48, 1996 WL 144373 (uscfc 1996).

41 Cont. Cas. Fed. 76,979 (INSLAW, Inc. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Norris v. PNC Bank, N.A.
D. Maryland, 2023
Dairyland Power Cooperative v. United States
123 Fed. Cl. 220 (Federal Claims, 2015)
Land Grantors in Henderson, Union v. United States
86 Fed. Cl. 35 (Federal Claims, 2009)
Vermont Yankee Nuclear Power Corp. v. United States
84 Fed. Cl. 339 (Federal Claims, 2008)
Stobie Creek Investments, LLC v. United States
81 Fed. Cl. 358 (Federal Claims, 2008)
J.L. Simmons Co. v. United States
60 Fed. Cl. 388 (Federal Claims, 2004)
Banfi Products Corp. v. United States
40 Fed. Cl. 107 (Federal Claims, 1997)
INSLAW, Inc. v. United States
42 Cont. Cas. Fed. 77,317 (Federal Claims, 1997)
Kanehl v. United States
41 Cont. Cas. Fed. 77,160 (Federal Claims, 1997)
Martin v. United States
37 Fed. Cl. 86 (Federal Claims, 1996)
Bear Claw Tribe, Inc. v. United States
36 Fed. Cl. 181 (Federal Claims, 1996)