Baskett v. United States

2 Cl. Ct. 356, 1983 U.S. Claims LEXIS 1753
CourtUnited States Court of Claims
DecidedMay 6, 1983
DocketNos. 161-78, 340-78, 317-79L, 311-80L and 616-80L
StatusPublished
Cited by35 cases

This text of 2 Cl. Ct. 356 (Baskett v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Baskett v. United States, 2 Cl. Ct. 356, 1983 U.S. Claims LEXIS 1753 (cc 1983).

Opinion

ORDER

LYDON, Judge:

In these five consolidated cases, some 95 owners of some 135 tracts of land adjacent to the Ohio River have sued to recover damages which they allege they have incurred, and are continuing to incur, as a result of activities relating to construction and operation of some 7 high-lift dams by the United States Army, Corps of Engineers (Corps). The issues are identical to those raised by some 23 different owners of land adjacent to the Ohio River in Loesch v. United States, 227 Ct.Cl. 34, 645 F.2d 905, cert. denied, 454 U.S. 1099, 102 S.Ct. 672, 70 L.Ed.2d 640 (1981).

On August 3, 1981, a pretrial order on liability was entered in these cases. Plaintiffs’ response to this pretrial order was submitted on or about December 7, 1981. Defendant’s response to the pretrial order and reply to plaintiffs’ response was submitted on or about September 13, 1982. Plaintiffs’ reply to defendant’s pretrial response was submitted on or about November 15, 1982. Plaintiffs have listed and identified 97 potential exhibits, whereas defendant has listed and identified 1034 potential exhibits. It is estimated, given the large number of witnesses which the parties anticipate calling, that a trial of some four (4) months can be expected under present circumstances. Defendant has listed 13 prospective witnesses. Plaintiffs have listed some 90 specific prospective witnesses but have also listed by classification a number of additional prospective witnesses, otherwise unidentified, e.g., county assessors and county auditors of each county where [359]*359plaintiffs’ lands are located, Directors of Soil Conservation Service for each such county, etc. Plaintiffs’ potential witness list could easily exceed 200. Under these circumstances both the court and the parties are under some obligation to make efforts to delimit the number of trial days and to take other steps to reduce the expense and effort generally associated with long trials of the duration estimated herein.

Defendant, on November 22,1982, filed a “Motion In Limine,” pursuant to Rule 16 RUSCC, seeking a pretrial order that precludes the admission of evidence at trial with respect to the flowage easement issue. Defendant also filed a second “Motion In Limine”, on November 22, 1982, seeking to preclude testimony by some of plaintiffs’ proposed witnesses. In effect, defendant seeks to limit the number of witnesses plaintiffs advise they intend to produce at trial. A motion in limine is a recognized method for getting an early ruling on trial matters. See C. Wright & A. Miller, Federal Practice and Procedure, Sec. 5037, p. 193; see also Zenith Radio Corp. v. Matsushita Elec. Ind. Co., 505 F.Supp. 1125, 1139-41 (E.D.Penn.1980). Plaintiffs, on December 21, 1982, filed a response to both motions in limine. This response given the nature, detail, specificity and legal citations, supporting defendant’s motions in limine, was most inadequate. Defendant’s motions were based on the pleadings, certain documentation, and the pretrial submission of the parties.

There are two basic issues in these cases. The first basic issue involves the question of whether the construction and the operation of certain high-life navigation dams on the Ohio River are responsible for the erosion that plaintiffs claim is, and has been, taking place on their properties adjacent to the Ohio River. This will be referred to as the erosion issue. The second basic issue, which will be referred to as the flowage easement issue, involves the question of whether Corps of Engineers personnel, or other government personnel, committed fraud or misrepresentation in the acquisition of flowage easements from plaintiffs in connection with the construction of the dams in question. Embraced within this broad fraud and misrepresentation question are subsidiary questions as to whether there are serious irregularities, fraudulent in nature, in the flowage easements themselves which serve to render them void, and as to whether ordinary high-water mark determinations made in connection with the preparation of the flowage easements were erroneous and thus misrepresented to plaintiffs.

It is deemed appropriate to consider first that motion in limine which seeks to eliminate the flowage easement issue as a viable triable issue. Thereafter, attention will be given to the second motion in limine which seeks to preclude testimony from certain individuals and/or groups of individuals plaintiffs propose to call as witnesses at trial.

I.

There is no question under RUSCC 16, that this court, as a trial court, has the power to issue pretrial orders simplifying issues for trial. Not only does this court have such power, it has a duty to exercise it in appropriate cases. This power allows the court, inter alia, to define the issues, facts, and theories actually in contention and to weed out extraneous issues. Too, this court also has the authority to issue pretrial rulings concerning the admissibility at trial of proposed testimony and documentary evidence. 6 C. Wright and A. Miller, Federal Practice and Procedure, Sec. 1525, at 586-589 (1971) and cases cited therein.

In this case, defendant’s first motion in limine, which seeks to preclude the admission of evidence on the flowage easement issue is, in effect, a request for a dispositive pretrial ruling eliminating such an issue from these cases. The-thrust, therefore, of defendant’s first motion is to obtain a favorable judgment before trial on the flow-age easement issue, thereby leaving the erosion issue as the sole issue for trial.

A federal trial court has considerable leeway in the use of its Rule 16 pretrial power and may appropriately rule, prior to trial, on the question of jurisdiction, see, [360]*360Nelson v. Keefer, 451 F.2d 289 (3d Cir. 1971); A.H. Emery Co. v. Marcan Products, Corp. 389 F.2d 11, 20 (2d Cir.1968), cert. denied, 393 U.S. 835, 89 S.Ct. 109, 21 L.Ed.2d 106; the legal sufficiency of a claim or defense, see American Machine & Metals, Inc. v. DeBothezat Impeller Co., 82 F.Supp. 556 (S.D.N.Y.1949), aff’d per curiam 173 F.2d 890 (2d Cir.1949), cert. denied, 339 U.S. 979, 70 S.Ct. 1025, 94 L.Ed. 1383; see also Schram v. Kolowich, 2 F.R.D. 343 (E.D.Mich.1942); and/or the ultimate merits of a particular claim where the undisputed facts indicate an unequivocal right to a judgment favoring a party. In Wirtz v. Young Elec. Sign Co., 315 F.2d 326, 327 (10th Cir.1963), it was noted that: “Summary disposition of a cause may logically and properly follow a pretrial conference when the pretrial procedures disclose the lack of a disputed issue of material fact and the facts so established indicate an unequivocal right to judgment favoring a party.” See also, Holcomb v. Aetna Life Ins. Co., 255 F.2d 577, (10th Cir.1958), cert. denied, 358 U.S. 879, 79 S.Ct. 118, 3 L.Ed.2d 110. In Klein v. Belle Alkali Co., 229 F.2d 658

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Langley v. United States
Federal Claims, 2017
Kahrs International, Inc. v. United States
33 Ct. Int'l Trade 1297 (Court of International Trade, 2009)
Gasa, Inc. v. United States
88 Fed. Cl. 752 (Federal Claims, 2009)
Stobie Creek Investments, LLC v. United States
81 Fed. Cl. 358 (Federal Claims, 2008)
Phillips v. United States
77 Fed. Cl. 513 (Federal Claims, 2007)
White & Case LLP v. United States
67 Fed. Cl. 164 (Federal Claims, 2005)
Dwen v. United States
62 Fed. Cl. 76 (Federal Claims, 2004)
North American Processing Co. v. United States
15 F. Supp. 2d 934 (Court of International Trade, 1998)
INSLAW, Inc. v. United States
35 Fed. Cl. 63 (Federal Claims, 1996)
Aeron Marine Shipping Co. v. United States
26 Cl. Ct. 946 (Court of Claims, 1992)
Cherokee Nation v. United States
23 Cl. Ct. 117 (Court of Claims, 1991)
Massachusetts Bay Transportation Authority v. United States
36 Cont. Cas. Fed. 75,912 (Court of Claims, 1990)
Kelley v. United States
36 Cont. Cas. Fed. 75,771 (Court of Claims, 1989)
Rogers v. United States
15 Cl. Ct. 692 (Court of Claims, 1988)
Bass v. United States
11 Cl. Ct. 295 (Court of Claims, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
2 Cl. Ct. 356, 1983 U.S. Claims LEXIS 1753, Counsel Stack Legal Research, https://law.counselstack.com/opinion/baskett-v-united-states-cc-1983.