Gasa, Inc. v. United States

88 Fed. Cl. 752, 2009 U.S. Claims LEXIS 364, 2009 WL 2633043
CourtUnited States Court of Federal Claims
DecidedAugust 20, 2009
DocketNo. 01-642 C
StatusPublished
Cited by1 cases

This text of 88 Fed. Cl. 752 (Gasa, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gasa, Inc. v. United States, 88 Fed. Cl. 752, 2009 U.S. Claims LEXIS 364, 2009 WL 2633043 (uscfc 2009).

Opinion

RULING ON DEFENDANT’S MOTION IN LIMINE

MARGARET M. SWEENEY, Judge.

In June 2000, plaintiff GASA, Inc. contracted with the United States Army Corps of Engineers (“Corps”) to dredge certain areas of the Monongahela River. As a result of difficulties encountered by the parities during the contract performance period, this lawsuit ensued, with plaintiff seeking delay damages, compensation for the dredging and placement of certain river material, and the return of withheld liquidated damages. The court narrowed the amount and types of damages recoverable by plaintiff in ruling on defendant’s two motions for summary judgment. Now, in the motion in limine presently before the court, defendant seeks to exclude the expert report and testimony of Michel J. Sadaka, plaintiffs expert on construction delays, pursuant to Federal Rule of Evidence 702 and Daubert v. Merrell Dow Pharmaceuticals, Inc., 509 U.S. 579, 113 S.Ct. 2786, 125 L.Ed.2d 469 (1993). For the reasons set forth below, the court denies defendant’s motion.

I. BACKGROUND1

On March 20, 2000, the Corps’ Pittsburgh District issued a sealed bid solicitation for the dredging of Braddoek Locks and Dam Pool 3 Navigation Channel in the Monongahela River (“the Project”). The Project consisted of dredging the river, disposal of some of the dredged material at an approved, off-site landfill, and placement of the remaining dredged material back in the river at a different location (“in-river placement”). The solicitation specifically identified four areas of the river to be dredged — referred to as MU-3, MU-59, MU-102, and the in-river placement area — as well as the cubic yards of material associated with each area. Only the material dredged from the in-river placement area was to be placed back in the river; the remaining material was to be disposed off-site. The solicitation indicated that most of [754]*754the contract earnings would be based on the quantity of material dredged and disposed of, except for the reimbursement for payment and performance bonds and the costs of mobilization and demobilization. The solicitation also indicated that contract performance was to begin within ten days of the Notice to Proceed (“NTP”) and completed within 180 days of the NTP. On June 6, 2000, plaintiff was awarded the contract in the amount of $6,410,559.55.

Almost every stage of contract performance was delayed in some manner for various reasons. The NTP was not issued until August 14, 2000, more than two months after the award of the contract. Plaintiff did not begin dredging operations until September 21, 2000, exceeding the ten-day post-NTP deadline provided for in the contract. And, dredging continued past February 10, 2001, the 180-day contract deadline for completing performance. Due to a contract provision prohibiting dredging after April 15 of any given year, plaintiffs last day of dredging was April 11, 2001, even though the full amount of work contemplated by the contract had not been completed.

Plaintiff filed the instant suit on November 14, 2001, subsequently amending its complaint on three occasions. In its Third Amended Complaint, plaintiff sought total damages of $1,906,718.43 plus interest, an amount that encompassed the return of $15,591.42 in assessed liquidated damages, compensation related to the in-river placement of dredged material in the amount of $178,737.57, and delay-related damages of $1,712,389.44. Plaintiff specified four ways in which the Corps caused its delay-related damages: the Corps delayed the issuance of the NTP; delayed the start of plaintiffs work until September 21, 2000; hindered and interfered with plaintiffs prosecution of the work; and prohibited plaintiff from mitigating the Corps-caused delays. In addition, plaintiff broke down its delay-related damages into three distinct elements. First, plaintiff contended that between April 20, 2000, and August 14, 2000, it incurred direct costs of $284,417.20 related to the Corps’ delay in issuing the NTP. Second, plaintiff claimed damages of $408,974.15 for work that it was unable to complete before the contract-mandated stoppage date of April 15, 2001, due to the alleged delaying actions of the Corps. Id. Third, plaintiff sought compensation in the amount of $1,018,998.09 for its extended field costs, encountered from December 31, 2000, through April 15, 2001, which resulted from the alleged delaying actions of the Corps.

The court ruled on defendant’s motions for summary judgment in a November 28, 2007 Opinion and Order, and concluded:

[TJhere is a genuine issue of material fact as to the reasonableness of the delay of the Corps’ issuance of the NTP, the existence, extent, and reasonableness of any delay associated with plaintiff’s dredging in MU-102,2 and the harm suffered by plaintiff as a result of the Corps’ delay in issuing the NTP and alleged delay in allowing dredging in MU-102.

GASA, Inc., 79 Fed.Cl. at 368 (footnote added). Consequently, the court limited the damages potentially recoverable by plaintiff to some direct costs associated with the NTP delay, extended field costs associated with the alleged delay of plaintiffs dredging in MU-102, and some liquidated damages. See id. at 347-71. In particular, the court determined that there were genuine issues of material fact concerning $34,417.20 of the direct costs, id. at 365-66, the extended field costs incurred during the thirty-one days following the contract completion date of February 10, 2001, id. at 367, and whether the liquidated damages should be reduced by an amount equivalent to thirty-one days, id. at 368. Subsequent to the court’s decision, defendant filed the instant motion, which has been fully briefed by the parties. Having determined that oral argument is unnecessary, the court is prepared to rule.

II. DISCUSSION

A. Motions In Limine

Rule 16 of the Rules of the United States Court of Federal Claims (“RCFC”) [755]*755empowers the court to, prior to trial, rule “on the admissibility of evidence” and limit “the use of testimony under Federal Rule of Evidence 702.” RCFC 16(c)(2)(C)-(D). A motion in limine is one of the means by which a party can obtain such a ruling. Such a motion “prevents] a party before trial from encumbering the record with irrelevant, immaterial or cumulative matters” and “enables a court to ... expedite and render efficient a subsequent trial.” Baskett v. United States, 2 Cl.Ct. 356, 367-68 (1983); see also id. at 368 (noting that the granting of a motion in limine does not preclude the parties from receiving a fair trial). The party offering the evidence that is the subject of the motion in limine must demonstrate its admissibility by a preponderance of evidence. Bourjaily v. United States, 483 U.S. 171, 175-76, 107 S.Ct. 2775, 97 L.Ed.2d 144 (1987) (concluding that “admissibility determinations that hinge on preliminary factual questions” under Federal Rule of Evidence

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Prakhin v. United States
Federal Claims, 2023

Cite This Page — Counsel Stack

Bluebook (online)
88 Fed. Cl. 752, 2009 U.S. Claims LEXIS 364, 2009 WL 2633043, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gasa-inc-v-united-states-uscfc-2009.