P. J. Carlin Construction Co. v. United States

92 Ct. Cl. 280, 1940 U.S. Ct. Cl. LEXIS 34, 1940 WL 4055
CourtUnited States Court of Claims
DecidedOctober 7, 1940
DocketNo. 43406
StatusPublished
Cited by7 cases

This text of 92 Ct. Cl. 280 (P. J. Carlin Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
P. J. Carlin Construction Co. v. United States, 92 Ct. Cl. 280, 1940 U.S. Ct. Cl. LEXIS 34, 1940 WL 4055 (cc 1940).

Opinion

Whaley, Chief Justice,

delivered the opinion of the courts

The plaintiff, P. J. Carlin Construction Company, entered into a contract with the defendant, on November 27, 1933, by the terms of which it agreed to furnish all labor and materials and perform all work required for the construction of the substructures of two highway bridges over the Cape Cod Canal, Massachusetts, for the lump sum consideration of $1,327,700, the work to be performed in accordance with plans and specifications which were made a part of the contract. The bridges in question are known as the Sagamore Bridge and the Bourne Bridge.

The substructure of the Sagamore Bridge consists of four separate units of masonry, two abutments and two piers,, commonly referred to as channel piers, with one abutment, and one channel pier on each side of the canal.

The substructure of the Bourne Bridge consists of eight separate pieces of masonry, two abutments and six piers. Of the six piers, two are commonly called channel piers and four intermediate piers. One abutment, one channel pier,, [294]*294and two intermediate piers are located on each side of the canal.

The plaintiff, with the approval of the defendant, entered into a subcontract with the Blakeslee-Bollins Corporation, a Massachusetts corporation, to do all the excavation work required, and to furnish and provide the cofferdams for the four main channel piers at Bourne and Saga-more, including the placing of the seal concrete, material for which was to be furnished by plaintiff. Promptly after receipt of notice to proceed, plaintiff commenced work, prosecuting it skillfully and diligently, and through the agency of its subcontractor completed the work undertaken to be performed by it. Plaintiff was paid the contract price of the work as modified by the various change orders, less the sum of $1,000 which was retained by the defendant as liquidated damages under Article 9 of the contract. Upon receipt of payment plaintiff executed to the United States a release of all claims arising under the contract except the items here sued on.

The plaintiff claims it has sustained damages in connection with the construction of the two highway bridges involved, as follows: (1) Excess cost of constructing the four main channel piers over and above what would have been the cost had the subsurface conditions encountered been as represented and warranted by the defendant in the specifications, including a reasonable profit of 10 percent thereon, $231,485.24; (2) Excess cost of endeavoring to eliminate or reduce sand-streaking in the concrete, including a reasonable profit of 10 percent, $55,785.02; (3) Cost of removing certain power lines, pursuant to orders of the defendant’s officers, $1,272; (4) Cost of maintenance and operation of three complete concrete units for a period of 89 days covering the period during which the construction of the four main channel piers was delayed because of subsurface conditions, including a reasonable profit of 10 percent thereon, $79,018.02; and (5) The amount retained by the defendant as liquidated damages, $1,000; or a total of $368,560.28.

The first item of the claim is one in which plaintiff has no personal interest but is prosecuted by it solely for the benefit of its subcontractor, the Blakeslee-Bollins Corpora[295]*295tion. That corporation prior to the submission of bids in this case and the acceptance of plaintiff’s bid by the defendant, had examined the site of the work, the plans and specifications, the boring maps and data, and had submitted a bid for the work of constructing the substructures of the two bridges to one of the unsuccessful bidders for the entire job. When the plaintiff was awarded the contract it took over the bid submitted to the unsuccessful bidder by the Blakeslee-Rollins Corporation and entered into a contract with that corporation for the construction by it of the substructure of the two bridges for the sum of $260,000. The plaintiff, through its subcontractor, submitted to the defendant’s contracting officer the plan of the cofferdam method that it proposed to follow in the construction of the four main channel piers. The proposed method was approved by the Government’s engineers and its contracting officer.

Almost from the beginning of the wrork the subcontractor encountered difficulties in driving the sheeting. Nested and compacted boulders, forming an almost impenetrable barrier, were encountered. In endeavoring to penetrate them the surrounding soil became agitated and mixed with water, with the result that a fine free-flowing sand was produced, an inevitable consequence of the excessive driving of the sheeting. Early in March 1934, the subcontractor notified defendant’s contracting officer that it would be. impossible to construct these piers by the cofferdam method, and that it would not be possible to rest them upon undisturbed natural soil at the elevations specified. The Government at the time insisted that the work proceed in accordance with the provisions of the specifications, but the excessive hammering and the drastic measures necessary to remove the boulders, added to the dangerous condition of the ground by disturbing its stability, and the outside pressure which forced water and sand into the cofferdams, made the work hazardous and expensive. These conditions, as the work progressed, resulted in frequent conferences between plaintiff, its subcontractor, and representatives of the defendant in regard to the situation. As a result of these conferences the defendant determined in June 1934, that be[296]*296cause of the disturbed, conditions of the soil caused by the excessive hammering in driving the steel sheeting and the removal of boulders, and the likelihood that such conditions might continue until the bottom of the required depth was reached, the elevations prescribed should be changed thus relieving plaintiff of carrying the excavation to the required depth. Appropriate change orders were issued, providing that excavation might be stopped at elevation 55 instead of elevation 48, and that a suitable foundation would be prepared by driving bearing piles into the soil at the bottom of the excavation. As a result of these change orders three of the four piers as finally constructed rest upon an artificial foundation created by the driving of a large number of wood bearing piles, and the fourth pier rests upon a ledge of solid rock formed by the nesting and compacting of numerous heavy boulders.

Prior to the issuance of the various change orders referred to plaintiff’s subcontractor had expended in the construction of the four main channel piers $210,441.13 in excess of the amount plaintiff and the subcontractor had estimated such costs would be at that stage of the work. It is contended by plaintiff that this excess cost of the work in connection with the construction of the main channel piers and the resulting loss and damage to its subcontractor was caused by misleading and deceptive representations made by the defendant as to the subsurface conditions at the site of the piers.

Plaintiff’s subcontractor, the Blakeslee-Bollins Corporation, and C. W. Blakeslee & Sons were the prime contractors, under a contract similar to the one here in question, to furnish all labor and materials and perform all work required for the construction of the substructure of the Vertical Lift Railway Bridge over the Cape Cod Canal, at Buzzards Bay, located approximately three-quarters of a mile from the sites of the highway bridges. Upon completion of the work C. W.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hellander v. United States
178 F. Supp. 932 (Court of Claims, 1959)
A. L. Coupe Construction Co. v. United States
139 F. Supp. 61 (Court of Claims, 1956)
Shepherd v. United States
113 F. Supp. 648 (Court of Claims, 1953)
Bein v. United States
101 Ct. Cl. 144 (Court of Claims, 1943)
Eastern Contracting Co. v. United States
97 Ct. Cl. 341 (Court of Claims, 1942)

Cite This Page — Counsel Stack

Bluebook (online)
92 Ct. Cl. 280, 1940 U.S. Ct. Cl. LEXIS 34, 1940 WL 4055, Counsel Stack Legal Research, https://law.counselstack.com/opinion/p-j-carlin-construction-co-v-united-states-cc-1940.