A. L. Coupe Construction Co. v. United States

139 F. Supp. 61, 134 Ct. Cl. 392, 1956 U.S. Ct. Cl. LEXIS 85
CourtUnited States Court of Claims
DecidedMarch 6, 1956
DocketNo. 50276
StatusPublished
Cited by8 cases

This text of 139 F. Supp. 61 (A. L. Coupe Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
A. L. Coupe Construction Co. v. United States, 139 F. Supp. 61, 134 Ct. Cl. 392, 1956 U.S. Ct. Cl. LEXIS 85 (cc 1956).

Opinion

Lakamoee, Judge,

delivered the opinion of the court:

This action is brought by plaintiff1 to recover damages for an alleged breach of the express and implied provisions of a contract to construct housing facilities for defendant at Oak Nidge, Tennessee, in 1943 and 1944.

Plaintiff bases its claims upon allegations that (1) defendant failed to stockpile lumber in the required sizes and quantities needed at a single location at or near the site of the work; (2) defendant interfered with plaintiff in the hiring and recruiting of labor; (3) defendant failed to construct and maintain adequate roads in the vicinity of the work; and (4) for the return of amounts deducted from the contract price for lodging plaintiff’s employees.

Defendant denies any liability for losses on account of unavailability of lumber, recruitment of labor, or condition [394]*394of the roads and asserts a legal right to the sum deducted for housing plaintiff’s employees. In addition, defendant asserts that the claims in suit were released by plaintiff upon completion of the work, and that plaintiff has not shown that it suffered any damage due to any actions of defendant.

The questions presented are: (1) whether plaintiff has released defendant from the claims asserted in this suit; (2) whether plaintiff suffered any unrecovered loss due to the lack of all the lumber at a single location in the sizes and quantities required and, if so, whether defendant is liable therefor; (3) whether the roads on the site of the work were different from what plaintiff should have contemplated and, if so, whether it suffered any loss and damages by reason thereof, and whether defendant may be held liable for any of it; (4) whether the conditions controlling the hiring and recruitment of labor for the work were different from that which plaintiff expected or should have expected before the award of the contract and, if so, whether defendant is liable for any loss suffered thereby;. (5) whether plaintiff’s losses on the contract in connection with any particular conditions or actions of plaintiff or defendant can be ascertained and separated in order to determine the amounts, if any, due as damages; (6) whether defendant is entitled to retain moneys assessed and withheld from plaintiff’s contract pay or collected from plaintiff for the cost of lodgings for plaintiff’s employees.

In this posture of the case, the first question to be passed upon is the assertion of defendant that all the claims in suit, except the hutment claim, have been released.

After the completion of the work and during the latter part of 1944, plaintiff filed claims with defendant for additional compensation in connection with its work under the .contract. On March 5, 1945, a formal claim asserting 10 itemized claims in the total amount of $72,543 was filed. On March 17, 1945, a final payment voucher in the amount of $73,437.16, covering monthly pay estimate No. 10 and marked “final” was sent to plaintiff with the request that the •certificate of the payee thereon be executed along with a release, as required by the contract, and returned to de[395]*395fendant in order that final payment may be made. Previously plaintiff had been requested to execute a release with the advice that the final pay estimate was being prepared and the release would be required in connection therewith. Mr. A. L. Coupe complied with the request and signed and submitted to defendant a release along with pay estimate No. 10. Payment on the estimate was made on April 2, 1945. No retained percentages were withheld from this estimate for the purpose of keeping the contract open.- The release, in pertinent part, is as follows:

RELEASE
Approved by the Under Secretary of War March 22, 1941
The work under contract number W-742l-Eng-4 dated 11-16-43 between the United States of America, represented by E. H. Marsden, Col., Corps of Engineers, as Contracting Officer, and the undersigned contractor, having been completed and finally accepted, the United States, its officers and agents, are hereby released from all claims and demands whatsoever arising under or by virtue of said contract, except as follows:
See list attached.
Executed this 24th day of March 1945.
Coupe CowstruotiON,
(Contractor)
By A. L. Coupe [s],
(Official Title)
Partner.
* * * * *

Subsequently the contracting officer allowed the claims as listed in items 4, 5, and 6 of the specifications, and on appeal the head of the department allowed items 1, 2, and 3, and payments thereon have been made to plaintiff in the total amount of $16,156.54. The claims set out in items 7, 8, and 10 of the specifications were denied by the contracting officer and the head of the department. Item 9 of the claim for hutment charges was allowed to the extent that it was found that the hutment services were not part of the construction contract and the deductions thereon could not be made from the construction contract. Item 7 of the claim was denied by the head of the department on the grounds [396]*396that the invitation to bid was not an offer to sell lumber to plaintiff at the prices stated therein, but was merely for the purpose of evaluating bids and that the price for such lumber sold must be determined by other standards of value and pricing. Item 8 of the claim was denied on the grounds that the contract had provided for extensions of time, but not for damages for delays due to any delay in the receipt of materials, equipment, or supplies to be furnished by the Government. Item 10 of the claim was denied on the grounds that plaintiff failed to establish proof of any basis for the claim. The board observed that the record before it showed each change order allowed additional sums based upon amounts requested by the contractor, or amounts arrived at after negotiations, and there was included in such amounts items of ten percent for overhead and ten percent in addition for profit, and further, the record showed no reservation of additional claims in connection with overhead. Plaintiff now says that the release above-quoted was without force and effect because it was not signed by the general partner, A. L. Coupe Construction Company, Inc., but by A. L. Coupe, one of the special partners.

On November 13,1943, the board of directors of the A. L. Coupe Construction Company, Inc., adopted a resolution which “authorized, empowered, and directed” Mr. Mueller to “execute all contracts, letter contracts and other papers, and do all things and perform all acts necessary or incident thereto” in connection with construction at Oak Ridge. The form for signature was specified as “Coupe Construction, by A. L. Coupe Construction Company, Inc. — General Partner, by — C. W. Mueller, Vice President.” However, this instruction appears to have been almost completely ignored.

Mr. Coupe was not only one of the limited partners, but also was president of the general partner, the corporation, and as such was the individual in practical control of the partnership operations.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Imprimis Investors LLC v. United States
83 Fed. Cl. 46 (Federal Claims, 2008)
Tecom, Inc. v. United States
66 Fed. Cl. 736 (Federal Claims, 2005)
Miya Bros. Construction Co. v. United States
34 Cont. Cas. Fed. 75,237 (Court of Claims, 1987)
G.M. Shupe, Inc. v. United States
32 Cont. Cas. Fed. 72,712 (Court of Claims, 1984)
J. G. Watts Construction Co. v. United States
161 Ct. Cl. 801 (Court of Claims, 1963)
Hellander v. United States
178 F. Supp. 932 (Court of Claims, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
139 F. Supp. 61, 134 Ct. Cl. 392, 1956 U.S. Ct. Cl. LEXIS 85, Counsel Stack Legal Research, https://law.counselstack.com/opinion/a-l-coupe-construction-co-v-united-states-cc-1956.