Miya Bros. Construction Co. v. United States

34 Cont. Cas. Fed. 75,237, 12 Cl. Ct. 142, 1987 U.S. Claims LEXIS 63
CourtUnited States Court of Claims
DecidedMarch 24, 1987
DocketNo. 139-85C
StatusPublished
Cited by2 cases

This text of 34 Cont. Cas. Fed. 75,237 (Miya Bros. Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Miya Bros. Construction Co. v. United States, 34 Cont. Cas. Fed. 75,237, 12 Cl. Ct. 142, 1987 U.S. Claims LEXIS 63 (cc 1987).

Opinion

ORDER

MOODY R. TIDWELL, III, Judge:

Defendant filed a motion for partial summary judgment requesting the court to dismiss a portion of the claims being litigated. Plaintiff opposes.

FACTS

On January 21, 1980 defendant, through the Federal Highway Administration (FHWA), awarded a contract pursuant to section 2 of the Small Business Act, amending section 8(a), 15 U.S.C. § 637(a), to plaintiff for the construction of approximately eight miles of unpaved road, known as Boulder Mountain Road, near Grover, Utah.

Plaintiff completed the road on August 28, 1981 and was paid $2,526,385.99 after executing a release which discharged all obligations to the government except for the reservation of certain claims that are the subject of this litigation. Plaintiff reserved seven claims in the release totalling $693,574.99, including an 80-day extension for time of performance, plus claims of its subcontractor, LaMar D. Construction Co., in the amount of $196,868.12.1

A year later, on June 23, 1983 plaintiff submitted a list of “revised” claims. Defendant alleges that the revised claims contained new claims not reserved in the release, as well as increased claims above the dollar amounts reserved on claims in the release.

The contracting officer issued a final decision on plaintiff’s claims which considered only those claims, time extensions, and dollar amounts originally reserved by plaintiff in the release. The FHWA withheld $30,-[144]*144000 from the final payment as liquidated damages for late performance. Defendant argued that the June 22, 1982 release discharged all obligations of the government except for the time and money claims specifically reserved by plaintiff and that to the extent the separate counts in the complaint set out claims not reserved, or in excess of those claims, they are barred by the release. Defendant seeks dismissal of the latter claims and all amounts in excess of the claims reserved in the release.

Plaintiff claims that only one new claim was submitted after it executed the release, the “benching” claim, which was eventually paid by defendant. During the course of negotiating the benching claim, some, if not all of the other claims, were discussed. In its letter of June 23, 1983 which first presented the benching claim, plaintiff states that it clarified its reserved claims in the context of the post-release negotiations during which time plaintiff realized that it had understated its claims. The clarification contained the increased value claims which, in turn, were included in the complaint.

DISCUSSION

Defendant argues that plaintiff is barred from asserting claims that were not reserved in the release and from asserting claims in excess of the amount specifically reserved. As a general rule, the filing of a release by a contractor reflects the contractor’s unqualified acceptance and agreement with its terms and is binding on both parties. Clark Mechanical Contractors, Inc. v. United States, 5 Cl.Ct. 84, 86 (1984). Moreover, a contractor may reserve claims from the release but if the contractor fails to do so, absent certain mitigating factors, it will preclude the contractor from pressing those “other” claims based on events prior to execution of the release. Clark at 86 (citing H.L.C. & Assocs. Constr. Co. v. United States, 176 Ct.Cl. 285, 293, 367 F.2d 586, 590 (1966)).

The mitigating factor here, so says plaintiff, is that defendant continued to discuss the claims made in its letter of December 18, 1981 after execution of the release and because defendant accepted, discussed, confessed liability and paid the benching claim which was first brought to the attention of the contractor officer one year after execution of the release. Thus, alleges plaintiff, the government never considered that the release constituted an abandonment by plaintiff of its later claims. In support of its position, plaintiff cites J.G. Watts Constr. Co. v. United States, 161 Ct.Cl. 801 (1963), which recognizes that there are “special and limited situations in which a claim may be prosecuted despite the execution of a general release.” Id. at 806. One of the exceptions, and the only exception put forward by plaintiff, is where the conduct of the parties in continuing to consider claims after execution of the release evidences that they never considered the release as constituting an abandonment of the claims. Under those circumstances, the release will not be held to bar the prosecution of a claim. Watts, however, cites to Winn-Senter Construction Co. v. United States, 110 Ct.Cl. 34, 75 F.Supp. 255 (1948), as authority for the exception to the general rule. Watts at 807. In Winn-Senter, the contractor executed the release while its claim was under consideration by the government and the consideration continued after the release had been given. In that situation, the court found that the conduct of both parties indicated that the claim had not been abandoned or forfeited. Id., 110 Ct.Cl. at 65-66, 75 F.Supp. at 260. The court also notes that the release in Winn-Senter was based, at least in part, on coercion by the government. Plaintiff also cites Metric Constr. Co. v. United States, 1 Cl.Ct. 383 (1983), for the same proposition, i.e., the conduct of the parties after execution of the release is proof that they never construed the release as an abandonment of the claim. Id. at 396-97.

On a different tack, plaintiff points to J.F. Shea Co., Inc. v. United States, 4 Cl.Ct. 46 (1983), which held that once a complaint has been filed and discovery undertaken, data may come of notice to plaintiff, which indicates it understated the value of its claim. Id. at 54. In that circumstance, plaintiff may change the amount of [145]*145the claim, but it may not present a new claim because it would not have met the jurisdictional prerequisite in this court of being submitted to and certified by the contracting officer. Shea continues, that “the increased amount of Shea’s claim which was not submitted to the contracting officer for decision does not represent a ‘new claim.’ ” Id. (citing Spradlin Corporation, ASBCA No. 23974, 81-2 BCA ¶ 15,423 at 76,430-31 (1981)).

In the case at bar, plaintiff alleged that only one new claim was filed after the general release—the benching claim. That claim was paid by defendant and is thus not before the court. If plaintiff is correct that the benching claim was the only new claim, plaintiff's motion should be denied. As to the increased claims, the court is of the opinion that they may be pled. The increased dollar value was before the contracting officer even though he refused to consider it. This court has jurisdiction to hear and decide the value of each claim. We are persuaded by the holdings in Shea and Spradlin Corporation that once a claim is presented to this court, the value of the claim may increase (or decrease) based upon information gained from the moment the claim is first presented to the government until today, and it may even change tomorrow. Plaintiff, of course, must still prove his claim, including its worth.

CONCLUSION

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Modeer v. United States
68 Fed. Cl. 131 (Federal Claims, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
34 Cont. Cas. Fed. 75,237, 12 Cl. Ct. 142, 1987 U.S. Claims LEXIS 63, Counsel Stack Legal Research, https://law.counselstack.com/opinion/miya-bros-construction-co-v-united-states-cc-1987.