Curley, Inc. v. United States

32 Cont. Cas. Fed. 72,942, 6 Cl. Ct. 274, 1984 U.S. Claims LEXIS 1300
CourtUnited States Court of Claims
DecidedSeptember 25, 1984
DocketNo. 340-83C
StatusPublished
Cited by4 cases

This text of 32 Cont. Cas. Fed. 72,942 (Curley, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Curley, Inc. v. United States, 32 Cont. Cas. Fed. 72,942, 6 Cl. Ct. 274, 1984 U.S. Claims LEXIS 1300 (cc 1984).

Opinion

ORDER ON DEFENDANT’S MOTION TO DISMISS AND PLAINTIFF’S CROSS-MOTION FOR REMAND

WHITE, Senior Judge.

In the complaint, the plaintiff, Curley, Incorporated (Curley), seeks damages in the amount of $95,299.61 because of an alleged breach by the Government of a contract under which Curley repaired water tanks and repainted several structures at Keesler Air Force Base, Mississippi.

The case is now before the court on the defendant’s motion asking the court to dismiss, for lack of jurisdiction, the portion of the complaint which seeks damages in excess of $31,594.64, or, in the alternative, to dismiss the complaint in its entirety, and on the plaintiff’s cross-motion that the case be remanded to the contracting officer. Counsel for the parties have presented oral arguments to the court.

The Facts

The contract in question was awarded on October 6, 1980, by a contracting officer of the Department of the Air Force to Curley and C.S. & W. Contractors, Inc. Later, Curley purchased the interest of C.S. & W. Contractors, Inc., in the project; and, consequently, Curley is the sole owner of the claim involved in the present litigation.

Under one of the provisions of the contract, the Air Force promised to supply to the contractor the water and electricity needed for the project.

Work on the project commenced February 1, 1981. When Curley connected its equipment to the Air Force’s transformer banks, the phased transformers could not maintain the increased power load. One transformer failed; and Curley procured a diesel-driven air compressor to finish the job.

On February 18, 1982, Curley filed with the contracting officer a claim in the amount of $31,594.64, allegedly based on the rental cost of the diesel-driven air compressor and the cost of the delay caused by the Air Force’s failure to provide the needed power. As the claim was for an amount less than $50,000, it- was not certified by the contractor. The contracting officer rejected this claim in a final decision dated June 28,1982, holding that the Government had fulfilled its contractual obligation respecting the furnishing of power to the contractor.

Thereafter, on May 25,1983, the plaintiff filed its complaint in this court under the so-called direct access provision of the Contract Disputes Act (41 U.S.C. § 609(a)(1) (1982)). The complaint, which seeks to recover $95,299.61 because of the Air Force’s alleged failure to provide power needed for the project, was accompanied by a certificate asserting that the claim is made in good faith, that the supporting data are accurate and complete, and that the [276]*276amount requested accurately reflects the contract adjustment for which Curley believes the Government is liable.

Discussion

The defendant’s motion is based principally upon the following requirements in the Contract Disputes Act:

§ 605. Decision by contracting officer
(a) Contractor claims
All claims by a contractor against the government relating to a contract shall be in writing and shall be submitted to the contracting officer for a decision. The contracting officer shall issue his decisions in writing, and shall mail or otherwise furnish a copy of the decision to the contractor. * * *
******
(c) Amount of claims; certification * * *
(1) * * * For claims of more than $50,-000, the contractor shall certify that the claim is made in good faith, that the supporting data are accurate and complete to the best of his knowledge and belief, and that the amount requested accurately reflects the contract adjustment for which the contractor believes the government is liable.

The defendant asserts in the brief supporting its motion that as no claim in the amount of $95,299.61, accompanied by the certificate prescribed in section 605(c)(1) for claims in excess of $50,000, was ever submitted to the contracting officer and, consequently, the contracting officer has never rendered a decision on such claim, the court does not have jurisdiction to consider the complaint insofar as it seeks damages in the amount of $95,299.61. The defendant cites the statement in Paragon Energy Corp. v. United States, 227 Ct.Cl. 176, 177, 645 F.2d 966, 967 (1981), to the effect that a decision by the contracting officer is the “linchpin” for appealing a claim under the Contract Disputes Action.

The defendant concedes that the plaintiff’s initial claim for $31,594.64 was properly submitted to the contracting officer and was the subject of a decision by the contracting officer; and, accordingly, that the court has jurisdiction to consider the complaint insofar as it seeks damages in the amount of $31,594.64.

The defendant concludes that “once a contractor has submitted a ‘claim’ to the contracting officer, a contractor may not later augment that claim after the final decision of the contracting officer”; and that “plaintiff’s claim for more than $31,-594.64 is barred.”

Just why the decision of a contracting officer should be immutable, whereas court decisions are subject to reconsideration, review, withdrawal, etc., under proper circumstances, is not explained clearly by the defendant.

It has been clearly established by earlier court decisions that, under the statutory provisions just quoted, all claims in excess of $50,000 must be certified by the contractor upon submission to the contracting officer; that certification is a jurisdictional prerequisite to a subsequent direct-access action by a government contractor in this court; and that the result of a failure to certify a claim for more than $50,000 is dismissal of the complaint. Palmer & Sicard, Inc. v. United States, 4 Cl.Ct. 420, 422 (1984), and cases cited.

The problem in this case is that the contractor’s claim, when submitted to the contracting officer, was for less than $50,000 and, accordingly, there was no statutory requirement that it be certified to the contracting officer; whereas, when the complaint was subsequently filed in this court, the contractor had increased the amount of the claim to more than $50,000.

It has previously been necessary for this court to deal with a problem under the Contract Disputes Act that was rather similar to the problem in the present case.

In J.F. Shea Co. v. United States, 4 Cl.Ct. 46 (1983), a contractor who had built an aqueduct for the Government submitted to the contracting officer a certified claim in the amount of $3,940,227; and later, upon the denial of the claim by the contracting officer, the contractor filed a com[277]*277plaint in this court seeking damages in the amount of $5,614,962. Before the court, the defendant contended (inter alia) that the court lacked jurisdiction because the total amount of the contractor’s claim had not been properly submitted and certified to the contracting officer in accordance with 41 U.S.C. § 605.

The court in Shea rejected the defendant’s jurisdictional defense. In doing so, the court stated in part as follows (4 Cl.Ct.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Modeer v. United States
68 Fed. Cl. 131 (Federal Claims, 2005)
Dawco Construction, Inc. v. United States
35 Cont. Cas. Fed. 75,755 (Court of Claims, 1989)
Miya Bros. Construction Co. v. United States
34 Cont. Cas. Fed. 75,237 (Court of Claims, 1987)
LDG Timber Enterprises, Inc. v. United States
32 Cont. Cas. Fed. 73,681 (Court of Claims, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
32 Cont. Cas. Fed. 72,942, 6 Cl. Ct. 274, 1984 U.S. Claims LEXIS 1300, Counsel Stack Legal Research, https://law.counselstack.com/opinion/curley-inc-v-united-states-cc-1984.