Palmer & Sicard, Inc. v. United States

31 Cont. Cas. Fed. 72,055, 4 Cl. Ct. 420, 1984 U.S. Claims LEXIS 1494
CourtUnited States Court of Claims
DecidedFebruary 6, 1984
DocketNo. 394-83C
StatusPublished
Cited by15 cases

This text of 31 Cont. Cas. Fed. 72,055 (Palmer & Sicard, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Palmer & Sicard, Inc. v. United States, 31 Cont. Cas. Fed. 72,055, 4 Cl. Ct. 420, 1984 U.S. Claims LEXIS 1494 (cc 1984).

Opinion

OPINION ON DEFENDANT’S MOTION FOR SUMMARY JUDGMENT

WHITE, Senior Judge.

The plaintiff, Palmer & Sicard, Inc., sues to recover from the Government the sum of $127,982.09 allegedly due under government contract DACA 51-79-C-0054 (“the contract”).

The complaint was filed on June 16,1983, under the Contract Disputes Act of 1978 (41 U.S.C. §§ 601-613 (Supp. V 1981)).

On September 6, 1983, the defendant filed a motion to dismiss the complaint on the ground that the court does not have jurisdiction to consider the claim because (according to the defendant) the plaintiff has not properly certified its claim, as required by 41 U.S.C. § 605(c)(1) (Supp. V 1981).

As the parties have submitted a number of documents for the consideration of the court in connection with the defendant’s motion, the motion will be treated as a motion for summary judgment.

The case is before the court on the defendant’s motion, the plaintiff’s response, filed November 1,1983, and the defendant’s reply, filed November 16, 1983.

The pending motion presents two questions for determination by the court: (1) whether it was necessary for the plaintiff to certify its claim under section 605(c)(1), and, if so, (2) whether the claim was properly certified by the plaintiff.

Necessity for Certification Under Section 605(c)(1)

Section 605(c)(1) of 41 U.S.C. (Supp. Y 1981) states in part as follows with respect to the submission by a government contractor of claims to the contracting officer:

* * * For claims of more than $50,000, the contractor shall certify that the claim is made in good faith, that the supporting data are accurate and complete to the best of his knowledge and belief, and that the amount requested accurately reflects the contract adjustment for which the contractor believes the government is liable.

Under the contract, which was entered into on March 23, 1979, between the plaintiff and the defendant, acting through a contracting officer of the United States Army Corps of Engineers (“the Corps”), the plaintiff was to alter the heating and air conditioning system at the L.G. Hanscom Air Force Base in Bedford, Massachusetts. The Corps issued a notice to proceed with the work on April 17, 1979, and the notice was received by the plaintiff on April 23, 1979.

Subsequently, in accordance with paragraph 18 of the contract, the Corps terminated the contract for the convenience of the Government. The termination became effective on January 29, 1980. Almost 80 percent of the contract had been completed as of the termination date. The termination notice instructed the plaintiff to proceed with the determination and submission of its termination claim.

On June 24, 1980, the defendant paid the plaintiff $54,538.91, which represented a payment estimate with respect to contract performance before the termination date.

After the plaintiff had requested a 90-day time extension for the submission of its termination claim and had been granted a 60-day time extension to March 30,1981, by the Corps, the plaintiff on March 27, 1981, submitted a claim to the contracting officer in the amount of $128,373.1 This amount was made up of $19,740 for “settlement expenses,” $8,071 for “settlements with subcontractors,” and a net of $100,562 ($210,-335 less payments of $55,234 and $54,539) [422]*422allegedly due for work done under the contract before the termination date.

It is indisputable that, under section 605(c)(1), all claims in excess of $50,000 must be certified by the contractor upon submission to the contracting officer. W.M. Schlosser Co., Inc. v. United States, 705 F.2d 1336, 1338 (Fed.Cir.1983); Skelly & Loy v. United States, 231 Ct.Cl.-,-, 685 F.2d 414, 416 (1982); W.H. Moseley Co. v. United States, 230 Ct.Cl. 405, 407, 677 F.2d 850, 852, cert. denied, 459 U.S. 836, 103 S.Ct. 81, 74 L.Ed.2d 77 (1982); Paul E. Lehman, Inc. v. United States, 230 Ct.Cl. 11, 13, 673 F.2d 352, 354 (1982). Moreover, certification is a jurisdictional prerequisite to a direct-access action by a government contractor in this court. W.M. Schlosser Co., Inc. v. United States, supra, 705 F.2d at 1338; W.H. Moseley Co. v. United States, supra, 230 Ct.Cl. at 406, 677 F.2d at 851; Warchol Construction Co. v. United States, 2 Cl.Ct. 384, 388 (1983). As stated by the Court of Claims: “ * * * Congress has determined that certification is necessary for there to be a valid claim under the [Contract Disputes] Act.” Paul E. Lehman, Inc. v. United States, supra, 230 Ct.Cl. at 16, 673 F.2d at 356. Consequently, the result of a failure to certify a claim for more than $50,000 is dismissal of the complaint. Skelly & Loy v. United States, supra, 231 Ct.Cl. at-, 685 F.2d at 416; Fidelity & Deposit Co. of Maryland v. United States, 2 Cl.Ct. 137, 146 (1983).

The plaintiff does not contest any of the legal propositions stated in the preceding paragraph. The plaintiff’s primary position simply is that its termination claim was for less than $50,000. According to the plaintiff, the amount which it sought from the contracting officer must be bifurcated into: (1) a pre-termination item representing the payment due under the contract for work completed before the contract was terminated; and (2) a post-termination item of $27,811 ($19,740 for the plaintiff’s own termination expenses, plus $8,071 for settlements made with subcontractors). The plaintiff argues that the pre-termination item for work actually done under the contract before the termination was due the plaintiff under the contract and was not a request for a “contract adjustment,” within the meaning of that term as used in section 605(c)(1); that the $27,811 item represented the only contract adjustment sought because of the Government’s termination of the contract; and that, as the termination claim was for less than $50,000, certification was not necessary.

The plaintiff’s argument is without merit. The plaintiff submitted to the contracting officer a single claim in the amount of $128,373. The letter submitting the claim stated in the first sentence that “Our claim in the amount of $128,373 is attached with schedules.” Also, in two other paragraphs of the letter, the plaintiff referred to its “claim” in the singular. The pre-termination item was as much a part of the plaintiff’s claim as was the post-termination item. The plaintiff sought reimbursement for both items from the contracting officer in a single adjustment of the contract price.

There is no concession of liability by the defendant in the record as to the whole, or any portion, of either the pre-termination or the post-termination item. (The defendant filed the motion to dismiss without having filed an answer to the complaint.) Consequently, both items, in their entirety, are still parts of the plaintiff’s single claim for a contract adjustment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Choggiung Ltd. v. United States
37 Cont. Cas. Fed. 76,200 (Court of Claims, 1991)
National Surety Corp. v. United States
36 Cont. Cas. Fed. 75,865 (Court of Claims, 1990)
Placeway Construction Corp. v. United States
35 Cont. Cas. Fed. 75,709 (Court of Claims, 1989)
City of El Centro v. United States
35 Cont. Cas. Fed. 75,724 (Court of Claims, 1989)
Triax Co. v. United States
35 Cont. Cas. Fed. 75,697 (Court of Claims, 1989)
Gardner Machinery Corp. v. United States
34 Cont. Cas. Fed. 75,441 (Court of Claims, 1988)
Technassociates, Inc. v. United States
34 Cont. Cas. Fed. 75,435 (Court of Claims, 1988)
United States v. Turner Construction Company
827 F.2d 1554 (Federal Circuit, 1987)
Christian Appalachian Project, Inc. v. United States
33 Cont. Cas. Fed. 74,558 (Court of Claims, 1986)
Fredenburg v. United States
33 Cont. Cas. Fed. 74,503 (Court of Claims, 1986)
Rider v. United States
32 Cont. Cas. Fed. 73,473 (Court of Claims, 1985)
Gunn-Williams v. United States
32 Cont. Cas. Fed. 73,106 (Court of Claims, 1984)
Curley, Inc. v. United States
32 Cont. Cas. Fed. 72,942 (Court of Claims, 1984)
T.J.D. Services, Inc. v. United States
32 Cont. Cas. Fed. 72,871 (Court of Claims, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
31 Cont. Cas. Fed. 72,055, 4 Cl. Ct. 420, 1984 U.S. Claims LEXIS 1494, Counsel Stack Legal Research, https://law.counselstack.com/opinion/palmer-sicard-inc-v-united-states-cc-1984.