Bein v. United States

101 Ct. Cl. 144, 1943 U.S. Ct. Cl. LEXIS 4, 1943 WL 4227
CourtUnited States Court of Claims
DecidedDecember 6, 1943
DocketNo. 44619
StatusPublished
Cited by10 cases

This text of 101 Ct. Cl. 144 (Bein v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bein v. United States, 101 Ct. Cl. 144, 1943 U.S. Ct. Cl. LEXIS 4, 1943 WL 4227 (cc 1943).

Opinions

Whaley, Chief Justice,

delivered the opinion of the court:

The plaintiffs jointly and severally entered into a contract with the United States, through the Assistant Administrator of the Federal Emergency Administration of Public Works, to furnish the materials and perform the work for the construction of the superstructure, including the electrical overhead and underground distribution system, included by “General Work for Base Bid No. 6” for the Brewster Housing Project, No. H-1201, in Detroit, Michigan, in strict accordance with the specifications, schedules, and drawings, for the consideration of $2,971,000.

This housing project consisted of 38 buildings and occupied 7 city blocks in the city of Detroit. On four of the blocks the excavation for and construction of the foundations had been performed by another contractor before the contract with the plaintiffs was entered into. In three other blocks the plaintiffs were to excavate for and construct the foundations and to construct the buildings on the foundations on all of the blocks.

The project was to be completed within 410 calendar days after notice to proceed. The notice was given to plaintiffs on June 25, 1937, which fixed the completion date as August 9,1938, which change orders extended to September 5,1938.

The project was completed on August 11, 1938, 26 days before the completion date as extended. The plaintiffs were paid the sum of $3,001,090.76, which was the contract price plus certain charges which were agreed to by change orders. The plaintiffs executed a release to the defendant excepting in the release two claims for additional payment — (1) for increased cost, loss and damage resulting from heating and steam mains not being located as shown on specifications and drawings and change from heating buildings by heat from the Detroit Edison Compan 7/ to a central heating plant in the sum of $48,000.00; and (2) for reimbursement for money which plaintiffs were required to pay because of charges against site of -work by Public Water Works System of the City of Detroit in the sum of $5,077.41.

[160]*160Plaintiffs seek to recover a muck larger sum in the petition but, having reserved only these two items and stated these several amounts, they are confined to only these specified items and amounts. P. J. Carlin Construction Co. v. United States, 92 C. Cls. 280, 305.

The first item involves the extra costs plaintiffs incurred in furnishing temporary heat. The whole plan as depicted in the contract, drawings, and specifications was conceived and based on the use of steam heat to be furnished by the Detroit Edison Company. This company had mains, vaults, and pipes laid in certain streets in the city of Detroit and furnished steam for the purpose of heating buildings. It was the intention of the defendant to use this system of heating in this project. All the plans, drawings, and specifications specifically show that plaintiffs’ contract was to cover only the plumbing that would connect with this system. The drawings show that a main was in the street adjacent to the project. The contract definitely states that the contractor is to construct a meter vault to this system after it has been brought into the ground of the project and the specifications state

Steam for the heating system will be supplied from the mains of the Detroit Edison Company * * *. Steam service piping will be brought by the Detroit Edison Co. to the point indicated in the meter vault indicated on block 500. The Contractor shall furnish the meter vault, and continue the piping underground to all the buildings * * *.

And the specifications further state

Steam for the heating system will be supplied from the source shown on the drawings, * * *.

The contract drawings plainly show a 14-inch main of the Detroit Edison Company in the street adjacent to the project running into the company’s valve pit in the street and from this main steam was to be brought by a 12-inch pipe into a meter vault on the premises and at a short distance therefrom connected with the Government’s steam main feeding the radiation system.

An investigation or inspection of the site would not have helped the plaintiffs. Had they discovered that the main [161]*161of the Detroit Edison Company was not on the street adjacent to the project that would not have prevented the Detroit Edison Company from erecting the main and bringing its facilities to the property by the time the plaintiffs were ready to make the connections inside the property. When the note on the drawings showed “14" Detroit Edison Co. Main,” it was a reasonable presumption that were the main not there it would be there at the proper time. There are other notes on the drawings such as “D. E. Co. Terminates Steam Main here,” and “Contr. Connects to D. E. Co. Main here.” All these notes gave notice to the plaintiffs that the facilities of the Detroit Edison Company would be available when the connections had been made inside the project for the temporary heat which plaintiffs were to furnish. No examination or inspection of the site would have shown that situation.

Plaintiffs’ work was confined to the distribution of the heating and the connection with the Detroit Edison Company’s main. A permanent heating system, independent of the Edison Company’s is not mentioned in the contract, drawings, or specifications.

Under the instructions to bidders the specifications do provide that bidders are to make their own estimate of the facilities attending the execution of the proposed contract and are notified to visit the site to fully acquaint themselves with conditions as they exist, but, even without these instructions, a bidder looking at the drawings would have come to the conclusion that the main of the Edison Company’s system of heating was adjacent to the project or would be brought to the place marked on the map showing it adjacent to the project.

Before the contract was executed plaintiffs knew that the defendant was negotiating with the Detroit Edison Company for the use of its heating system in the project and plaintiffs subsequently sought terms with this company for the temporary heating.

The defendant and the Detroit Edison Company could not arrive at a satisfactory contract with the result that the defendant changed the plans for the heating system by installing its own plant.

[162]*162The contract for the erection of this plant was given to another company but plaintiffs were given a change order for the installation of return pipe lines. The Detroit-Edison system did not use return pipe lines. The change of the plans of the heating system radically changed the basis on which both parties had contracted. Both believed that the heat could be obtained from the Detroit Edison Company. The defendant based the entire project heating lay-out and advertised for bids with the specifications and drawings based on obtaining heat from the Detroit Edison Company.

The plaintiffs made their bid, executed the contract and went to work relying on these statements. They were justified in making their bid with the understanding that temporary heat could and would be obtained from the Detroit Edison Company and that they would not be required to construct an independent heating plant.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Elgin Builders, Inc. v. United States
29 Cont. Cas. Fed. 81,901 (Court of Claims, 1981)
J. G. Watts Construction Co. v. United States
161 Ct. Cl. 801 (Court of Claims, 1963)
A. L. Coupe Construction Co. v. United States
139 F. Supp. 61 (Court of Claims, 1956)
Wagner Whirler & Derrick Corp. v. United States
121 F. Supp. 664 (Court of Claims, 1954)
Shepherd v. United States
113 F. Supp. 648 (Court of Claims, 1953)
Mitchell Canneries, Inc. v. United States
77 F. Supp. 498 (Court of Claims, 1948)
Loftis v. United States
76 F. Supp. 816 (Court of Claims, 1948)

Cite This Page — Counsel Stack

Bluebook (online)
101 Ct. Cl. 144, 1943 U.S. Ct. Cl. LEXIS 4, 1943 WL 4227, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bein-v-united-states-cc-1943.