Asheville Contracting Co. ex rel. Grantsville Construction Co. v. United States

76 F. Supp. 707, 110 Ct. Cl. 459, 1948 U.S. Ct. Cl. LEXIS 35
CourtUnited States Court of Claims
DecidedApril 5, 1948
DocketNo. 45732
StatusPublished

This text of 76 F. Supp. 707 (Asheville Contracting Co. ex rel. Grantsville Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Asheville Contracting Co. ex rel. Grantsville Construction Co. v. United States, 76 F. Supp. 707, 110 Ct. Cl. 459, 1948 U.S. Ct. Cl. LEXIS 35 (cc 1948).

Opinion

Howell, Judge,

delivered the opinion of the court:

This case involves a claim of the Asheville Contracting Company on behalf of the Grantsville Construction Company, a subcontractor, for certain excavation work and the building of certain retaining walls required under a contract dated April 25, 1936, with the defendant for the grading, draining and construction of two tunnels, a construction of approximately 3.442' miles of the Blue Ridge Parkway from Buck Creek Gap to Big Laurel Mountain, in Yancey and McDowell Counties, North Carolina.

[490]*490There are five separate claims involved, and all of them arise out of and by reason of disputed measurements of quantities. These claims will be discussed separately.

FIRST CAUSE OF ACTION

The facts relating to this item of claim are fully set forth in Findings 15 through 2'4 and need not here be repeated. The head of the department determined that there were 2,228 cubic yards in the slide and that 2,018 were removed by plaintiff’s subcontractor.

In his classification and in awarding values to the work performed, Thomas H. MacDonald, Commissioner of Public Eoads, representing the head of the department, sustained the contracting officer by classifying the removal of 1,500 cubic yards of the 2,013 cubic yards, under item 2 of the contract at 49 cents per cubic yard. He also added 513 cubic yards under item 4, unclassified excavation for structures, at $1 per cubic yard.

There is no provision in the specifications under the heading “excavation for structures,” providing payment for the removal of slide material. However, under the general provision, “contractor’s responsibility for work,” provision is made that the contractor shall rebuild, repair, restore, and make good all damages to any portion of the work except, among other things “slides found by the engineer to have been unavoidable.” This slide was determined to have been unavoidable.

Under “Sections accepted for traffic,” page 4, paragraph 2 of the specifications, it is provided that any parts of the highway which have been completed and “accepted for traffic” by the project engineer, shall not be the responsibility of the contractor to maintain, and that the work performed thereon would be compensated for in the manner provided in “extra and force-account work,” “providing, however, that any slides that may occur on such sections previous to completion and acceptance of the entire project shall be removed by the contractor at the unit price per cubic yard for unclassified excavation.” [Italics supplied.] It is our determination that the contracting officer in applying the rate provided under this section is in error.

[491]*491The foregoing provisions relating to slides concerns only those portions of the highway which, had been completed and accepted by the project engineer. Nothing contained therein is found applicable to slides occurring on uncompleted work, such as the slide described in Findings 15 to 25, inclusive.

The slide which occurred at station 444 refilled that portion of the trench in which no masonry construction had been performed. It also piled material higher than the original grade line, both over the trench area, and behind the portion of the wall which had been partially completed, and also a small portion overflowing the construction area was deposited below the trench.

Plaintiff’s subcontractor not only excavated the material which landed in the trench where previous excavation had been performed, and which MacDonald found represented excavation for structure, but it also excavated material which had piled up to a greater height than the original grade line, .as well as material which lodged upon the portion of the completed wall and back of it. It was necessary to reexca-vate back of the completed portion of the retaining wall for the reason that this wall had not properly cured, and under the specifications backfilling was not permitted, except upon the direction of the project engineer. In the case of concrete or masonry work, of which the retaining wall was constructed, backfilling was preferably not to be ordered until the masonry had been in place 21 days.

Accordingly, plaintiff’s subcontractor excavated the 2,013 cubic yards of material for the purpose of uncovering the completed portion of the wall and removing pressure from behind it as well as the reexcavation of the trench in order to complete the remainder of the retaining wall.

It is our determination that all of this excavation represented “unclassified excavation for structures” under item 4 of the contract.

Plaintiff was directed by the project engineer to replace behind the completed wall approximately one-half of the slide material excavated after the wall had cured.

MacDonald found, in accordance with item 25 of the contract, that only the material representing “excavation for [492]*492structures” could be paid for as “special disposition of unclassified excavation for structures” (Finding 23). This item of the contract does not provide for the replacement of unclassified excavation under item 2.

Plaintiff having excavated 2,013 cubic yards of this slide material and having restored at least one-half of this amount for the embankment of the wall, would be entitled to the payment for this one-half or 1,006 cubic yards as special disposition under item 25 of the contract, at 50 cents per cubic yard.

Besult of Slide_ 2,223 Cubic Yards
Head of department determined that 2,013 cubic yards were excavated by plaintiff’s subcontractor. This determination seems to be accepted by all parties, as it was also by the commissioner.
Final determination by the head of the department:
513 cubic yards reexcavated from the trench and allowed under item 4, at $1 per cubic yard_$513.00
1,500 cubic yards excavated from behind the trench, between trench and mountain in order to save the uncured wall, under item 2, at 50 cents_ 735.00
500 cubic yards which, as shown above, was rehandled and reexcavated from the trench, was, by direction of defendant’s project engineer, rehandled and placed behind the wall — allowed under item 25 at 50 cents_ 256.50
1,504.50
2,013 cubic yards.
210 cubic yards fell down the side of the mountain and not rehandled.
2,223 cubic yards total slide.
Commissioner’s report gives the subcontractor—
2,013 cubic yards at $1 per cubic yard_$2,013.00
1,006 cubic yards at 50 cents_ 503.00
2, 516.00
Less amount already paid_ 1,504.50
Amount plaintiff is entitled to recover_ 1,011.50

SECOND AND FOURTH CAUSES OF ACTION

The second and fourth causes of action involve claims for an additional quantity of excavation for cement stone masonry walls and for an additional quantity of cement stone [493]*493masonry wall constrnctin. They are, therefore, considered together.

Under the supervision of H. C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rego Building Corp. v. United States
99 Ct. Cl. 445 (Court of Claims, 1943)
Bein v. United States
101 Ct. Cl. 144 (Court of Claims, 1943)

Cite This Page — Counsel Stack

Bluebook (online)
76 F. Supp. 707, 110 Ct. Cl. 459, 1948 U.S. Ct. Cl. LEXIS 35, Counsel Stack Legal Research, https://law.counselstack.com/opinion/asheville-contracting-co-ex-rel-grantsville-construction-co-v-united-cc-1948.