Loftis v. United States

76 F. Supp. 816, 110 Ct. Cl. 551
CourtUnited States Court of Claims
DecidedApril 5, 1948
Docket46078
StatusPublished
Cited by34 cases

This text of 76 F. Supp. 816 (Loftis v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Loftis v. United States, 76 F. Supp. 816, 110 Ct. Cl. 551 (cc 1948).

Opinion

LITTLETON, Judge.

Plaintiff brought this suit under a unit price contract with defendant to recover additional compensation in the total amount of $904,390.98 which he alleges became due him under the terms of the equitable adjustment provisions of Article 4 of the contract, quoted in finding 21. It is claimed that this amount, computed at $1.50 per cubic yard as a fair price for certain excavation, less 37 cents per cubic yard paid, should be allowed by reason of unknown and latent subsurface conditions encountered during performance of the contract *818 which necessitated a large amount of additional and more expensive work of excavating and rehandling, upon written order of defendant, 800,346 cubic yards of subsurface wet and muck materials. It is insisted that this work of excavating subsurface materials of the character and in the amount encountered was not contemplated by the contract nor included in the original contract unit price of 37 cents per cubic yard for the excavation indicated and called for in the specifications and drawings; that an examination and investigation of conditions at the site did not disclose that any such excavation would be necessary or that the unstable subsurface conditions subsequently encountered existed; that the subsurface conditions discovered were unknown conditions of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inhering in embankment fill construction work of the character provided for in the plans and specifications; that the conditions encountered could not reasonably be anticipated or foreseen from a thorough examination of the site, and were not discovered by the best investigation of the conditions at the site, which it was possible to make with the facilities available and within the time allowed prior to the submission of bids.

Defendant denies that “Changed conditions,” within the meaning of Article 4, were encountered and has also filed a counterclaim for certain alleged excess excavation allowances and overpayments at the contract rate.

On September 1, 1942, defendant issued an invitation for unit price bids to be submitted by September 7, 1942, on the basis of written specifications, drawings and the standard Government form of construction contract, without the standard provision for “Liquidated damages.” Plaintiff’s bid, submitted September 6, was accepted. On the following day, the contract was awarded to plaintiff and the standard contract dated September 7, 1942, was executed by the parties. The contract, in Article 1, made the specifications and drawings a part thereof but such documents became a part of the contract subject to the express provisions in the several articles of such contract. Plaintiff commenced work September 10, 1942.

The work called for by the contract documents consisted of the enlargement of the existing airfield at the Charleston Bomber Command Station, located about ten miles northwest of Charleston, South Carolina, by extending each of the three existing runways a distance of 2,500 feet and the construction of embankment fills for such runways and, also, for certain additional taxiways and hardstand parking areas.

As shown in the specifications and indicated on the drawings, this work involved certain clearing and grubbing, grading excavation, borrow excavation, construction of embankment fills, paving and the construction of miscellaneous buildings.

The main question in the case concerning “Changed conditions” first arose about October 27, 1942, in connection with the grading excavation and constructing embankment fills for the NE-SW runway extension and taxiway 5. Subsurface excavation in other construction areas is also involved in the claim, but the subsurface conditions encountered in the NE-SW runway and taxiways 1 and 5, will be first discussed.

The other questions in the case relate, first, to the finality of the decisions of the contracting officer and the Board of Contract Appeals, representing the Secretary of War, which held “Changed conditions” within the meaning of Article 4 had not been encountered, second, to a fair price for the additional work, and third, to the three items of the counterclaim.

The quantities and character of the subsurface materials excavated and rehandled were not in dispute before the contracting officer and the Board of Contract Appeals, and are not in dispute here except as to an amount of 180,288 cubic yards involved in one item of defendant’s counterclaim.

Near the conclusion of the work the contracting officer had a determination made by several of his engineers in cooperation with plaintiff and his engineers of the quantities of subsurface materials excavated and rehandled, which he approved for the purpose of payment. He also made decisions, *819 on the basis of which he made payments, of the amounts of excavation (not relating to the “Changed conditions”) involved in the other two items of the counterclaim. The contract made the contracting officer’s decisions conclusive as to questions of fact and this included decisions as to quantities, and defendant’s proof in support of its counterclaim is not sufficient to show that any of the decisions so made were erroneous.

The information shown in the specifications, the pertinent provisions of which are set forth in findings 17-20, and indicated on' the drawings or plans, was based on surface conditions and measurements in the several new construction areas, and such specifications and drawings contained no representation or information relative to, or concerning the nature or character of subsurface conditions, nor did they disclose or indicate that it was believed or suspected that there existed any unstable subsurface conditions that would or might require subsurface excavation beyond draining and clearing the surfaces of certain pools of water, the surface debris and decayed vegetation in the embankment construction areas. The defendant had made no subsurface examinations or explorations in any of the construction areas, except at one point near station 50 where the original NE-SW runway ended, but this point was not within the so-called strip mine area. That boring had been made, in connection with drainage, soon after the completion of the original airfield, but it disclosed a firm and impervious subsurface of gumbo material. Therefore, defendant’s engineers and contracting officers, who made the surveys and prepared the specifications and plans for the new construction work, were not in possession of any information and did not possess knowledge of any facts concerning the character or quality of the subsurface materials and conditions in the strip mine section of the construction areas of the NE-SW runway extension and taxiways 1 and 5, where plaintiff encountered unforeseen and unstable subsurface conditions after considerable excavation and embankment construction work had been performed.

By reason of the subsurface conditions encountered in these areas it was necessary for plaintiff to excavate and rehandle, pursuant to a written order finding changed conditions, approximately twenty-four times the total amount of excavation estimated by defendant in such areas as indicated on the plans and as estimated by plaintiff after his investigations of the ground conditions.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Youngdale & Sons Construction Co. v. United States
38 Cont. Cas. Fed. 76,467 (Federal Claims, 1993)
Servidone Construction Corp. v. United States
36 Cont. Cas. Fed. 75,797 (Court of Claims, 1990)
Consolidated Diesel Electric Co. v. United States
533 F.2d 556 (Court of Claims, 1976)
Ray D. Bolander Co. v. United States
186 Ct. Cl. 398 (Court of Claims, 1968)
Morrison-Knudsen Company, Inc. v. The United States
397 F.2d 826 (Court of Claims, 1968)
State, Department of Highways v. A & G Excavating Co.
421 P.2d 309 (Alaska Supreme Court, 1966)
Thompson Ramo Wooldridge Inc. v. The United States
361 F.2d 222 (Court of Claims, 1966)
Schutt Construction Co. v. United States
353 F.2d 1018 (Court of Claims, 1965)
Schutt Construction Company, Inc. v. United States
353 F.2d 1018 (Court of Claims, 1965)
A. Teichert & Son, Inc. v. State of Cal.
238 Cal. App. 2d 736 (California Court of Appeal, 1965)
Farnsworth & Chambers Co., Inc. v. The United States
346 F.2d 577 (Court of Claims, 1965)
The Jack Stone Company, Inc. v. The United States
344 F.2d 370 (Court of Claims, 1965)
Kaiser Industries Corporation v. The United States
340 F.2d 322 (Court of Claims, 1965)
Hol-Gar Manufacturing Corp. v. The United States
351 F.2d 972 (Court of Claims, 1965)
H. L. Yoh Co., Inc. v. United States
288 F.2d 493 (Court of Claims, 1961)
H. L. Yoh Co. v. United States
153 Ct. Cl. 104 (Court of Claims, 1961)
Fehlhaber Corp. v. United States
151 F. Supp. 817 (Court of Claims, 1957)
Fehlhaber Corporation v. United States
151 F. Supp. 817 (Court of Claims, 1957)

Cite This Page — Counsel Stack

Bluebook (online)
76 F. Supp. 816, 110 Ct. Cl. 551, Counsel Stack Legal Research, https://law.counselstack.com/opinion/loftis-v-united-states-cc-1948.