The Jack Stone Company, Inc. v. The United States

344 F.2d 370, 170 Ct. Cl. 281, 1965 U.S. Ct. Cl. LEXIS 92
CourtUnited States Court of Claims
DecidedApril 16, 1965
Docket312-62
StatusPublished
Cited by44 cases

This text of 344 F.2d 370 (The Jack Stone Company, Inc. v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Jack Stone Company, Inc. v. The United States, 344 F.2d 370, 170 Ct. Cl. 281, 1965 U.S. Ct. Cl. LEXIS 92 (cc 1965).

Opinion

DAVIS, Judge. 1

This is a contract case which is before the court on cross-motions for summary judgment. The plaintiff complains that in its performance under a contract for electrical work at the National Institutes of Health, Bethesda, Maryland — entered into between the plaintiff and the General Services Administration — it was required to install certain brand-name items it alleges were more costly than similar items manufactured by another firm which were equal to the other and permitted under the terms of the contract. It is said that the contracting officer’s refusal, sustained by the Board of Review of the General Services Administration, to allow the use of the alternate items was contrary to the agreement, capricious, arbitrary, and not supported by substantial evidence. We have before us the entire record on which the action of the Board of Review was taken, including the briefs of the parties.

Two main questions are presented. First, did the contract require the installation of the brand-name items, or stated conversely, did it permit the use of alternate “equal” items? Second, is the adverse action by the Board of Review final and conclusive against the plaintiff under the terms of the Wunderlich Act ?

In August 1960, the Public Buildings Service of the General Services Administration issued an invitation to bid on a project covering the modernization of the electric power and alarm system at the National Institutes of Health. The plaintiff was the successful bidder under this invitation.

*372 The printed general conditions which were included in the contract specifications contained a provision entitled “Standard References” which reads, in part, as follows:

“1-19. STANDARD REFERENCES * * * * *
“(c) Reference in the specifications to any article, device, product, materials, fixture, form or type of construction by name, make, or catalog number, shall be interpreted as establishing a standard of quality, and not as limiting competition. The Contractor may make substitutions equal to the items specified if approved in advance in writing by the Contracting Officer. * * * ”

Section 16 of the specifications related to the fire alarm system. Paragraph 16-3 provided as follows:

“16-3. GENERAL. — The Contractor shall furnish all labor and materials necessary to install complete all additions and revisions to the existing Fire Alarm System as herein specified and as shown on Drawings Nos. 27-207 through 27-218. The existing system is of Sper-ti Faraday manufacture. All new equipment and parts furnished shall be of the same manufacturer to insure full and satisfactory performance of the completed system.”

There was a reference to Sperti Faraday items in sixteen of the «paragraphs of section 16 on the fire alarm system.

In August 1960, when it saw the invitation, the plaintiff apparently requested from the Sperti Faraday firm a quotation on the materials necessary for the fire alarm and watch report systems. It received such a quotation by the end of August, but it did not base its bid on that amount but on a lower sum for which it estimated that it could obtain the equipment. The contract was dated October 13, 1960, and the notice to proceed came on October 21, 1960. There was a year to do the work.

On January 31, 1961, the defendant wrote to the plaintiff requesting that it submit, as required by the specifications, a list of material which the plaintiff intended to use in its performance of the work. The plaintiff submitted some information, apparently in response to this letter, which included the contractor’s shop drawings, showing the use of equipment for the fire alarm and watch report systems which was manufactured by American District Telegraph Company (A.D.T.). On February 21, 1961, the plaintiff was advised that the material lists and catalogue materials showing the A.D.T. items for the fire alarm and watch report systems were not approved because the material “ * * * does not comply with the specifications.” On March 9, 1961, the plaintiff wrote to the contracting officer requesting, in effect, reconsideration of the A.D.T. material and approval of its use. The letter complained that the plaintiff considered the price quoted by Sperti Faraday to be very much out of line. The contracting officer replied, on March 21, 1961, in the following terms:

“This is in reply to your letter of March 9, 1961, relative to your request to substitute the use of A.D.T. Co. components in the renovation of the existing Sperti-Faraday fire alarm and watchman report systems and in the installation of related extensions and additions in the various buildings at the National Institutes of Health, Bethesda, Md.
“We have investigated this matter and have determined that the renovation and the related extensions and additions using different manufacturer’s components in conjunction with the - existing fire alarm and watchman report systems, will not satisfy the requirements of the Government.
“You are, therefore, instructed to proceed with the use of Sperti-Fara-day equipment and services as indicated and as specified under the contract requirements.”

*373 The plaintiff countered with a proposition that it use Sperti Faraday material on some of the work (the individual fire alarm systems) but that it would use A.D.T. equipment on the balance (the central system). On April 12, 1961, the contracting officer wrote to the plaintiff directing that it proceed with the work using Sperti Faraday equipment as it had been instructed by the defendant’s March 21 letter. The plaintiff was told that this was the final decision of the contracting officer and that it had the right of appeal under the disputes clause of the contract.

On April 17, 1961, the plaintiff, by counsel, appealed the contracting officer’s decision of April 12, 1961, to the Administrator of the General Services Administration. The appeal was heard for the Administrator by the G.S.A. Board of Review (on June 20, 1961) and was denied on August 16, 1962, While the appeal was pending, plaintiff used Sperti Faraday products to complete performance.

The basis for the Board’s rejection of the appeal was that the specifications expressly called for the Sperti Faraday material, that in the planning stage it had been decided that the fire alarm system should be of one manufacturer — a system manufactured by one company as distinguished from a mixed system comprised of equipment produced by more than one manufacturer. Various factors were pointed out by the decision as believed to be of importance in restricting the specifications to the one manufacturer, including reliability, protection and maintenance. While the Board did not affirmatively find that the A.D.T. equipment was equal to the Sperti Faraday equipment, it found that the record did not indicate that the Government considered it unequal or inadequate. The provisions of paragraph 1-19 of the general conditions of the specifications, supra, were held to be permissive. Since the contracting officer felt that the work in question required the use of Sperti Faraday products, the refusal of the contracting officer to approve the substitute could not, said the Board, be arbitrary and capricious.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gilbert Solutions, LLC
Armed Services Board of Contract Appeals, 2023
Carothers Construction, Inc.
Armed Services Board of Contract Appeals, 2021
P.W. Construction, Inc. v. United States
53 F. App'x 555 (Federal Circuit, 2002)
Interstate General Government Contractors, Inc. v. United States
42 Cont. Cas. Fed. 77,314 (Federal Claims, 1998)
Florida Bd. of Regents v. Mycon Corp.
651 So. 2d 149 (District Court of Appeal of Florida, 1995)
C. Sanchez & Son, Inc. v. United States
37 Cont. Cas. Fed. 76,152 (Court of Claims, 1991)
J.L. Malone & Associates, Inc. v. The United States
879 F.2d 841 (Federal Circuit, 1989)
Baltimore Contractors, Inc. v. United States
34 Cont. Cas. Fed. 75,267 (Court of Claims, 1987)
Interstate Coatings, Inc. v. United States
32 Cont. Cas. Fed. 73,208 (Court of Claims, 1985)
E. A. Berman Co. v. City of Marlborough
419 N.E.2d 319 (Massachusetts Appeals Court, 1981)
American Electric Contracting Corp. v. United States
579 F.2d 602 (Court of Claims, 1978)
James A. Mann, Inc. v. United States
535 F.2d 51 (Court of Claims, 1976)
Consolidated Diesel Electric Co. v. United States
533 F.2d 556 (Court of Claims, 1976)
Kenneth Reed Construction Corp. v. United States
475 F.2d 583 (Court of Claims, 1973)
California-Pacific Utilities Co. v. United States
194 Ct. Cl. 703 (Court of Claims, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
344 F.2d 370, 170 Ct. Cl. 281, 1965 U.S. Ct. Cl. LEXIS 92, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-jack-stone-company-inc-v-the-united-states-cc-1965.