P.W. Construction, Inc. v. United States

53 F. App'x 555
CourtCourt of Appeals for the Federal Circuit
DecidedDecember 12, 2002
DocketNo. 02-5038
StatusPublished

This text of 53 F. App'x 555 (P.W. Construction, Inc. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
P.W. Construction, Inc. v. United States, 53 F. App'x 555 (Fed. Cir. 2002).

Opinion

RADER, Circuit Judge.

In a bench ruling, the United States Court of Federal Claims awarded P.W. Construction, Inc. (PWCI) money damages in connection with a construction contract. Because the record does not support the grant of damages for lost productivity, additional landscaping, and additional pipe, this court vacates those awards. Because the trial court erred in holding the Government liable for PWCI’s above-bid costs incurred to secure valves under the contract, this court reverses the grant of damages on that issue. Accordingly, this court vacates-in-part, reverses-in-part, and remands.

The Government awarded PWCI a fixed-price contract for the installation of natural gas pipe, valves, meters, and pressure stations at Vandenberg Air Force Base in California. During performance of the contract work, PWCI encountered unexpected underground obstructions. PWCI alleged that these obstructions delayed project completion and increased completion costs. PWCI sued the Government for $1,700,000 in damages. Following closing arguments, the Court of Federal Claims ruled from the bench, finding the Government hable for lost productivity, additional landscaping, and additional pipe used to route around the obstructions. The court also found the Government liable for additional costs incurred because the Government refused to allow PWCI to substitute KOSO earthquake valves for the required Quake Master valves.

DISCUSSION

This court reviews the Court of Federal Claims’ factual findings for clear error, Hankins Const. Co. v. United States, 838 F.2d 1194, 1195 (Fed.Cir.1988), and its legal determinations without deference, Dairyland Power Coop. v. United States, 16 F.3d 1197, 1201 (Fed.Cir.1994). The trial court’s selection of a method for determining damages is a legal question, which this court reviews “non-deferentially on the basis of reasonableness.” Dawco Const., Inc. v. United States, 930 F.2d 872, 880 (Fed.Cir.1991), rev’d in non-relevant part by Reflectone, Inc. v. Dalton, 60 F.3d 1572 (Fed.Cir.1995). This court reviews damage calculations by the Court of Federal Claims for an abuse of discretion. Hughes Communications Galaxy, Inc. v. United States, 271 F.3d 1060, 1065 (Fed. Cir.2001). A trial court abuses its discretion when: “(1) the court’s decision is clearly unreasonable, arbitrary or fanciful; (2) the decision is based on an erroneous construction of the law; (3) the trial court’s factual findings are clearly erroneous; or (4) the record contains no evidence [557]*557upon which the trial court rationally could have based its decision.” Id.

Court of Federal Claims Rule 52 states that “[i]n all actions tried upon the facts, the court shall find the facts specially and state separately its conclusions of law thereon.” See also Fed.R.Civ.P. 52(a) (2002). The purpose of this rule is, inter alia, to provide this court with an adequate basis for meaningful review. Cf. Pretty Punch Shoppettes, Inc. v. Hauk, 844 F.2d 782, 784, 6 USPQ2d 1563, 1565 (Fed.Cir.1988). Thus, the Court of Federal Claims may not merely state its findings in conclusory terms, but must provide sufficient explanation as to how it reached its conclusions on pertinent factual and legal issues. This court may not speculate about the trial court’s ultimate findings of fact or conclusions of law. If the Court of Federal Claims does not state a decision in terms sufficient for meaningful review, this court generally will vacate. Cf. Gechter v. Davidson, 116 F.3d 1454, 1458 (Fed.Cir. 1997).

Using the measured mile method, PWCI’s expert, David Ough, presented an estimate of PWCI’s lost productivity attributed to the underground obstructions. Based on his calculations, he testified that PWCI was entitled to $505,120.37 in lost productivity. Using Mr. Ough’s productivity rates, the Court of Federal Claims determined that PWCI was entitled to $260,830.10 in lost productivity. Although the trial court’s calculations corrected a mathematical error in Mr. Ough’s estimate, the trial court still relied on Mr. Ough’s productivity rates for its calculations. Based on Mr. Ough’s rates, the trial court found the Government liable for 48% of PWCI’s labor hours. Those rates, however, have several problems.

The primary problem with the productivity rates is that they do not compare equivalent types of work. See Thomas E. Shea, Proving Productivity Losses in Government Contracts, 18 Pub. Cont. L.J. 414, 426 (1989) (“The type of work must be equivalent for the pre- and post-disruption periods in order to allow a fair comparison. It would not be valid to compare the rate for the production of large widgets during the pre-disruption (normal) period with the production of smaller widgets during the disruption period.”). The pre-disruption period rate in this case did not include intensive welding and trenching work performed by subcontractors, but the impaired rate included such work. Additionally, the rates did not consider whether productivity would be affected if PWCI used steel versus polyethylene pipe. The trial court recognized this problem, but did not correct for the error.

The record shows that welding in the impaired period was butt-welding on polyethylene pipes, which takes only 15 seconds to 2 minutes per weld, whereas the welding done in the pre-disruption period was steel welding, which may take up to 2.69 hours per weld. Without more, this evidence suggests that a comparison of the pre-and post-disruption periods must take into account the difference in welding costs. To account for this difference, Mr. Ough deleted both the welding work and the trenching work from the pre-disruption rate and left both kinds of work in the post-disruption period. Mr. Ough’s deletion thus yields a rate that reflects a higher productivity than actually enjoyed by PWCI. PWCI argues that this deletion from the ideal rate has a negligible impact on the overall productivity rates.

In the first place, Mr. Ough’s calculation deleted trenching work from the ideal period, but included the same work in the impaired period. Furthermore, Mr. Ough’s method deleted all welding time from the ideal period, but included the butt-welding time in the impaired period. [558]*558The two periods thus have not made a correct comparison, as acknowledged by the trial court, which nonetheless used these rates to calculate damages. Indeed, the Government submitted unrebutted evidence that adding the welding costs back into the ideal period yields an ideal rate of 0.171 hours per linear foot, a rate very close to the impaired rate. This testimony suggests that the inclusion of welding and trenching costs for the different pipes is not negligible.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
53 F. App'x 555, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pw-construction-inc-v-united-states-cafc-2002.