Dairyland Power Cooperative v. United States

16 F.3d 1197, 39 Cont. Cas. Fed. 76,618, 1994 U.S. App. LEXIS 2632, 1994 WL 43495
CourtCourt of Appeals for the Federal Circuit
DecidedFebruary 15, 1994
Docket93-5131
StatusPublished
Cited by203 cases

This text of 16 F.3d 1197 (Dairyland Power Cooperative v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dairyland Power Cooperative v. United States, 16 F.3d 1197, 39 Cont. Cas. Fed. 76,618, 1994 U.S. App. LEXIS 2632, 1994 WL 43495 (Fed. Cir. 1994).

Opinion

CLEVENGER, Circuit Judge.

Dairyland Power Cooperative appeals the March 29, 1993 judgment of the United States Court of Federal Claims dismissing its complaint for failure to state a claim upon which relief can be granted. In ruling on the parties’ cross-motions for summary judgment, the Court of Federal Claims held as matters of law that Dairyland’s execution of a valid release discharging the Government from liability barred Dairyland’s claim for contract damages and that the absence of mutual mistake of fact barred Dairyland’s claim for contract reformation. Dairyland Power Coop. v. United States, 27 Fed.Cl. 805 (1993). We affirm.

I

This ease involves a contract executed on June 6,1962 between Dairyland and the U.S. Atomic Energy Commission (AEC) pursuant to which Dairyland on November 1, 1969 began operating a nuclear reactor plant constructed by AEC on a site owned by Dairy-land near LaCrosse, Wisconsin. This contract obligated Dairyland to purchase the steam produced by the 50-megawatt LaCrosse boiling water nuclear reactor plant and to operate an adjacent turbine-generator facility constructed by Dairyland to convert the steam into electricity. The 1962 contract also provided for the offer for sale of the LaCrosse plant to Dairyland at AEC’s option after November 1, 1974 at the price of “the cost of construction [of the reactor plant] ... less appropriate depreciation.” If Dairyland chose not to purchase the LaCrosse plant, the contract permitted AEC to dismantle the reactor plant subject to “mak[ing] the reactor site safe from the public health and safety standpoint.”

In 1971, AEC began negotiating with Dairyland for the early sale of the LaCrosse plant after determining that AEC’s “most pressing reactor development efforts” no longer included its participation in the LaCrosse project. Although the parties reached an agreement for the purchase of the LaCrosse plant by Dairyland for $2.75 million, Dairyland later declined to execute this agreement because it had originally underestimated the $2.7 million minimum cost actually required to obtain a full-term operating license. Ultimately, AEC and Dairyland executed a modification to the 1962 contract on August 6, 1973 (the 1973 sale contract), in which AEC agreed to convey title in the reactor plant, two nuclear fuel cores, and spare parts to Dairyland for one dollar. Despite the dramatic reduction in this purchase price from that contemplated in the 1971 negotiations, AEC’s justification for the sale was its relief of “the [Government’s] financial responsibility under the [1962] contract for the cost of operating and possibly decommissioning [the LaCrosse] reactor which has no further ... value [to AEC’s reactor development mission].” The 1973 sale contract provided that upon the sale and transfer of title to the LaCrosse plant, the 1962 contract “shall thereupon cease to be effective and neither [Dairyland] nor the Government shall thereafter have any further rights or obligations thereunder.”

AEC recognized that the LaCrosse plant’s operational efficiency at the time of the 1973 sale contract made its economic value marginal compared to that of a fossil-fuel plant of similar size. AEC postulated, however, that if Dairyland could reduce costs through operating economies, Dairyland could offset its initial costs of plant modifications required to obtain a full-term operating license and continue operation of the LaCrosse plant. *1200 Nonetheless, AEC admitted that “[i]n view of the nature of the risks assumed by [Daiiy-land] under the terms of the [1973 sale contract], the sale of the [LaCrosse] plant ... would not appear to result in a windfall to [Dairyland].” AEC noted the potential consequences for Dairyland to include the reduction of the plant’s economic value to zero, the loss of use of the $7 million turbine-generator facility constructed by Dairyland, and the costs associated with decommissioning the LaCrosse plant. On the other hand, Dairy-land also appreciated the implications of the sale, commenting that its purchase of the LaCrosse plant was “a calculated risk, a gamble ... that [Dairyland] can make this plant perform economically, for our power system.”

Dairyland’s commercial operation of the LaCrosse plant began on February 1, 1971. AEC granted Dairyland a provisional operating license on August 28, 1973. Although Dairyland applied for a full-term operating license on October 9, 1974, Dairyland never received such a license because it did not complete work necessary to bring the LaCrosse plant into compliance with safety standards set forth by the U.S. Nuclear Regulatory Commission (NRC). Dairyland permanently ceased operation of the LaCrosse plant on April 30, 1987.

In addition to the LaCrosse plant, Dairy-land purchased the reactor’s two nuclear fuel cores, which had an estimated value of $5.2 million after the costs of reprocessing the spent nuclear fuel contained in the cores into new usable nuclear fuel. Neither the original 1962 contract nor the 1973 sale contract, however, contained' any reference to spent nuclear fuel reprocessing or disposal. At the time of the 1973 sale contract, Nuclear Fuel Services, Inc. (NFS) operated the only licensed commercial nuclear fuel reprocessing plant in the United States. Moreover, even NFS had suspended its reprocessing activity by then.

On March 14, .1975, Dairyland contracted ■with NFS for spent nuclear fuel reprocessing and storage with the understanding that 1988 would be the earliest possible date for resumption of reprocessing. Dairyland and NFS, however, agreed to terminate the fuel reprocessing portion of the contract in a contract modification on September 15, 1976. On April 7,1977, President Carter suspended indefinitely commercial reprocessing of nuclear fuel. Although President Reagan lifted the ban on commercial reprocessing on October 8, 1981, the reprocessing industry never revived.

Regarding nuclear fuel disposal, Congress established a Department of Energy (DOE) program in January 1983 for the permanent storage at federal repositories of spent fuel assemblies from commercial nuclear reactor plants. Nuclear Waste Policy Act of 1982, Pub.L. No. 97-425, 96 Stat. 2201 (1983) (codified at 42 U.S.C. §§ 10101-10226 (1988)). The earliest projected start of DOE storage operations, however, was the year 2010. The decommissioning plan for the LaCrosse plant approved on August 7, 1991 by the NRC required Dairyland to continue on-site storage of its spent fuel assemblies in compliance with the NRC’s SAFSTOR guidelines. Dairyland estimates that SAFSTOR storage of its spent fuel assemblies until 2011, and the subsequent decommissioning of the LaCrosse plant, will cost over $97 million.

II

On October 12, 1990, Dairyland submitted to DOE an initial claim pursuant to the Contract Disputes Act of 1978 (CDA), 41 U.S.C. § 609(a)(1) (1988), seeking rescission of the 1973 sale contract, or contract damages in the alternative. The DOE Contracting Officer (CO) denied the claim without issuing a decision, determining that the claim was not cognizable under the CDA Dairyland resubmitted its claim on May 1, 1991, and provided additional support for its claim on September 18,1991. Before the CO issued a final decision on Dairyland’s claim, however, Dairyland filed suit in the U.S.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shoreline Foundation, Inc.
Armed Services Board of Contract Appeals, 2024
GSI Construction Corp.
Armed Services Board of Contract Appeals, 2024
Chugach Federal Solutions, Inc.
Armed Services Board of Contract Appeals, 2023
Assad v. United States
Federal Claims, 2023
Dynamic Systems Technology, Inc.
Armed Services Board of Contract Appeals, 2023
Spellers v. United States
Federal Claims, 2021
Lind v. United States
W.D. Washington, 2021
StarKist Co. v. United States
485 F. Supp. 3d 1362 (Court of International Trade, 2020)
Crawley v. United States
Federal Claims, 2020
The Kalencom Corp. v. United States
450 F. Supp. 3d 1318 (Court of International Trade, 2020)
Halim v. United States
Federal Circuit, 2020
CLC Construction Company
Armed Services Board of Contract Appeals, 2020
Castillo v. United States
952 F.3d 1311 (Federal Circuit, 2020)

Cite This Page — Counsel Stack

Bluebook (online)
16 F.3d 1197, 39 Cont. Cas. Fed. 76,618, 1994 U.S. App. LEXIS 2632, 1994 WL 43495, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dairyland-power-cooperative-v-united-states-cafc-1994.