North American Landscaping Construction & Dredge Company, Inc. v. United States

CourtUnited States Court of Federal Claims
DecidedApril 30, 2020
Docket17-903
StatusPublished

This text of North American Landscaping Construction & Dredge Company, Inc. v. United States (North American Landscaping Construction & Dredge Company, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
North American Landscaping Construction & Dredge Company, Inc. v. United States, (uscfc 2020).

Opinion

Case 1:17-cv-00903-PEC Document 41 Filed 04/30/20 Page 1 of 6

Corrected

In the United States Court of Federal Claims No. 17-903C

(E-Filed: April 30, 2020)

) NORTH AMERICAN LANDSCAPING, ) CONSTRUCTION AND DREDGE ) COMPANY, INC., ) Summary Judgment; RCFC 56; ) Contract Interpretation. Plaintiff, ) ) v. ) ) THE UNITED STATES, ) ) Defendant. ) ) )

Joseph L. Katz, Bethesda, MD, for plaintiff.

Daniel B. Volk, Trial Attorney, with whom were Joseph H. Hunt, Assistant Attorney General, Robert E. Kirschman, Jr., Director, and Elizabeth M. Hosford, Assistant Director, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washington, DC, for defendant. Mark R. Higgins, United States Army Corps of Engineers, Norfolk, VA, of counsel.

OPINION

CAMPBELL-SMITH, Judge.

This matter is before the court on defendant’s second motion for summary judgment, pursuant to Rule 56 of the Rules of the United States Court of Federal Claims (RCFC), ECF No. 30, and plaintiff’s cross-motion for summary judgment, ECF No. 36. Defendant filed a response/reply brief, ECF No. 37, and plaintiff filed a reply, ECF No. 39. The parties also relied on, and therefore the court also considered, the appendix filed in support of defendant’s first motion for summary judgment, ECF No. 12-1. This matter is fully briefed and ripe for decision. For the reasons set forth below, defendant’s second motion for summary judgment is GRANTED, and plaintiff’s cross-motion is DENIED. Case 1:17-cv-00903-PEC Document 41 Filed 04/30/20 Page 2 of 6

I. Background

This case arises out of a contract between plaintiff and the United States Army Corps of Engineers for maintenance dredging of a creek in Virginia.1 See ECF No. 30 at 2. Plaintiff was to be paid for the dredging work according to the quantity of material removed from the creek bed, which was to be determined from analyzing survey data. See id.; see also ECF No. 12-1 at 129. The contract terms provide that the amount of material to be paid for would be:

measured by the cubic yard in place by computing the volume between the bottom surface shown by soundings of the last surveys made before dredging, and the bottom surface shown by the soundings of surveys made as soon as practicable after the work has been completed.

ECF No. 12-1 at 129. The contract further provides that the contractor’s unit price for each cubic yard of material would “include his evaluation of shoaling, other natural changes in the waterway, or changes caused by the Contractor’s operations that might occur during the period between the surveys before dredging and the surveys for acceptance of the work.” Id. at 130.

The contract also provided a process for defendant to accept the work and finalize the calculation of material removed. See id. at 329. Fourteen days prior to completion of the work, plaintiff was to request an “After Dredging Survey” from the contracting officer “to ensure prompt performance of the after dredging acceptance surveys.” Id. If the after-dredging acceptance survey discovered “any shoals, lumps, or other lack of contract depth, . . . the Contractor [would] be required to remove [the] same by dredging at the contract rate for dredging.” Id. The government was to fund the full cost of the survey unless more than two were required “by reason of work for the removal of shoals disclosed at a prior sounding.” Id.

The contemplated before-dredging survey was completed on July 13, 2015, and partial progress surveys were performed on September 2, 2015, and October 6, 2015. See ECF No. 30 at 3; ECF No. 36 at 3. Defendant then completed an after-dredging survey in November 2015 and found that some areas “lack[ed] contract depth,” requiring further dredging as anticipated by the contract. See ECF No. 12-1 at 329; ECF No. 30 at 3. The work had not been finalized and accepted by defendant at the time of the first after- dredging survey.2 See ECF No. 12-1 at 465. Plaintiff completed the additional work,

1 The court previously set forth the factual details and procedural history of this case in its first summary judgment opinion, ECF No. 23. The court will only address the facts relevant to defendant’s current motion. 2 Plaintiff states in its motion that it was “required to re-dredge previously dredged, approved, and paid for areas.” ECF No. 36 at 6. Assuming plaintiff is referring to the areas that

2 Case 1:17-cv-00903-PEC Document 41 Filed 04/30/20 Page 3 of 6

and defendant performed another after-dredging survey on December 4, 2015, at which point the work was accepted. See ECF No. 30 at 3; ECF No. 36 at 5; ECF No. 12-1 at 487.

Defendant then compared the before-dredging survey from July 2015 and the after-dredging survey from December 2015, determined that plaintiff had removed 46,065 cubic yards of material, and paid plaintiff the contractual unit price for that amount of material. See ECF No. 30 at 3. Plaintiff contends that it was underpaid because defendant’s method of calculating the amount of removed material was flawed. See ECF No. 36 at 3-4.

Plaintiff filed a certified claim with the agency, which was denied, and then filed its complaint in this court. See ECF No. 1. In the cross-motions for summary judgment previously addressed by the court, defendant’s motion was granted as to all of plaintiff’s claims except its claim regarding payment for re-dredging—which is the subject of the current motions. See ECF No. 23. Plaintiff’s motion was denied in its entirety. See id.

II. Legal Standards

According to RCFC 56(a), summary judgment is appropriate “if the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” “[A]ll evidence must be viewed in the light most favorable to the nonmoving party, and all reasonable factual inferences should be drawn in favor of the nonmoving party.” Dairyland Power Coop. v. United States, 16 F.3d 1197, 1202 (Fed. Cir. 1994) (citations omitted). A genuine dispute of material fact is one that could “affect the outcome” of the litigation. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986). The parties in this case agree as to the material facts and dispute only the application of the terms of the contract.

Contract interpretation is “‘generally amenable to summary judgment’” because it involves questions of law. West Bay Builders, Inc. v. United States, 85 Fed. Cl. 1, 13-14 (2008) (quoting Varilease Tech. Grp., Inc. v. United States, 289 F.3d 795, 798 (Fed. Cir. 2002)). “When the United States enters into contract relations, its rights and duties therein are governed generally by the law applicable to contracts between private individuals.” Lynch v. United States, 292 U.S. 571, 579 (1934). The court therefore applies general principles of contract law when reviewing and interpreting contracts between the United States and a private party. See Franconia Assoc. v. United States, 536 U.S. 129, 141 (2002).

were the subjects of the interim surveys as those areas that were “approved,” the court notes that plaintiff was required to re-dredge after each survey because it had failed to meet contract specifications. See ECF No. 12-1 at 460.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lynch v. United States
292 U.S. 571 (Supreme Court, 1934)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Franconia Associates v. United States
536 U.S. 129 (Supreme Court, 2002)
Dairyland Power Cooperative v. United States
16 F.3d 1197 (Federal Circuit, 1994)
Varilease Technology Group, Inc. v. United States
289 F.3d 795 (Federal Circuit, 2002)
Nvt Technologies, Inc. v. United States
370 F.3d 1153 (Federal Circuit, 2004)
Premier Office Complex of Parma, LLC v. United States
134 Fed. Cl. 83 (Federal Claims, 2017)
West Bay Builders, Inc. v. United States
85 Fed. Cl. 1 (Federal Claims, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
North American Landscaping Construction & Dredge Company, Inc. v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/north-american-landscaping-construction-dredge-company-inc-v-united-uscfc-2020.