Chugach Federal Solutions, Inc.

Armed Services Board of Contract Appeals·Decided October 24, 2023·No. 61320·Published

Opinion

DOCUMENT FOR PUBLIC RELEASE The decision issued on the date below is subject to an ASBCA Protective Order.

This version has been approved for public release.

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - )

)

Chugach Federal Solutions, Inc. ) ASBCA No. 61320 )

Under Contract No. N44255-14-D-9000 )

APPEARANCES FOR THE APPELLANT: Richard B. O’Keeffe, Jr., Esq.

William A. Roberts III, Esq. Gary S. Ward, Esq. Cara L. Lasley, Esq. Wiley Rein LLP Washington, DC

APPEARANCES FOR THE GOVERNMENT: Craig D. Jensen, Esq.

Navy Chief Trial Attorney David M. Marquez, Esq. Robyn L. Hamady, Esq. Anthony Hicks, Esq. Trial Attorneys

OPINION BY ADMINISTRATIVE JUDGE D’ALESSANDRIS ON THE GOVERNMENT’S MOTION FOR PARTIAL RECONSIDERATION

Pending before the Board is the government’s motion for reconsideration of portions of our June 8, 2023 decision in this appeal. See Chugach Federal Solutions, Inc., ASBCA No. 61320, 23-1 BCA ¶ 38,372. For the reasons stated below we deny the government’s motion.

I. Standard Of Review For Motions For Reconsideration

A motion for reconsideration is not the place to present arguments previously made and rejected. “[W]here litigants have once battled for the court’s decision, they should neither be required, nor without good reason permitted, to battle for it again.” Dixon v. Shinseki, 741 F.3d 1367, 1378 (Fed. Cir. 2014) (quoting Official Comm. of the Unsecured Creditors of Color Tile, Inc. v. Coopers & Lybrand, LLP, 322 F.3d 147, 167 (2d Cir. 2003)). Moreover, “[m]otions for reconsideration do not afford litigants the opportunity to take a ‘second bite at the apple’ or to advance arguments that properly should have been presented in an earlier proceeding.” Dixon, 741 F.3d at 1378; see also Avant Assessment, LLC, ASBCA No. 58867, 15-1 BCA ¶ 36,137 at 176,384. On the other hand, if we have made mistakes in the findings of fact or conclusions of law, or by failing to consider an appropriate matter, reconsideration

DOCUMENT FOR PUBLIC RELEASE The decision issued on the date below is subject to an ASBCA Protective Order.

This version has been approved for public release.

may be appropriate. See Robinson Quality Constructors, ASBCA No. 55784, 09-2 BCA ¶ 34,171 at 168,911; L&C Europa Contracting Co., ASBCA No. 52617, 04-2 BCA ¶ 32,708. The Board has summarized the standard for reconsideration stating “[i]n short, if we have made a genuine oversight that affects the outcome of the appeal, we will remedy it.” Relyant, LLC, ASBCA No. 59809, 18-1 BCA ¶ 37,146 at 180,841. Here, as in Relyant, no such mistakes have been identified.

II. Procedural History

In its motion for partial reconsideration, the government asserts two errors in our decision: first, that we “erroneously concluded that the Navy did not identify specific costs for non-performed or late-performed work in FY16” (gov’t mot. at 2-3); and second, that we “erred in holding that the Navy cannot withhold payment for late- performed work” (gov’t mot. at 3-6).

At issue in this motion for reconsideration are the government’s withholdings of contract funds. In November 2015, the government withheld approximately $450 thousand for specifically identified tasks that were not performed and positions that were not filled. See, Chugach, 23-1 BCA ¶ 38,372 at 186,387; (R4, tab 12.632.3 at GOV421048-1, tab 12.632.2 [native] (spreadsheet detailing deductions)). These deductions are not in dispute. In addition, the withholding letter provided that the government would be making “temporary” withholdings, and that if the performance problems persisted the withholdings would be made permanent at the end of the fiscal year “once the full extent of the non-conformance is determined” (R4, tab 12.632.3 at GOV421048-2). The withholding amount was initially 10 % of contract payments due, but was reduced to 5 %. Chugach, 23-1 BCA ¶ 38,372 at 186,388.

In its opening post-hearing brief, Chugach argued that the government had not established a right to withhold a generalized “10% or 5% withholding of the negotiated contract price” and that the government could not establish that the withholdings bore a “reasonable relationship” to the damages suffered by the government (app. br. at 164). 1 With Chugach having raised these issues, it was incumbent upon the government to identify the legal basis for its withholding. In addition, it was incumbent upon the government to establish that there was late- performed or non-performed work and to demonstrate some rational relationship between the identified work and the withholding.

1 Chugach argued that there was no relationship between the withholding and the harm to the government because the government was responsible for Chugach’s non-performance and late-performance.

DOCUMENT FOR PUBLIC RELEASE The decision issued on the date below is subject to an ASBCA Protective Order.

This version has been approved for public release.

In its Rule 11 brief, the government addressed Chugach’s argument with three sentences and a string-cite of its proposed findings of fact. In its entirety, the government’s argument was:

Moreover, NAVFAC documented significant instances of CFSI’s nonperformance, including failure to perform required preventative maintenance across multiple annexes, failure to meet required completion deadlines, and failure to fill key positions required by the WSBOS Contract. Navy PFF Nos. 375-384. CFSI admitted that it had not fully performed required work in either FY15 or FY16, the two claim years. Navy PFF Nos. 378, 380, 385-386. The work that CFSI failed to perform – e.g., unstaffed key positions, time-based maintenance, late completion, etc. – was not amenable to re-performance. Navy PFF No. 385.

(Gov’t br. at 82-83) Although not included in the Navy’s string cite, our opinion cited the Navy’s proposed finding of fact number 387 as the only support for the Navy’s 5 percent retainage. This was a declaration by a contracting officer, (but not the contracting officer that instituted the withholding nor the contracting officer that reduced the withholding rate to 5%) stating that “NAVFAC estimated the cost of the FY16 non-performed work as 5% of the contract value of the recurring work.” We held that this conclusory statement by a contracting officer was:

[U]nsupported by citation to any workpapers or documentation of non-performed work. Moreover, Mr. Sandoval does not state that he personally estimated the value of the non- performed [work], but just that “NAVFAC” estimated the cost without identifying the individual or individuals that purportedly estimated the value to be 5 percent.

Chugach, 23-1 BCA ¶ 38,372 at 186,400 (citing gov’t ex. 1 ¶ 20).

In its Rule 11 reply brief, Chugach again challenged the Navy’s withholding as being without a rational relationship to the unperformed work, although this time arguing that the Navy failed to carry its burden and relied “on items it either already valued in its deductive modifications (which suggest double withholding) or late work that Chugach admittedly performed (for which Chugach is entitled to be paid)” (app. reply at 107). Chugach requested, and was granted, leave to file a sur-reply, but did not respond to this issue in its sur-reply.

DOCUMENT FOR PUBLIC RELEASE The decision issued on the date below is subject to an ASBCA Protective Order.

This version has been approved for public release.

III. The Government’s Assertions of Error

A. The Navy Did Not Identify Specific Costs For Non-Performed or Late-

Performed Work in FY16

Free access — add to your briefcase to read the full text and ask questions with AI

Chugach Federal Solutions, Inc., (asbca 2023).

Chugach Federal Solutions, Inc. (Chugach Federal Solutions, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Dixon v. Shinseki
741 F.3d 1367 (Federal Circuit, 2014)