Dg21, LLC v. Mabus

819 F.3d 1358, 2016 U.S. App. LEXIS 8387, 2016 WL 2860725
CourtCourt of Appeals for the Federal Circuit
DecidedMay 6, 2016
Docket2015-1830
StatusPublished
Cited by5 cases

This text of 819 F.3d 1358 (Dg21, LLC v. Mabus) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dg21, LLC v. Mabus, 819 F.3d 1358, 2016 U.S. App. LEXIS 8387, 2016 WL 2860725 (Fed. Cir. 2016).

Opinion

LOURIE, Circuit Judge.

DG21, LLC (“DG21”) appeals from the decision of the Armed Services Board of Contract Appeals (the “Board”) denying an appeal from the final decision of the contracting officer (“CO”) denying DG21 an equitable adjustment to account for escalated fuel costs under a government contract. See DG21, LLC, ASBCA No. 57980, 15-1 BCA ¶ 86016 (Mar. 3, 2015); see also Joint App. (“J.A.”). 1-26. For the following reasons, we affirm.

Background

The Department of the Navy (“the Navy”) maintains a support facility at Diego Garcia, a small atoll in the Indian Ocean. J.A. 36-37. -The atoll occupies approximately 10.5 square miles in area, and is located approximately 1,800 miles east of the coast of Africa and 1,200 miles south of the southern tip of India. J.A. 36. Access to Diego Garcia is restricted to. military personnel, authorized, government personnel, and contractors of the United States or United Kingdom, and there is no commercial or civilian infrastructure. J.A. 38..

In September 2005, the Navy issued a solicitation for bids on a firm fixed-price contract to provide base operating support services at Diego Garcia. J.A. 39. The services to be performed by the contractor varied widely, from informatioh technology services to refuse collection and recycling. J.A. 39. In. addition to providing-the services themselves, the contractor was required to implement a fuel conservation initiative, with a goal of cumulatively reducing fuel use by 10% per year of the contract. j.A. 48-49. Success in the fuel conservation initiative was responsible for 10% of the contractor’s award-fee pool each year. J.A. 50.

The solicitation identified two categories of fuel used under the contract. J.A. 115, 116. The first category, “government-furnished fuel,” was provided by the Navy to the contractor without any payment required, and could be used for most of the services in the contract. J.A. 115. The second category, which applied to all contractor base support vehicles and equipment (“BSVE”) and labelled as “contractor-furnished fuel,” was in fact also provided by the Navy. Rather than being provided without payment, however, the solicitation required the contractor to reimburse the Navy for that fuel “at the prevailing DoD [Department of Defense] rate at the time of purchase.” J.A. 116. The solicitation indicated that the reimbursement program was “to ensure that the fuel conservation program achieves its full impact throughout the life of the contract.” 'J.A. 115. The solicitation also provided historical fuel prices and usage rates for' contractors to use in crafting their bids. J.A. 116.

The solicitation incorporated by reference several provisions of the-Federal Acquisition Regulations (“FAR”)/ J.A. 136. One incorporated provision provides that:

(a) The Contracting Officer may, at any time ... by written order designated or *1360 indicated to be a change order, make changes in the work within the general scope of the contract, including changes—
(3) In the Government-furnished facilities, equipment, materials, services, or site[.]
(b) Any other written or oral order ... from the Contracting Officer that causes a change shall be treated as a change order under this clause; provided, that the Contractor gives the Contracting Officer written notice stating (1) the date, circumstances, and source of the order and (2) that the Contractor regards the order as a change order.
(d) If any change under this clause causes an increase or decrease in the Contractor’s cost of ... performance of any part of the work under this contract, whether or not changed by any such order, the Contracting Officer shall make an equitable adjustment and modify the contract in writing.

48 C.F.R. § 52.243-4 (1987).

DG21 submitted a bid on the solicitation, and performed calculations to determine how much contractor-furnished fuel it expected to consume. J.A. 57-58. It arrived at “a significantly lower number of gallons than the total gallons” reflected in the solicitation, and so its fuel estimate was significantly less than the Navy’s. J.A 58. DG21 also indicated that if fuel rates varied from historical rates by 10% or more, it would request an equitable adjustment, but that it would not escalate the amount of costs over the life of the contract. J.A. 232.

The Navy responded that “[t]he historical fuel consumption and rates” were “provided for informational purposes only.” J.A. 234. The Navy also clarified that as the solicitation was firm fixed-price, “DG21 assumes the full risk of consumption and/or rate changes. Please price your proposal accordingly. Please review and correct/adjust as appropriate.” J.A. 234. The Navy also questioned DG21’s decision not to include an escalation clause, and accordingly requested clarification and confirmation of DG21’s intentions regarding its rates. J.A. 233-34. DG21 did not change its estimate of fuel costs, reasoning that although fuel prices “fluctuate dramatically from year-to-year ... [it] believes that fuel costs overall should decrease through the Energy Efficiency Program.” J.A, 235. Accordingly, DG21 took the position that fuel costs did not need to be escalated and therefore did not change its pricing. J.A. 235. DG21 also removed the provision from its proposal indicating that it would seek an equitable adjustment if fuel prices changed more than 10%. See J.A. 236-38. DG21’s final proposal was accepted, and DG21 was awarded the fixed-price contract on July 6, 2006. J.A. 239, 241. The total estimated price for the contract was $455,292,490. J.A. 241.

During the course of the contract, fuel prices — and thus the prevailing DoD rate for fuel — rose dramatically, reaching a maximum of more than double the historical rate indicated in the solicitation. See J.A. 106-07. At one point, DG21 sought to cap the price for fuel at a 10% change from historical rates, despite having removed that language from its final proposal. J.A. 287-88. The Navy did not accept that request, and DG21 dutifully reimbursed the Navy for all “contractor-provided” fuel that it consumed. J.A. 122-23.

On July 8, 2011, DG21 requested an equitable adjustment to account for the unexpected increase in fuel costs. J.A. 100-02. DG21 calculated the weighted average of prices before contract performance began as $1.75 per gallon, and calcu *1361 lated the requested adjustment by subtracting the amount it would have paid at $1.75 per gallon from the amount actually paid. J.A. 106-07. DG21 reasoned that because the government determined the prevailing DoD rate and invoiced DG21 for fuel, the change in fuel price was a “change” to the contract under FAR § 52.243-4. Accordingly, DG21 requested an equitable increase of $1,171,475.90. J.A. 100-02.

The CO denied DG21’s request. The CO stated that the historical rates had been provided for informational purposes only and that the price fluctuations were not changes to the contract under FAR § 52.243-4. J.A. 131-32. DG21 appealed the CO’s denial to the Board.

After exhaustively reviewing the record, the Board denied DG21’s appeal.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

C.J. Mahan Construction Company
Armed Services Board of Contract Appeals, 2025
Chugach Federal Solutions, Inc.
Armed Services Board of Contract Appeals, 2023
Strategic Technology Institute, Inc.
Armed Services Board of Contract Appeals, 2022
Noaa Maryland, LLC v. Gsa
Federal Circuit, 2021

Cite This Page — Counsel Stack

Bluebook (online)
819 F.3d 1358, 2016 U.S. App. LEXIS 8387, 2016 WL 2860725, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dg21-llc-v-mabus-cafc-2016.