C.J. Mahan Construction Company

CourtArmed Services Board of Contract Appeals
DecidedSeptember 30, 2025
Docket63031
StatusPublished

This text of C.J. Mahan Construction Company (C.J. Mahan Construction Company) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
C.J. Mahan Construction Company, (asbca 2025).

Opinion

DOCUMENT FOR PUBLIC RELEASE The decision issued on the date below is subject to an ASBCA Protective Order. This version has been approved for public release.

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) C. J. Mahan Construction Company ) ASBCA No. 63031 ) Under Contract No. W912QR-18-C-0033 )

APPEARANCES FOR THE APPELLANT: Lawrence M. Prosen, Esq. Josephine M. Bahn, Esq. Cozen O’Connor Washington, DC

Michael W. Currie, Esq. Currie & Associates LLC Grove City, OH

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney James M. Inman, Esq. R. Lauren Horner, Esq. Zachary J. Grader, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Louisville

OPINION BY ADMINISTRATIVE JUDGE D’ALESSANDRIS

Appellant, C.J. Mahan Construction Company (Mahan) entered into a contract with respondent, the United States Army Corps of Engineers (government or USACE) to remove a lock and dam on the Ohio River, near Brookport, Illinois. Mahan employed divers to remove underwater metal portions of the lock and dam structure. Unlike recreational SCUBA diving in the crystal-clear waters of a Caribbean island, this underwater demolition work was performed by surface supplied air in water with minimal visibility, a swift current, and the additional hazard of floating debris. Because of these dangers, the contract required compliance with the diving operations section of the USACE Safety and Health Requirements Manual (EM 385). An appendix to the dive section of the manual provides “Manning Levels for Dive Teams” specifying a four-person minimum team size (diving supervisor, diver, standby diver, and tender) for one diver performing the type of demolition work involved in the project. The appendix further provides that the standby diver can act as a second working diver if certain conditions are met, including the addition of a second tender, creating a minimum dive team size of five. DOCUMENT FOR PUBLIC RELEASE The decision issued on the date below is subject to an ASBCA Protective Order. This version has been approved for public release.

Mahan bid the contract based on a proposed five-person dive team, with two working divers. Mahan submitted dive safety plans based on five-person crews with two working divers, and the government approved Mahan’s dive safety plans. Around this time, two events relevant to the dispute occurred: first, the USACE appointed a new District Dive Coordinator (DDC); and second, a diver died on a nearby but separate USACE project. When Mahan attempted to use a second working diver on this project, the USACE informed Mahan that it would be required to employ a sixth crew member.

Mahan submitted a request for equitable adjustment seeking compensation for the additional costs it claims to have incurred due to lower productivity during the period it had to work with a single diver, and the added costs of a sixth crew member when it worked with two divers. The government denied Mahan’s REA despite issuing a contract modification to Mahan on another nearby dive contract for the same requirement of employing a sixth crew member. On another similar nearby dive project the government included a note to bidders that additional staffing beyond that required by EM385 would be required.

The parties agreed to submit these appeals on the record without a hearing pursuant to Board Rule 11 and have requested that the Board decide entitlement and quantum. For the reasons stated below we find that the government constructively changed the contract by requiring Mahan to employ a sixth dive team member, after initially approving Mahan’s dive safety plan to use five-member dive teams. We grant Mahan damages in the amount of $1,076.686.85.

FINDINGS OF FACT

A. The Solicitation and Contract

The government issued a sealed bid solicitation on July 30, 2018 (R4, tab 7 at 446). The solicitation indicated that the contract would be firm-fixed-price (id. at 468-69). The bid schedule called for a single price for all work on the project, except the estimated quantity for stone protection, which was unit priced (id. at 450- 51). The summary of work stated that the project was for the demolition of Lock and Dam 52, including “demolition of a 600 foot and a 1200 foot lock, demolition of the separating piers, and removal of the 540 foot Chanoine weir, 160 foot Bebout weir, three bear traps,[1] 725 foot fixed weir, 1248 feet of navigable pass wickets, and fixed weir abutment” (id. at 545). The project also required demolition of cells, which are generally cylindrical sheet pile columns filled with rock, gravel, and concrete (R4,

1 “Bear traps are a type of gate used to increase the level of the upper pool of the dam and to direct the flow of water over the gates to allow floating debris such as trees to continue flowing downstream” (R4, tab 2 at 3).

2 DOCUMENT FOR PUBLIC RELEASE The decision issued on the date below is subject to an ASBCA Protective Order. This version has been approved for public release.

tab 2 at 4). Demolition of the cells generally required removing the fill and then cutting the sheet pile (R4, tab 7 at 657-58). Lock and Dam 52 was located on the Ohio River near the confluence with the Mississippi River (R4, tab 8 at 756).

The solicitation and resulting contract included the Disputes Clause, Federal Acquisition Regulation (FAR) 52.233-1 (R4, tab 7 at 468). The solicitation and resulting contract included the Permits and Responsibilities clause, FAR 52.236-7 (id.), the Accident Prevention clause, Alternate I, FAR 52.236-13 Alt. I, (id.), and the Changes clause, FAR 52.243-4 (id. at 469).

The solicitation included Specification 01 35 26.00 06 Government Safety Requirements (R4, tab 7 at 583-602), including the requirement of an “ACTIVITY HAZARD ANALYSIS (AHA)” in accordance with USACE EM 385-1-1 “for every operation involving a type of work presenting hazards not experienced in previous project operations” (id. at 592). The contract incorporates USACE EM 385-1-1 in various places. Relevant to this appeal, Specification 02 41 00 Demolition, required submission of a demolition plan in accordance with EM 385-1-1 (id. at 650-64). The solicitation provided no direction with respect to diving operations or dive crew manning level requirements beyond those provided in the EM 385 Safety and Health Requirements Manual (R4, tab 7).

Paragraph 30(A)(13) of EM 385 requires that certain documents be reviewed and found acceptable in order to engage in diving activities (R4, tab 5 at 419). Paragraph 30(A)(14) requires that a dive operations plan be completed for each separate diving operation and be submitted through the contracting officer (id.). Relevant to this appeal, Appendix G to EM 385, Manning Levels for Dive Teams, states:

General. Manning level tables shown are a minimum. Actual manning levels may increase, as determined by the DDC, after considering the diving support systems, the task at hand, weather conditions, dive platform and location, and other factors. Team members may rotate through the dive team positions as long as the minimum manning levels are maintained and team members are qualified and accepted for the position.

(R4, tab 6 at 441) Appendix G also specifies minimum dive crew sizes for different types of diving operations. For dives using surface supplied air, between 0 to 100 ft depth the appendix provides:

3 DOCUMENT FOR PUBLIC RELEASE The decision issued on the date below is subject to an ASBCA Protective Order. This version has been approved for public release.

b. Deploying the Standby Diver as a Worker Diver. The Standby diver may be deployed as a working diver provided all of the following conditions are met:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McAbee Construction, Inc. v. United States
97 F.3d 1431 (Federal Circuit, 1996)
Melka Marine, Inc. v. United States
187 F.3d 1370 (Federal Circuit, 1999)
bell/heery v. United States
739 F.3d 1324 (Federal Circuit, 2014)
Dg21, LLC v. Mabus
819 F.3d 1358 (Federal Circuit, 2016)
Bgt Holdings LLC v. United States
984 F.3d 1003 (Federal Circuit, 2020)
J.F. Allen Co. & Wiley W. Jackson Co. v. United States
37 Cont. Cas. Fed. 76,268 (Court of Claims, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
C.J. Mahan Construction Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cj-mahan-construction-company-asbca-2025.