Wickham Contracting Co., Inc. v. Dennis J. Fischer, Acting Administrator, General Services Administration

12 F.3d 1574, 39 Cont. Cas. Fed. 76,608, 1994 U.S. App. LEXIS 130
CourtCourt of Appeals for the Federal Circuit
DecidedJanuary 6, 1994
Docket19-1358
StatusPublished
Cited by84 cases

This text of 12 F.3d 1574 (Wickham Contracting Co., Inc. v. Dennis J. Fischer, Acting Administrator, General Services Administration) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wickham Contracting Co., Inc. v. Dennis J. Fischer, Acting Administrator, General Services Administration, 12 F.3d 1574, 39 Cont. Cas. Fed. 76,608, 1994 U.S. App. LEXIS 130 (Fed. Cir. 1994).

Opinion

MICHEL, Circuit Judge.

Wickham Contracting Company appeals from a decision of the General Services Administration Board of Contract Appeals (Board), denying Wickham’s claim for an equitable adjustment for overhead expenses incurred under a contract with the General Services Administration (GSA) as a result of GSA-imposed delays. Wickham Contracting Co., GSBCA No. 8675, 92-3 BCA ¶ 25,040, 1992 WL 88326 (Apr. 29, 1992). First, the Board held that the Eichleay formula is the proper method for calculating unabsorbed home office overhead when a contractor otherwise satisfies the Eichleay requirements. 1 Second, the Board would not allow Wickham to expand the overhead pool by including direct costs. Third, the Board rejected Wickham’s claim to an increased delay period because the contractor had not shown that it would have finished by the projected early date. Fourth, the Board held that Wickham is not entitled to interest for use of its equity capital or borrowed funds. We affirm the decision of the Board, upholding its ruling on each of these four issues, again presented here. Regarding the Eichleay formula, we hold it is the only proper method of calculating unabsorbed home office overhead. No other formula may be used.

I. BACKGROUND

On July 28, 1977, Wickham entered into a contract with GSA to renovate the Federal Post Office and Courthouse in Albany, New York, for the sum of $2,968,000. The contract allowed 365 days from the notice to proceed to perform the work which was due to be completed on August 15, 1978. Early in the renovation process, GSA became concerned about structural problems with the building and ordered many delays in the work. The parties agree that, due to GSA-imposed delays, the work was not substantially complete until April 10, 1981, 969 days after the contracted date. Many of Wick-ham’s claims against the government for additional costs due to such delays have been *1576 settled. However, certain costs associated with home office overhead have not.

Wickham’s home office staff during the renovation work consisted of the president, a construction engineer, the project manager, and three secretaries. In addition to the Albany project, Wickham performed only two other major contracts during the same time frame — the West Point project and the Foley Square project. Both of these projects were managed mainly on site while the Albany project was managed mainly from the home office.

In June 1986, the contracting officer awarded Wickham an additional $333,084 on its claim for unabsorbed home office overhead due to the delay, based on the Eichleay formula. 2 Before the Board, Wickham argued that, for three reasons, it was due a larger amount for the unabsorbed home office overhead. Wickham complained that the percentage of the home office overhead pool allocated to the Albany contract based on the Eichleay formula, approximately 34%, was too low and did not fairly compensate Wick-ham for its overhead expenses. The contractor argued that it was entitled to be reimbursed for 80% of its overhead expenses incurred during the delay period because 80% of its home office activity and, therefore, 80% of its home office overhead expense was devoted to the Albany contract during that time frame. Wickham made the argument first to the contracting officer, then to the Board.

On appeal to us, Wickham repeatedly states that the 80% figure is undisputed. However, the government points out that Wickham did not keep current books or records which could document the 80% figure and that Wickham did not develop that figure until January 1985. The record supports the government’s assertions. Therefore, we conclude the figure is disputed.

The Board did not make a clear finding as to whether Wickham actually proved that 80% of its home office activity was devoted to the Albany contract. Instead, the Board rejected Wickham’s theory of recovery on the basis that unabsorbed overhead is always calculated according to the Eichleay formula when a contractor meets the Eichleay requirements after government-imposed delay. The Board applied the Eichleay formula based on the notion that it is a theoretical construct of the amount of unabsorbed overhead caused by the contract delay and, therefore, the actual amount of overhead allegedly caused by the contract was not relevant.

The parties agree on many of the components of the overhead pool. The components of the overhead pool to which the Board applied the Eichleay formula are general and administrative salaries, rent, insurance, depreciation, hospitalization and medical costs, dues and subscriptions, office expenses, auto and truck maintenance, utilities, plans and specifications, cleaning, protection, taxes and licenses, and officer’s salaries. 92-3 BCA ¶ 25,040 at 124,818-19.

Before the Board, however, Wickham also argued that the contracting officer wrongly excluded several specific field costs from the overhead pool. The field costs are for travel and business meetings, telephones, professional fees, union welfare benefits, payroll taxes and equipment rental. Their inclusion would increase the amount paid to Wickham under either the Eichleay formula or Wick-ham’s allocation figure of 80%. The Board, however, found that as direct, not overhead costs, they may not be included in the overhead pool.

In addition, Wickham argued that the com-pensable delay period was actually 1029 days rather than the 969 days admitted by GSA. The longer delay would entitle Wickham to a larger payment under either the Eichleay formula or its preferred figure of 80%. Wickham measures the delay from its projected early finish date of June 15,. 1978, suggested by the critical path method schedule, rather than the finish date of August 15, 1978, set by the contract. The Board found that Wickham was not entitled to reimbursement based on the longer delay period be *1577 cause it did not prove that it would have finished by the earlier date.

Finally, Wickham sought reimbursement for the cost of use of its equity capital and alleged use of borrowed funds during the delay. The Board rejected this claim also, the former as unallowable and the latter as unproven.

Wickham appealed to this court pursuant to the Contract Disputes Act of 1978 (CDA), 41 U.S.C. § 607(g)(1) (1988). Our jurisdiction rests on that Act and 28 U.S.C. § 1295(a)(10) (1988).

II. STANDARD OF REVIEW

The CDA dictates the standard this court applies in reviewing decisions of agency contract appeal boards. 41 U.S.C. § 609(b).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Speedway Orion JV
Armed Services Board of Contract Appeals, 2023
NXP USA Inc v. Impinj Inc
W.D. Washington, 2023
Dg21, LLC v. Mabus
819 F.3d 1358 (Federal Circuit, 2016)
KBJ, Inc.
Armed Services Board of Contract Appeals, 2016
Vistas Construction of Illinois, Inc.
Armed Services Board of Contract Appeals, 2016
JMR Construction Corp. v. Environmental Assessment & Remediation Management, Inc.
243 Cal. App. 4th 571 (California Court of Appeal, 2015)
H. J. Lyness Construction, Inc. v. United States
121 Fed. Cl. 287 (Federal Claims, 2015)
System Fuels, Inc. v. United States
457 F. App'x 930 (Federal Circuit, 2012)
Boston Edison Co. v. United States
658 F.3d 1361 (Federal Circuit, 2011)
Energy Northwest v. United States
641 F.3d 1300 (Federal Circuit, 2011)
Redland Co. v. United States
97 Fed. Cl. 736 (Federal Claims, 2011)
Delhur Industries, Inc. v. United States
95 Fed. Cl. 446 (Federal Claims, 2010)
Entergy Nuclear Vermont Yankee, LLC v. United States
95 Fed. Cl. 160 (Federal Claims, 2010)
Yankee Atomic Power Co. v. United States
94 Fed. Cl. 678 (Federal Claims, 2010)
Arizona Public Service Co. v. United States
93 Fed. Cl. 384 (Federal Claims, 2010)
Martin County v. Polivka Paving, Inc.
44 So. 3d 126 (District Court of Appeal of Florida, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
12 F.3d 1574, 39 Cont. Cas. Fed. 76,608, 1994 U.S. App. LEXIS 130, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wickham-contracting-co-inc-v-dennis-j-fischer-acting-administrator-cafc-1994.