Doyon Utilities, LLC v. United States

CourtUnited States Court of Federal Claims
DecidedApril 20, 2020
Docket19-199
StatusPublished

This text of Doyon Utilities, LLC v. United States (Doyon Utilities, LLC v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Doyon Utilities, LLC v. United States, (uscfc 2020).

Opinion

In the United States Court of Federal Claims No. 19-199C (Filed: April 20, 2020)

DOYON UTILITIES, LLC, Plaintiff, Keywords: 12(b)(1); Changes v. Clause; 12(b)(6); No-Interest Rule; Sovereign Immunity

UNITED STATES, Defendant.

Adam Whitfield Cook, Birch, Horton, Bittner & Cherot, P.C., Anchorage, AK, for Plaintiff.

Steven Charles Hough, Trial Attorney, Steven J. Gillingham, Assistant Director, Robert E. Kirschman, Jr., Director, and Joseph H. Hunt, Assistant Attorney General, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washington, D.C., with whom were Brandon Cogswell, Senior Counsel, Defense Logistics Agency Energy, Ft. Belvoir, VA, for Defendant.

MEMORANDUM OPINION AND ORDER

TAPP, Judge. 1

In this Contracts Dispute Acts (CDA) case, Plaintiff, Doyon Utilities, LLC (“Doyon”), constructed two landfill natural gas (“LFG”) facilities in order to supply Defendant, the United States, with electricity at Joint Base Elmendorf-Richardson (“JBER”)—a joint air force and army base in Anchorage, Alaska. (See Compl. ¶ 1, ECF No. 1). Under a pass-through agreement between the United States and Doyon, Doyon was to purchase LFG from the Municipality of Anchorage (“MoA”), who owned and operated a landfill generating LFG, and resell that LFG to the United States at cost. (See Compl. at 2–3). However, because of the United States’ delay in payment, Doyon was forced to obtain a loan to sustain its operations and the United States refused to reimburse Doyon for the interest it incurred on that loan. (Id. at 4–7). Thus, Doyon filed this suit seeking a reimbursement of $178,096 for interest accrued between June 28, 2013 (when Doyon made its initial loan payment) and January 9, 2015 (when Doyon received payment from the United States). (Id. at 8–10).

Before the Court is the United States’ Motion to Dismiss. (Def.’s Mot., ECF No. 14). The United States seeks dismissal on two separate grounds: (1) lack of subject matter jurisdiction

1 The case was originally assigned to Senior Judge Charles F. Lettow and transferred to Judge David A. Tapp on December 3, 2019. (See ECF No. 22).

1 pursuant to RCFC 12(b)(1); and (2) failure to state a claim under RCFC 12(b)(6). (Id. at 1). On October 11, 2019, Doyon filed its Response. (Pl.’s Resp., ECF No. 17). On January 24, 2020, the United States filed its Reply. (Def.’s Reply, ECF No. 25). This matter is now fully briefed and ripe for decision. For the reasons set forth below, the Court GRANTS the United States’ Motion to Dismiss.

Background

Doyon is a regulated utility provider and owns twelve facilities located at three United States Army bases within Alaska. (Compl. at 1). On September 28, 2007, Doyon entered into a contract (“the initial contract”) with the Defense Logistics Agency Energy (“DLA Energy”) 2 to provide electric, natural gas, water, and wastewater utility services at Joint Base Elmendorf- Richardson (“JBER”)—a joint air force and army base in Anchorage. (Id. at 2; Ex. A.). Under the terms of the initial contract, Doyon was obligated to operate and maintain these utility systems, replace and upgrade the infrastructure, and extend service to new connections as requested by the United States. (Pl.’s Resp., at 3). The United States sought to develop a means for capturing and converting into electricity landfill natural gas (“LFG”) generated at a nearby landfill operated by the MoA. (Compl. at 2). The initial contract did not initially provide for the supply of energy; even so, Doyon took steps to fulfill that role in constructing and operating an LFG processing facility for the benefit of the United States. (Id.).

A. Landfill Gas Powerplant

In 2010, the MoA awarded Doyon a competitive procurement for construction and operation of an LFG processing facility at MoA’s landfill in Anchorage, Alaska. (Id.). After the MoA accepted its proposal, Doyon, the MoA, and the United States began working together to develop an LFG power project. (Id.). On March 21, 2011, Doyon submitted a proposal to the United States for the construction and operation of an LFG processing facility at the MoA landfill (the “Techno-Economic Proposal”). (Id. at 3). The facility would collect and process LFG for delivery to a power plant at JBER. (Id.).

In response to the Techno-Economic Proposal, the DLA Contracting Officer gave Doyon a Notice to Proceed with development of a 35% design of an LFG processing facility on April 12, 2011. (Id. at 3–4). The Techno-Economic Proposal delineated that the project would require the purchase of the LFG from the MoA, that Doyon would operate the facility and deliver the LFG to a powerplant in JBER, and that the United States, as a beneficiary of the resulting utility services, would be ultimately responsible for the funding of the project through a pass-through 3 agreement whereby Doyon would be reimbursed for the LFG it purchased. (Id. at 3).

On May 24, 2011, the MoA approved construction and operation of the LFG processing facility in accordance with the Techno-Economic Proposal. (Id. at 4). On July 18 and August 2, 2011, Doyon and DLA Energy executed two supplemental agreements authorizing Doyon to

2 DLA Energy, formerly known as the Defense Energy Support Center, is a subordinate command of the Defense Logistics Agency, a combat support agency of the United States Department of Defense. (Compl. at 2).

3 Doyon uses the terms “pass-through” and “flow-through” interchangeably to describe this agreement.

2 proceed with 65% of the design and purchase “long-lead items” for construction of the LFG processing facility. (Id. at 3–4). On September 12, 2011, Doyon entered into a separate contract with the MoA to purchase LFG for the JBER power plant. (Id. at 4). This was a Master Implementation Agreement (“MIA”) in which the MoA agreed to sell LFG to Doyon. (Id.). The MIA established a pricing mechanism for the sale of LFG to Doyon according to the weighted average of the price of natural gas reflected in a Cost of Power Adjustment (“COPA”) filed by an Alaska utility with the Regulatory Commission of Alaska, referred to as the “COPA System.” (Id. at 4).

In August of 2012, Doyon commissioned the new LFG processing facility and power plant for delivering LFG for power generation. (Id.). In late 2012, Doyon and the United States negotiated a pass-through mechanism by which Doyon would pass the cost of LFG to the United States at an identical rate as negotiated between Doyon and the MoA. (Id.). The pass-through agreement referenced in the Techno-Economic Proposal states that: “Doyon Utilities . . . with the visibility and support of the government, entered into a Master Implementation Agreement to purchase landfill gas from the Municipality of Anchorage in August of 2011. . . .” (Id., Ex. 1 at 2). 4 That agreement further provides that, “[Doyon Utilities] will provide to the Government an invoice for landfill gas which is based upon the same volume and base price used to compute payment for landfill gas to the Municipality.” (Id., Ex. 1 at 3). 5 Thus, the COPA System utilized in Doyon’s MIA with the MoA would govern the price paid by the United States for the LFG. (Id.). On January 17, 2013, the contracting officer for DLA notified Doyon that DLA had received the funds necessary for purchase of the LFG and a contract modification was being drafted to establish contract line items (CLINs) necessary to fund the purchase. 6 (Compl. at 4). Despite those assurances, a modification was not executed for several months. (Id. at 5). Pursuant to its underlying contract, Doyon began paying the MoA for LFG on May 29, 2013. (Id.).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Scheuer v. Rhodes
416 U.S. 232 (Supreme Court, 1974)
United States v. Testan
424 U.S. 392 (Supreme Court, 1976)
Library of Congress v. Shaw
478 U.S. 310 (Supreme Court, 1986)
Lujan v. Defenders of Wildlife
504 U.S. 555 (Supreme Court, 1992)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Easter v. United States
575 F.3d 1332 (Federal Circuit, 2009)
Energy Northwest v. United States
641 F.3d 1300 (Federal Circuit, 2011)
Getty Oil Company v. The United States
767 F.2d 886 (Federal Circuit, 1985)
Gevyn Construction Corp. v. The United States
827 F.2d 752 (Federal Circuit, 1987)
John G. Rocovich, Jr. v. The United States
933 F.2d 991 (Federal Circuit, 1991)
Donald A. Henke v. United States
60 F.3d 795 (Federal Circuit, 1995)
Sommers Oil Company v. United States
241 F.3d 1375 (Federal Circuit, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
Doyon Utilities, LLC v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/doyon-utilities-llc-v-united-states-uscfc-2020.