KBJ, Inc.

CourtArmed Services Board of Contract Appeals
DecidedMarch 3, 2016
DocketASBCA No. 58512
StatusPublished

This text of KBJ, Inc. (KBJ, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
KBJ, Inc., (asbca 2016).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) KBJ, Inc. ) ASBCA No. 58512 ) Under Contract No. NNC11CA18C )

APPEARANCE FOR THE APPELLANT: Joseph R. Spoonster, Esq. Harpst Ross Ltd. Uniontown, OH

APPEARANCES FOR THE GOVERNMENT: Scott W. Barber, Esq. NASA Chief Trial Attorney Laura A. Henry, Esq. Tamika S. Laldee, Esq. MacAllister A. West, Esq. Trial Attorneys NASA Glenn Research Center, OH

OPINION BY ADMINISTRATIVE JUDGE SCOTT

Appellant, KBJ, Inc. (KBJ), appealed pursuant to the Contract Disputes Act (CDA), 41 U.S.C. §§ 7101-7109, from the contracting officer's (CO's) final decision denying its $558,791.33 suspension and delay claim under the captioned contract to replace two boilers at the National Aeronautics and Space Administration's (NASA's) Glenn Research Center (GRC). The Board conducted a two-day hearing in Cleveland, Ohio. We decide entitlement and quantum. For the reasons set forth below, we sustain the appeal in part and otherwise deny it.

FINDINGS OF FACT

1. On 16 March 2011 NASA awarded the subject contract, a section 8(a) set-aside, to KBJ in the firm-fixed-price of $3,621,900 (R4, tab 3 at 42, tab 5 at 59-60; tr. 2/18). Under the contract, KBJ was to remove and replace Boilers 3 and 4 at GRC's steam plant, based upon a design provided by NASA (R4, tab 5, attach. A at 122-102; tr. 2/18). The boilers, which were about 18 feet wide, 30 feet long, and 28 feet tall, operated 365 days of the year to provide heat and humidification to GRC's approximately 350-acre campus. They were critical to GRC's operations, including daily support of significant research projects and experiments. The steam plant was very old and the boilers needed to be upgraded to make the plant more cost-effective and functional. (Tr. 1/23, 127-29, 174, 2/18-19) 2. To facilitate installation of the replacement boilers, KBJ was required to demolish a portion of the existing masonry wall on one face of the steam plant building and, after installation of the new boilers, reconstruct the wall with new energy efficient light panels and an insulated overhead door. KBJ was also required to provide a new combustion air system for the steam plant; replace two low pressure steam condensate collection and return pumps with non-electric pressure-powered units with steam pressure equalization tanks; install new conduit and wire for new boiler fans and blowers; install compatible starters for the boiler in the motor control center; and replace low voltage electrical distribution panels and associated feeders. (R4, tab 5, attach. A at 122-007 to -008)

3. On 11 February 2011, prior to contract award, NASA issued solicitation Amendment No. 2, answering prospective bidders' questions (R4, tab 1 at 7-16). Question 18 asked whether NASA would consider a schedule extension "due to the boiler lead time," noting that the replacement boilers would be "delivered at just about the time NASA wants them to be activated." NASA had responded that its "intention is for the work to be complete per the solicitation." (Id. at 11)

4. The contract anticipated the presence of asbestos-containing materials during work performance and required KBJ to remove them. It provided that the asbestos work included the removal of 1,000 square feet of boiler insulation material. (R4, tab 5, attach. A at 122-008, -102) Pre-bid Question No. 14 had asked NASA to confirm that the 1,000 square feet of boiler asbestos abatement included the ductwork extending from the boilers. NASA responded that the "1000 sf should include abatement of all asbestos necessary to remove boilers 3 and 4 safely." (R4, tab 1 at 10; tr. 2/89) Kevin Stiles was NASA's project manager. At the time, he was employed by a private contractor that worked for NASA. According to Mr. Stiles, NASA had allotted for 1,000 square feet of asbestos for the project and, if additional asbestos were discovered, NASA planned to modify the contract to add abatement of that asbestos. (Tr. 2/5-6, 58-59) We find that the contract required KBJ to abate only 1,000 square feet of asbestos-containing boiler insulation material.

5. Contract clause H.12 provided that "[t]he Superintendent is considered essential to the work being performed under this contract" and it required that KBJ identify a superintendent who "shall be dedicated solely to this contract and shall be on site full time whenever work is being performed under this contract" (R4, tab 5 at 87).

6. The contract incorporated numerous Federal Acquisition Regulation (FAR) clauses, including FAR 52.233-1, DISPUTES (JUL 2002); FAR 52.242-14, SUSPENSION OF WORK (APR 1984); and FAR 52.243-4, CHANGES (JUN 2007) (R4, tab 5 at 67, 103). The Suspension of Work clause provided in pertinent part:

(a) The [CO] may order the Contractor, in writing, to suspend, delay, or interrupt all or any part of the work of this

2 Il contract for the period of time that the [CO] determines appropriate for the convenience of the Government.

(b) If the performance of all or any part of the work is, for an unreasonable period of time, suspended, delayed, or interrupted (1) by an act of the [CO] in the administration of this contract, or (2) by the [CO's] failure to act within the time specified in this contract (or within a reasonable time if not specified), an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit) necessarily caused by the unreasonable suspension, delay, or interruption, and the contract modified in writing accordingly. However, no adjustment shall be made under this clause for any suspension, delay, or interruption to the extent that performance would have been so suspended, delayed, or interrupted by any other cause, including the fault or negligence of the Contractor, or for which an equitable adjustment is provided for or excluded under any other term or condition of this contract.

7. NASA issued a notice to proceed to KBJ on 12 April 2011, which it received that day (R4, tab 25; compl. ii 12). KBJ was to complete performance within 180 calendar days from the issuance of the notice to proceed, i.e., by 9 October 2011 (R4, tab 5 at 67; tr. 1/76). From the point NASA approved the contractor's submittals for the new boilers, the lead time for boiler manufacture was typically four to six months (tr. 2/29).

8. KBJ submitted its initial construction schedule on 22 April 2011, which NASA did not approve, in part because it was difficult to determine the critical path (R4, tab 26; tr. 2/23-24). On 12 May 2011 KBJ resubmitted its schedule, which NASA approved on 13 May 2011 (ex. G-1; tr. 2/24). Under the approved schedule KBJ planned to begin boiler asbestos abatement on 19 May 2011 and complete boiler demolition by 18 July 2011. Foundation construction for the replacement boilers was to be complete by 28 July 2011. KBJ planned to begin boiler assembly on 13 June 2011 and to have replacement Boilers 4 and 3 on site on 12 and 26 August 2011, respectively. It planned to begin replacement boiler installation on 15 August 2011 and to complete work on them by 14 October 2011. The contract performance period, as planned, was to end on 4 November 2011. (Ex. G-1; compl. ii 14; gov't hr. at 2; app. hr. at 2, ii 9).

9. On 26 May 2011 Mr. Stiles gave what he described as a direction to KBJ:

Regarding the Repair Steam Plant Project, I have been instructed that we are to proceed as follows: I 3 We are free to mobilize at the Steam Plant to perform work that can be started within a reasonable time frame after installing the barricades and to perform work that does not render any of the boilers non-functional at this point.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
KBJ, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/kbj-inc-asbca-2016.