Altmayer v. Johnson

79 F.3d 1129, 1996 WL 124813
CourtCourt of Appeals for the Federal Circuit
DecidedMarch 21, 1996
DocketNo. 95-1223
StatusPublished
Cited by27 cases

This text of 79 F.3d 1129 (Altmayer v. Johnson) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Altmayer v. Johnson, 79 F.3d 1129, 1996 WL 124813 (Fed. Cir. 1996).

Opinion

MAYER, Circuit Judge.

Jay P. Altmayer; Nancy Hirschler; Jane Beskin; AmSouth Bank, N.A., as trustee under the will of Claire Pollack; and Jay P. Altmayer and AmSouth Bank, N.A., as co-trustees under the will of Marvin C. Altmayer (collectively “Altmayer”) appeal the decision of the General Services Administration Board of Contract Appeals in Altmayer v. General Services Administration, 95-1 B.C.A. (CCH) ¶ 27,515, 1995 WL 53976 (GSBCA 1995), granting in part and denying in part Altmayer’s appeal of a contracting officer’s final decision. Because the board erred in denying Altmayer’s subcontractor, Haas Construction, Inc., recovery of its extended home office overhead under the formula set out in Eichleay Corp., 60-2 B.C.A. (CCH) ¶ 2688, 1960 WL 538 (ASBCA 1960), [1131]*1131aff'd on recon., 61-1 B.C.A. (CCH) ¶ 2894, 1960 WL 684 (ASBCA 1960), we affirm-in-part, reverse-in-part, vaeate-in-part, and remand.

Background

This appeal arises from a contract that the General Services Administration (“GSA” or “government”) awarded to Altmayer on December 30,1991, for a ten-year lease of office space owned by Atmayer in Savannah, Georgia. Prior to lease commencement, Atmayer was required to “build out” the space, which was to be used as a United States Attorney’s office, in accordance with the solicitation’s specifications and with plans to be provided by the government. As amended, the contract required Atmayer to complete these renovations by February 25,1993.

Atmayer subcontracted the renovation work to Haas Construction, Inc. Atmayer and Haas contracted initially for demolition work prior to the renovations and simply modified that contract through the issuance of change orders for each subsequent module of work to be performed by Haas. In August 1992, Haas established a critical path schedule, which set forth all of the critical tasks to be performed on the contract in a logical sequence that would ultimately lead to timely completion of the contract.

As set out in its critical path, Haas planned to install wood trim to be ordered by the government and then paint the interior walls over the course of fifteen days, between November 17, 1992, and January 5, 1993. It also planned to install carpet the government was to specify over fifteen days, between December 15, 1992, and January 19, 1993. The government’s carpet selection was especially critical because the manufacturer could not deliver the carpet until six to eight weeks after an order had been placed. Consequently, to begin carpet installation in accordance with Haas’s critical path schedule, the carpet had to be ordered in mid-October 1992. These were the last two tasks to be completed on Haas’s critical path, after which it was to do the final clean-up and complete its punch list items.

GSA had expected to order the carpet and wood trim by August 1992, but it did not do so. Throughout the balance of 1992, Atmayer continued to impress upon the government the importance of obtaining the carpet and wood finish selections if the contract was to be completed on time. Its pleas, however, were unavailing.

Athough the government delivered a finish schedule, identifying its carpet and wood trim selections, in October 1992, it told Haas not to use the schedule because it would be changed. In November, the government furnished a revised finish schedule and instructed Atmayer to order its chosen carpet. Just two weeks later, however, the government directed Atmayer to put the order “on hold” because of price concerns. Similarly, it designated a particular trim, which was not on the original contract, in November 1992. Haas explained that its selection would increase the price. As a result, the parties, including a representative of the U.S. Attorney’s office, spent the next three months discussing available woods and stains, and their respective prices. On February 24, 1993, the government directed Atmayer to order a particular wood trim, but it did not designate a stain. Moreover, the parties still had not agreed on a price for the trim. The government later substituted a different trim.

Because of Atmayer’s concern that the government’s indecision about its wood trim and carpet selections had precluded completion of the contract on time, it requested an extension of the contract and a price adjustment on January 7, 1993. The contracting officer promised to respond by January 26, 1993, but he failed to do so. On February 9, 1993, Atmayer again requested an extension, and again received no immediate response. On March 1, 1993, four days after the originally-scheduled date for completion, the government granted Atmayer an extension until June 1, 1993. However, it denied any monetary liability for the delay, contending that Atmayer was concurrently responsible for a number of reasons the board ultimately rejected and the government does not appeal.

Eventually, on March 8, 1993, the government gave Atmayer its carpet selections. However, it was not until March 15, 1993, [1132]*1132that it finished selecting the wood trim. Haas then completed the renovations, and on May 28, 1993, the lease began.

Soon thereafter, Altmayer submitted a certified claim to the contracting officer for amounts due to both Altmayer and Haas as a result of the delay. On August 30, 1993, the contracting officer denied the claim in its entirety. Altmayer appealed that decision to the board, claiming inter alia, Haas’s extended home office overhead as calculated under the Eichleay formula.

The board held that the government’s failure to select carpet material until March 1993, after the date originally contemplated for contract completion, was the sole cause of the contract’s late completion. It explicitly rejected the government’s contention that Altmayer was partly responsible for the delay because all work, save for the carpet and trim items, had not been finished by February 25,1993.

As for damages, the board held, in pertinent part, that the government was liable for the salaries and taxes of two of Haas’s supervisors who remained on site through the extended performance period. It also awarded certain direct costs associated with the two supervisors. The board then granted ten percent of the sum of the supervisors’ salaries and the associated direct costs to compensate Haas for its “home office costs” during the delay. However, the board denied recovery of extended home office overhead as calculated under Eichleay. Altmayer, as the prime contractor, appeals.

Discussion

The primary issue

Free access — add to your briefcase to read the full text and ask questions with AI

Related

KBJ, Inc.
Armed Services Board of Contract Appeals, 2016
SWR, Inc.
Armed Services Board of Contract Appeals, 2014
Oak Environmental Consultants, Inc. v. United States
77 Fed. Cl. 688 (Federal Claims, 2007)
Jackson Construction Co. v. United States
62 Fed. Cl. 84 (Federal Claims, 2004)
Nicon, Inc. v. United States
331 F.3d 878 (Federal Circuit, 2003)
P.J. Dick Inc. v. Principi
324 F.3d 1364 (Federal Circuit, 2003)
Gladwynne Const. v. Mayor and City Council of Baltimore
807 A.2d 1141 (Court of Special Appeals of Maryland, 2002)
Sergent Mechanical Systems, Inc. v. United States
54 Fed. Cl. 47 (Federal Claims, 2002)
Pete Vicari, General Contractor, Inc. v. United States
53 Fed. Cl. 357 (Federal Claims, 2002)
Nicon, Inc. v. United States
51 Fed. Cl. 324 (Federal Claims, 2001)
Overstreet Electric Co. v. United States
47 Fed. Cl. 728 (Federal Claims, 2000)
Melka Marine, Inc. v. United States
187 F.3d 1370 (Federal Circuit, 1999)
Safeco Credit & Fraley Associates, Inc. v. United States
44 Fed. Cl. 406 (Federal Claims, 1999)
Life Care Center of New Market v. Department of Medical Assistance Services
489 S.E.2d 708 (Court of Appeals of Virginia, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
79 F.3d 1129, 1996 WL 124813, Counsel Stack Legal Research, https://law.counselstack.com/opinion/altmayer-v-johnson-cafc-1996.