Overstreet Electric Co. v. United States

47 Fed. Cl. 728, 2000 U.S. Claims LEXIS 200, 2000 WL 1478393
CourtUnited States Court of Federal Claims
DecidedAugust 16, 2000
DocketNo. 00-314C
StatusPublished
Cited by107 cases

This text of 47 Fed. Cl. 728 (Overstreet Electric Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Overstreet Electric Co. v. United States, 47 Fed. Cl. 728, 2000 U.S. Claims LEXIS 200, 2000 WL 1478393 (uscfc 2000).

Opinion

OPINION

ALLEGRA, Judge:

This pre-award bid protest action is before the court on the parties’ cross-motions for judgment on the administrative record. At issue is whether defendant acted arbitrarily and capriciously, and contrary to law, in rejecting plaintiffs low bid because it found the price unreasonable. After careful consideration of the briefs filed by the parties, the oral argument, and for the reasons discussed below, the court GRANTS plaintiffs motion for judgment on the administrative record and DENIES defendant’s motion for judgment on the administrative record. The court further concludes that plaintiff is entitled to injunctive relief as described below.

I. Facts2

On December 6, 1999, defendant, through the Louisville District of the Army Corps of Engineers (the Corps), issued IFB No. DACW27-00-B-0002, which invited sealed bids for a construction project consisting of the rehabilitation of pump stations located on the Little Calumet River in Lake County, Indiana. The solicitation envisioned that the awardee would purchase and have installed the large pumps and piping that form the heart of these facilities, as well as rehabilitate and replace such varied items as electrical wiring, ladders, hoists, floor plates and fencing. The solicitation anticipated that a significant portion of this work would be subcontracted.

The solicitation provided that the project was a “100 per cent set aside for small business” and established a bid opening date of January 5, 2000. On December 23, 1999, the Corps issued Amendment 0001 to the IFB, which changed the contract completion time from 900 to 700 calendar days and made changes to the specifications and drawings. [730]*730On December 27, 1999, the Corps issued Amendment 0002, which added two drawings that had previously been omitted from the solicitation. Three sealed bids were submitted in response to the IFB and were opened on January 5, 2000. Plaintiff, Overstreet Electric Company, Inc., submitted the low bid of $4,638,400; HRP Construction, Inc. submitted a bid of $4,773,545; and Kovilic Construction submitted a bid of $4,827,770.

The Corps’ original estimate of the cost of the Little Calumet project, without profit, was $2,915,265. Plaintiffs low bid exceeded this estimate by 59.1 per cent. After the bid opening, the Corps determined that an upward correction of its estimate was appropriate and increased its estimate to $3,510,910.3 Plaintiffs low bid still exceeded the revised Corps’ estimate by 32.1 per cent. On February 2, 2000, the Corps issued its “Findings and Determination with Respect to Unreasonable Prices,” which explained that all bids would be rejected as excessive and that the IFB would be converted to a negotiated procurement pursuant to Federal Acquisition Regulations (FAR) §§ 14.404-1(c)(6), (e)(1), and (f).4 On February 9, 2000, the Corps amended the solicitation by issuing Amendment 0003, which notified the three bidders that the IFB was being converted to a negotiated procurement. Amendment 0003 noted, in pertinent part:

[In accordance with] FAR 14.404.1(c)(6) ‘Cancellation of Invitations After Opening,’ all bids are hereby rejected and the subject solicitation is hereby converted to a negotiated procurement. Ml otherwise acceptable bids received were at unreasonable prices. Ml bidders are given opportunity to participate in negotiations. The award will be made to the responsible bidder offering the lowest negotiated price.

Plaintiff filed a protest with the General Accounting Office (GAO) on February 15, 2000. In responding to the GAO protest, the Corps indicated that it had rejected the offers based not only on FAR § 14.404.1, but also 33 U.S.C. § 624 (1994). Under the latter section, the Corps is prohibited from awarding a contract for river and harbor improvements if it “determines that the contract price [offered] is more than 25 per centum in excess of what [the Corps] determines to be a fair and reasonable estimated cost of a well-equipped contractor doing the work.” 33 U.S.C. § 624(a)(2). The GAO denied plaintiffs bid protest on May 12, 2000, concluding that “from our review of the protester’s specific allegations challenging the revised government estimate and the agency’s detailed responses, we cannot find the revised government estimate to be materially understated or developed in a manner inconsistent with applicable regulations.” Over-street Electric Co., Inc., B-284691, 2000 WL 621308, at *3 (Comp.Gen. May 12, 2000).

Plaintiff filed this pre-award bid protest on May 25, 2000, seeking a temporary restraining order, a preliminary injunction, and a permanent injunction enjoining the Corps from converting the IFB to a negotiated procurement and from awarding a contract to anyone other than plaintiff as the lowest bidder. The Corps agreed to suspend action on the procurement until August 18, 2000, while the court resolves the pending suit. Based upon this agreement, plaintiff withdrew its request for the temporary restraining order and preliminary injunction. On July 31, 2000, oral argument was conducted on the parties cross-motions for judgment on the administrative record.

II. Discussion

A. Legal Background

In a bid protest case filed preaward, this court will enjoin performance of [731]*731the contract only where the agency’s actions were arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law. 5 U.S.C. § 706(2)(A) (1994). See also 28 U.S.C. § 1491(b)(4) (Supp. III 1997).5 Regarding this standard, which is drawn from the Administrative Procedures Act (APA), 5 U.S.C. §§ 701-706 (1994), the Supreme Court has stated:

Section 706(2) (A) requires a finding that the actual choice made was not “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.” To make this finding the court must consider whether the decision was based on a consideration of the relevant factors and whether there has been a clear error of judgment. Although this inquiry into the facts is to be searching and careful, the ultimate standard of review is a narrow one. The court is not empowered to substitute its judgment for that of the agency.

Citizens to Preserve Overton Park, Inc. v. Volpe, 401 U.S. 402, 416, 91 S.Ct. 814, 28 L.Ed.2d 136 (1971) (citations omitted). See also Advanced Data Concepts, Inc. v. United States, 216 F.3d 1054, 1057-58 (2000); Blount, Inc. v. United States, 22 Cl.Ct. 221, 227, 1990 WL 210734 (1990).6 Accordingly, this court will interfere with the government procurement process “only in extremely limited circumstances.” CACI, Inc-Federal v. United States, 719 F.2d 1567, 1581 (Fed.Cir. 1983) (quoting United States v. John C. Grimberg Co.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
47 Fed. Cl. 728, 2000 U.S. Claims LEXIS 200, 2000 WL 1478393, Counsel Stack Legal Research, https://law.counselstack.com/opinion/overstreet-electric-co-v-united-states-uscfc-2000.