Quality Control International v. United States

United States Court of Federal Claims·Decided January 31, 2020·No. 20-37·Published

Opinion

In the United States Court of Federal Claims No. 20-37C

(Filed: January 31, 2020)* *Opinion originally filed under seal on January 28, 2020

)

QUALITY CONTROL ) INTERNATIONAL, LLC, )

) Bid Protest; Post-Award; Preliminary Plaintiff, ) Injunction )

)

v.

)

)

THE UNITED STATES, )

)

Defendant, )

)

and, )

)

PHOENIX MANAGEMENT, INC., )

)

Defendant-Intervenor. )

)

David A. Rose, Valdosta, GA, for plaintiff. Kara M. Westercamp, Civil Division, United States Department of Justice, Washington, D.C., with whom were Joseph H. Hunt, Assistant Attorney General, Robert E. Kirschman, Jr., Director, Allison Kidd-Miller, Assistant Director, for defendant. Robert Schlattman, Deputy General Counsel, General Services Administration, Denver, CO, of counsel. Johnathan M. Bailey, San Antonio, TX, for defendant-intervenor.

OPINION AND ORDER DENYING PRELIMINARY INJUNCTION

FIRESTONE, Senior Judge.

Pending before the court are the plaintiff’s, Quality Control International, LLC (“QCI”), motions for a temporary restraining order (“TRO”) (ECF No. 2) and preliminary injunction (ECF No. 3). QCI is the incumbent providing current maintenance services for the General Service Administration (“GSA”) in Montana, and its contract is set to end on January 31, 2020. The subsequent contract for these maintenance services was awarded to Phoenix Management, Inc. (“PMI”) on August 28, 2019. QCI was notified about the award on September 6, 2019. QCI protested the award in the Government Accountability Office (“GAO”) on September 16, 2019, and the GAO denied QCI’s protest of the award decision on December 20, 2019. On January 13, 2020, QCI filed a complaint in this court. QCI seeks a preliminary injunction to enjoin the GSA from proceeding with work awarded to PMI pending resolution of this action.

QCI argues that it is entitled to preliminary injunctive relief because QCI is likely to succeed on the merits by showing that but for the GSA’s misleading discussions regarding QCI’s price during the procurement, QCI would have had a substantial chance of being awarded the contract at issue. QCI further argues that QCI will suffer irreparable harm from the costs to mobilize and demobilize equipment for the contract, and that the balance of harms and public interest in awarding a lawful procurement weigh in favor of granting preliminary relief.

The defendant United States (the “government”) and PMI filed oppositions (ECF Nos. 16, 17) to plaintiff’s motions. The government and PMI argue that QCI is unlikely to succeed on the merits because, as the GAO found, GSA’s discussions regarding pricing were consistent among offerors, accurate, and not misleading. The government

and PMI further argue that QCI has not shown that it will suffer irreparable harm, and neither the balance of the hardships nor the public interest weigh in favor of enjoining GSA from obtaining its required services from PMI.

For the reasons that follow, the court finds that QCI has not demonstrated that it is likely to succeed on the merits, that it will suffer irreparable harm, or that the balance of hardships or public interest weigh in favor of granting a preliminary injunction. The plaintiff’s motion for a preliminary injunction is DENIED.1 I. FACTUAL BACKGROUND The following facts are taken from the Administrative Record (“AR”) filed on January 21, 2020 (ECF No. 20).

On May 1, 2018, GSA issued a request for proposals No. 47PJ0018R0027 (“RFP”). AR 1. The RFP was a small business set-aside and sought proposals to provide maintenance services for multiple GSA facilities in Montana. AR 1, 3. The RFP contemplated an award of a fixed-price contract, AR 20, and included a base period of one year and four one-year options, AR 3. In terms of evaluating offers, the RFP explained that award was to be made on a best-value tradeoff basis, with non-price factors, when combined, to be considered approximately equal to price. AR 220.

Regarding price, the RFP stated that prices “will be evaluated for low price, price reasonableness, price realism and balance.” AR 222. Further, the “sum of the pricing . . .

1 Because the court has addressed QCI’s motion for a preliminary injunction prior to QCI’s contract expiration, QCI’s motion for a TRO is DENIED AS MOOT.

in the price proposal submitted by each offeror will be evaluated. Offerors whose prices are unbalanced, unreasonable, or unrealistic, may be rejected as unacceptable.” Id.

On June 6, 2018, QCI timely submitted its first price proposal. AR 224. QCI’s proposed overall price was $6,009,580. AR 233. The GSA evaluated initial proposals. In evaluating QCI’s price, GSA compared the overall price to the Internal Government Estimate (“IGE”) of $7,398,875.37. AR 438. GSA stated that QCI’s “price appears to be borderline unrealistic” and “[w]hen comparing the total costs between the IGE and offeror pricing, QCI’s costs appear unrealistically low” because the proposed price was “19% lower than the IGE and 16% lower than averaged offeror pricing.” AR 440; see AR 488 (Source Selection Evaluation Board Recommendation for first round offers stating the same). The internal review further stated “[h]owever, QCI only has a few pricing elements that appear potentially unrealistic.” AR 440.

GSA decided to conduct discussions with the offerors. In conducting discussions with QCI, GSA noted that several pricing factors were unreasonably or unrealistically low. See AR 268. A letter was subsequently provided on June 10, 2018 to memorialize the discussion. AR 266. In connection to QCI’s price, the letter stated:

• The mechanical level of effort at Bozeman, Butte, and Missoula appear significantly low.

• The mechanical labor costs at Bozeman, Butte, and Missoula appear significantly low.

• The mechanical direct costs (costs other than self-performed labor) appear significantly low at Billings, Bozeman, Butte, and Missoula.

• The offeror’s price of $6,009,580.00 does not appear realistic.

• The price proposal fails to include pricing for an administrative support position.

• The proposed markup rates, when combined, are significantly high.

AR 268; see AR 440 (internal GSA review stating the same). The letter also provided that “any items raised by the Government during the discussions must be addressed in writing in QCI’s revised proposal.” AR 266.

Following the first round of discussions, QCI and other offerors submitted revised proposals. QCI’s revised proposed price was $7,461,340.00. AR 276. GSA evaluated the revised proposals. AR 494. Regarding price, GSA evaluated whether QCI’s revised proposal improved on the previously identified weaknesses. AR 532-33. Regarding QCI’s overall price, GSA stated that “[t]he majority of the price proposal increase is due to the increase level of effort for mechanical, grounds maintenance/snow removal and custodial” and that “QCI’s proposal appears to have addressed our concerns about the low level of total price.” AR 533. The only significant weakness remaining was QCI’s markup rate. Id.; see AR 546 (Source Selection Evaluation Board Recommendation stating the same); AR 552 (Source Selection Decision Document stating the same).

GSA decided to conduct another round of discussions with six offerors, AR 548, and a letter was subsequently provided on July 23, 2019 to memorialize those discussions with QCI, AR 309. The letter stated:

• QCI’s markup rates remain high.

• QCI was also notified that it is not the Government’s intention to conduct another round of discussions so offerors should submit their most competitive offer.

AR 310.

Following the final round of discussions, QCI and other offerors submitted final revised proposals. QCI’s final proposed price was $7,247,080.00. AR 317. GSA

evaluated the final revised proposals, AR 555, and determined that QCI’s final revised price was consistent with the Government estimate and that the markup rates remained high, AR 572. However, GSA concluded that the markup rates were “not a weakness” despite raising GSA’s costs by $180,000. AR 597.

Free access — add to your briefcase to read the full text and ask questions with AI

Quality Control International v. United States, (uscfc 2020).

Quality Control International v. United States (Quality Control International v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related