Jackson Construction Co. v. United States

62 Fed. Cl. 84, 2004 U.S. Claims LEXIS 245, 2004 WL 2095579
CourtUnited States Court of Federal Claims
DecidedSeptember 15, 2004
DocketNo. 97-31C
StatusPublished
Cited by11 cases

This text of 62 Fed. Cl. 84 (Jackson Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jackson Construction Co. v. United States, 62 Fed. Cl. 84, 2004 U.S. Claims LEXIS 245, 2004 WL 2095579 (uscfc 2004).

Opinion

OPINION

YOCK, Senior Judge.

This dispute arose out of a construction contract between the plaintiff, Jackson Construction Company, Inc. (“Jackson”), and the defendant, the Department of the Army New York District Corps of Engineers (“Corps”). Evidence and testimony was presented to the Court at a trial held in this case on April 20-22, 2004. In accordance with Contract No. DACA 51-92-C-0092 (“Contract”), Jackson constructed a new building for the Corps, the Technical Information Analysis Center (“TIA Center”), which was located on the grounds of the Corps’ Cold Regions Research and Engineering Laboratory (“CRREL”) in Hanover, New Hampshire. Jackson began construction on October 26,1992, and completed the TIA Center on March 30, 1994, the completion date mandated by the Contract. Jackson was paid $4,183,189 under the Contract, which included the lump-sum Contract price of $3,565,000 plus $618,189 in additional compensation for changes to the work that were agreed upon and authorized by bilateral modifications. Although Jackson completed the work within the time mandated by the Contract and was paid for all the changes required by the Corps, Jackson nevertheless brought this lawsuit in which it seeks to recover additional compensation in the form of delay and impact damages.

At trial, Jackson presented two separate claims, an early completion delay claim and an impact claim. First, Jackson contends that it had to overcome a 120-day delay at the start of the project, during which Jackson redesigned and relocated a waterline that ran through the footprint of the ,new building. According to Jackson, “[tjhis early delay, occasioned by the redesign and relocation of the utilities, carried over a one hundred twenty (120) day period from late October of 1992 through March of 1993.” PL, Jackson Construction Company’s Mem. in Support of PL’s Claims for Delay and Impact Costs and Unabsorbed Overhead Costs at 3 (“PL’s Post-trial Mem.”).1 Under Count I, Jackson seeks $196,338 in damages for this claim, which represents additional home office overhead incurred during the delay period calculated using the Eichleay formula.

Second, Jackson has claimed additional damages that were allegedly incurred due to the cumulative impact of the numerous changes required by the Corps during the course of performance. According to Jackson, the Corps issued hundreds of changes, which resulted in 24 bilateral modifications that increased the Contract price by $618,189. See PL’s Post-trial Mem. at 1, 3. Under Count II, Jackson requested $135,078 for this cumulative impact claim, which it calculated using the total cost method. Finally, Jackson’s Complaint had also asserted an additional claim for extra work totaling $35,325 under Count III, but this claim was dismissed before the trial because the parties reached a settlement regarding payment for the claimed extra work.

After conducting a trial on the merits of Counts I and II and considering all of the evidence presented at trial, the Court concludes that the defendant prevails in this action.2 First, Jackson’s claims under Count [88]*88I and Count II are barred by the doctrine of accord and satisfaction. Second, even if Jackson’s claims were not barred by accord and satisfaction, Jackson failed to prove either claim on the merits. On Count I, Jackson did not meet its burden of proving the existence and extent of a compensable delay, nor did it prove entitlement to Eichleay damages under an early completion theory. On Count II, Jackson did not meet its burden of proving the existence of a cumulative impact claim, nor did it prove entitlement to damages under a total cost theory. Accordingly, judgment must be entered on behalf of the defendant on both Count I and Count II of the Complaint.

Facts

A. The Contract

On September 23,1992, Jackson submitted its bid for the TIA Center project, which was located at the Corps’ existing CRREL facility in Hanover, New Hampshire. The Corps awarded the Contract to Jackson on September 30, 1992, and the parties executed Contract No. DACA 51-92-C-0092 in the amount of $3,565,000. The total Contract price included Jackson’s base bid amount of $3,550,000, which covered all labor, materials, equipment, and services required to construct the TIA Center, and an additional $15,000 for an optional item, demolition of the ATCO building at the CRREL facility. By the time the Corps made final payment upon Jackson’s completion of the Contract, the Corps had paid Jackson a total of $4,183,189, which included the full Contract price of $3,565,000 plus an additional $618,189 resulting from 24 bilateral modifications. These bilateral modifications compensated Jackson for changes that occurred during the course of performance.

The Contract required Jackson to “complete the entire work ready for use not later than 520 calendar days after the date the Contractor receives the notice to proceed * * Joint Ex. 1, Contract, Section H.l.a. The parties have stipulated that the Corps issued the notice to proceed on October 21, 1992, and that Jackson acknowledged receipt of that notice on October 26, 1992. The parties further stipulated that Jackson achieved beneficial occupancy 520 days later, on March 30, 1994. Jackson, however, contends that it would have completed the Contract four months earlier if it had not been for delays caused by the Corps at the beginning of the project. At trial, Jackson attributed most of the delays to problems that it had encountered with an 8-inch waterline that ran through the footprint of the new building. According to Jackson, this problem with the waterline hindered its progress from October 1992 through March 1993.

B. Waterline relocation

Much of the evidence heard at trial related to Jackson’s assertion of a 120-day delay at the beginning of the Contract arising from its relocation of an 8-inch waterline that was located within the footprint of the new TIA Center. This waterline serviced several existing buddings that were adjacent to the new construction. The drawings that accompanied the bid solicitation depicted the waterline’s location within the footprint and contained a note that confirmed the contractor’s responsibility to maintain water service to the adjacent buildings at all times during construction and to protect the waterline “from the elements” during construction. Def.’s Ex. 83/6 (Plans Sheet C-1, Rev. 1, Note 2).

Much of the testimony regarding the difficulties experienced by Jackson related to this waterline came from Jackson’s superintendent, Mr. John Sullivan, who was responsible for overseeing the work on a daily basis. Mr. Sullivan became involved in the project in late October 1992, as Jackson mobilized at the site following receipt of the notice to proceed. According to Mr. Sullivan, at the very beginning of his involvement, Jackson’s estimator, Mr. Vinny Murphy, had alerted him that it was going to be a “problem * * * to work around the waterline” within the footprint. Tr. at 200. Mr. Sullivan described the Corps’ plan to maintain the waterline within the footprint during construction as both a logistical problem and a potential hazard:

[89]*89A * * * You know, nothing is impossible. We put a man on the moon, so obviously we can put up this building. You know, it’s never an issue. But the problem was that we were inviting trouble.
Q Why ?

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ingham Regional Medical Center v. United States
126 Fed. Cl. 1 (Federal Claims, 2016)
Imprimis Investors LLC v. United States
83 Fed. Cl. 46 (Federal Claims, 2008)
Bell BCI Co. v. United States
81 Fed. Cl. 617 (Federal Claims, 2008)
Axion Corp. v. United States
68 Fed. Cl. 468 (Federal Claims, 2005)
District of Columbia v. United States
67 Fed. Cl. 292 (Federal Claims, 2005)
Southern Comfort Builders, Inc. v. United States
67 Fed. Cl. 124 (Federal Claims, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
62 Fed. Cl. 84, 2004 U.S. Claims LEXIS 245, 2004 WL 2095579, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jackson-construction-co-v-united-states-uscfc-2004.