Westerhold v. United States

38 Cont. Cas. Fed. 76,509, 28 Fed. Cl. 172, 1993 U.S. Claims LEXIS 15, 1993 WL 133565
CourtUnited States Court of Federal Claims
DecidedApril 27, 1993
DocketNo. 757-85C
StatusPublished
Cited by12 cases

This text of 38 Cont. Cas. Fed. 76,509 (Westerhold v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Westerhold v. United States, 38 Cont. Cas. Fed. 76,509, 28 Fed. Cl. 172, 1993 U.S. Claims LEXIS 15, 1993 WL 133565 (uscfc 1993).

Opinion

[173]*173OPINION

SMITH, Chief Judge.

This case involves a government contractor’s claim for an equitable adjustment to a contract with the General Services Administration (GSA). The contract was for the construction of two overhead walkways at the Federal Center in Saint Louis, Missouri, between two sets of buildings at the Center. Plaintiffs, Harold Richard Westerhold and Marjorie Ann Lanemann Westerhold, have performed the contract and pursuant to 41 U.S.C. § 609(a)(1) (1988), appeal from the contracting officer’s (CO) final decision denying their request for relief. After a two day trial, and a thorough consideration of the legal issues before it, the court finds that the plaintiffs partially prevail on the merits. However, plaintiffs have failed to prove any delay damages. As a result of representations at trial, the court will allow plaintiffs to submit a status report supporting a refund of any previously paid liquidated damages not to exceed $6,100.

FACTS

On October 22, 1982, the contract at issue here was awarded to Dimarco Corporation (Dimarco).1 The GSA issued a notice to proceed on November 22, 1982, with a scheduled completion date 180 days later (May 23, 1983). The original contract price was the lump sum of $310,002.00. All of the plans, specifications, and other contract documents were prepared by defendant.

Plaintiffs claim that in November of 1982 while Dimarco was preparing the steel fabrication drawings, using the plans and specifications of the contract, it noticed that there was no provision in any of the contract documents for any camber2 on the longitudinal axes of either of the two walkways. On December 7, 1982, when Dimar-co sent its steel fabrication drawings to defendant for approval, plaintiffs claim that they expected defendant to make a provision for longitudinal camber. However, on December 29, 1982, defendant returned to Dimarco its steel fabrication drawings approved but without any provisions for longitudinal camber. Plaintiff, Harold Westerhold, alleged that he contacted defendant by telephone to raise the camber question, but received no definitive response. Defendant disputed that this conversation occurred.

On January 10, 1983, Dimarco sent its purchase order to Hammert’s Iron Works (Hammert’s) for the purchase of the required structural steel, however, the steel contained no provision for any longitudinal camber. Dimarco wrote defendant regarding its concern for the lack of camber on February 3, 1983, and on February 15, 1983, defendant notified plaintiffs that two inches of camber was to be built into the trusses of the walkways. However, defendant refused to admit that the added camber justified any contract modification. When notified that camber was needed, Hammert’s agreed to provide the camber in the appropriate pieces of steel if the price for the steel was increased by $4,500.00, there was no guaranteed delivery date, and that Dimarco make no claim against Ham-mert’s for any liquidated damages. Plaintiffs allege that defendant threatened to cancel Dimarco’s contract if it did not show appropriate activity on the job site. Therefore, Dimarco argues it was forced to do part of the steel fabrication at the job site, and it cancelled its contract with Ham-mert’s.

Dimarco then notified defendant that with the added charges for overhead, labor, and profit, its price for the camber addition [174]*174would be $5,693.00 and that an extension of time to September 30, 1983, to complete the contract would also be necessary. On April 12, 1983, defendant informed Dimar-co that it would issue a proposal request to Dimarco for the cost of adding camber, which it did on July 6, 1983. On July 8, 1983, Dimarco sent its proposal to add the camber for $5,693.00. Defendant accepted Dimarco’s proposal on August 31,1983, but refused to give Dimarco a new completion date. Pursuant to a subsequent letter from GSA, dated November 11, 1983, the completion date was extended 59 days.

The contract also provided for steel “L” angle irons in the top chord3 of the trusses of the walkways. The dimensions of the “L” angle irons were prescribed as being seven inches by four inches by five eighths of an inch. These angle irons were special order items as they were not readily available in regular production. Dimarco proposed that “L” angle irons of a thickness of half an inch be substituted for the angle irons of five eighths of an inch thickness, but defendant refused. Subsequently angle irons with a thickness of three quarters of an inch were substituted, however, defendant refused to modify the contract by adding $2,363.00 to the total price of the contract to cover the thicker angle irons.

Dimarco claimed it was damaged in the total amount of $80,283.55. By the CO’s final decision of December 20, 1984, Dimar-co’s claim was denied in its entirety. The CO’s decision was received by Dimarco on December 28,1984. Dimarco filed its claim in this court on December 26, 1985. Plaintiffs seek a judgment against defendant in the amount of $80,283.55, with interest thereon per 41 U.S.C. § 611 from July 26, 1984 until paid, together with their costs and reasonable attorney’s fees.

Due to the serious illness of one of the key individuals involved in this litigation, more delay has occurred in resolving this suit than is normally desirable.

DISCUSSION

I. Defective Specifications and Accord and Satisfaction

It is well-settled law that government contracts contain a warranty that if the specifications are followed satisfactory performance is possible. However, if defective specifications result in increased costs by reason of the defect, the government is liable. United States v. Spearin, 248 U.S. 132, 39 S.Ct. 59, 63 L.Ed. 166 (1918). The damages recoverable extend to any costs incurred due to delay incurred by reason of the mistake in the specifications. Laburnum Constr. Corp. v. United States, 163 Ct.Cl. 339, 350, 325 F.2d 451 (1963). “[A]ll delay produced by defective specifications is per se unreasonable and compensable.” Beauchamp Constr. Co. v. United States, 14 Cl.Ct. 430 (1988), citing Chaney and James Constr. Co. v. United States, 190 Ct.Cl. 699, 707, 421 F.2d 728 (1970). The lack of camber in the specifications is clearly a design defect as evidenced by testimony at trial.

Plaintiffs seek $77,920.55 (plus interest) as a result of the cost of delay for incorporating the camber. It is not disputed that delay damages may be recoverable in certain cases, such as in Beauchamp Constr. Co., however, defendant contends that such an entitlement is barred by an accord and satisfaction when a comprehensive contract modification is executed without reserving the right to bring additional claims. De Barros v. United States, 5 Cl.Ct. 391 (1984); B.D. Click Co. v. United States, 222 Ct.Cl. 290, 295, 614 F.2d 748 (1980);

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jackson Construction Co. v. United States
62 Fed. Cl. 84 (Federal Claims, 2004)
W & F Building Maintenance Co. v. United States
56 Fed. Cl. 62 (Federal Claims, 2003)
National Steel & Shipbuilding Co. v. United States
49 Fed. Cl. 579 (Federal Claims, 2001)
Starflight Boats v. United States
48 Fed. Cl. 592 (Federal Claims, 2001)
Bank United v. United States
49 Fed. Cl. 1 (Federal Claims, 1999)
Statesman Savings Holding Corp. v. United States
41 Fed. Cl. 1 (Federal Claims, 1998)
Morris v. United States
39 Fed. Cl. 7 (Federal Claims, 1997)
Neal & Co. v. United States
41 Cont. Cas. Fed. 77,003 (Federal Claims, 1996)
United International Investigative Services v. United States
40 Cont. Cas. Fed. 76,767 (Federal Claims, 1995)
Coastal Industries, Inc. v. United States
39 Cont. Cas. Fed. 76,722 (Federal Claims, 1994)
McLain Plumbing & Electrical Service, Inc. v. United States
39 Cont. Cas. Fed. 76,593 (Federal Claims, 1993)
Mega Construction Co. v. United States
39 Cont. Cas. Fed. 76,564 (Federal Claims, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
38 Cont. Cas. Fed. 76,509, 28 Fed. Cl. 172, 1993 U.S. Claims LEXIS 15, 1993 WL 133565, Counsel Stack Legal Research, https://law.counselstack.com/opinion/westerhold-v-united-states-uscfc-1993.