National Steel & Shipbuilding Co. v. United States

49 Fed. Cl. 579, 2001 U.S. Claims LEXIS 117, 2001 WL 747853
CourtUnited States Court of Federal Claims
DecidedJune 15, 2001
DocketNo. 96-112C
StatusPublished
Cited by1 cases

This text of 49 Fed. Cl. 579 (National Steel & Shipbuilding Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Steel & Shipbuilding Co. v. United States, 49 Fed. Cl. 579, 2001 U.S. Claims LEXIS 117, 2001 WL 747853 (uscfc 2001).

Opinion

OPINION

HORN, Judge.

This case arises out of a government contract for the design and construction of the AOE-6 Class of Past Combat Support Ships on which plaintiff, National Steel and Shipbuilding Company (NASSCO), was the prime contractor. NASSCO filed a complaint in this court challenging the final decision of the contracting officer denying plaintiffs request for an equitable adjustment of the contract. NASSCO submitted the request for equitable adjustment primarily on behalf of its first tier subcontractor, Jered Brown Brothers Inc. (JBB) and its second-tier subcontractor, YARD USA, Inc. (YUSA). Plaintiff bases its claim for equitable adjustment on delays incurred by it and its subcontractors due to alleged defective government specifications and the alleged late delivery or failure by the government to deliver government furnished equipment and government furnished information (collectively referred to as government furnished property). The total amount NASSCO claims it is due is $1,830,579.00, plus interest since July 23, 1990. Initially, the court held a trial on the limited issue of whether plaintiffs claim regarding delays arising from the lack of government furnished property is barred by an accord and satisfaction.

The parties agree that the issue before the court in the limited trial was whether contract Modification A00139, executed by the parties on March 7 and 8 of 1989, constituted an accord and satisfaction sufficient to discharge NASSCO’s claim for all damages arising out of the lack of government furnished property. Based on the joint stipulations, the testimony of the witnesses presented at the trial and the exhibits entered into evidence, the court finds that Modification A00139 covers the management costs of handling, reviewing, negotiating and attempting to resolve the problems associated with the lack of government furnished property. For example, the Modification covers the costs of audits, exchanges of correspondence and developing supporting documentation. Modification A00139, however, does not cover the actual delay costs arising out of the government’s failure and, in part, alleged failure to make the government furnished property available to NASSCO and its subcontractors on schedule. The parties continued to negotiate the claims for delay costs caused by the lack of government furnished property after they executed Modification A00139, manifesting an intent that they did not settle those claims. Therefore, Modification A00139 did not act as an accord and satisfaction discharging NASSCO’s claim for delay damages arising out of the lack of government furnished property.

FINDINGS OF FACT

NASSCO was the prime contractor on Contract No. N00024-87-C-2002 for the design and construction of the AOE-6 Class of Fast Combat Support Ships. NASSCO was to construct one AOE.-6 ship with a government option for three additional ships. The AOE-6 was to contain a steering system consisting of two parts, the machinery centralized control subsystem and the computerized steering control subsystem. The subcontractor for the steering system was JBB. JBB employed YUSA as a second-tier subcontractor to furnish and install the computerized steering control subsystem for the AOE-6 steering system. JBB designed and manufactured the machinery centralized control subsystem itself.

The government solicited bids for the contract on or about June 10, 1986. ’ Bidders were to submit their offers on October 31, 1986. The government awarded the firm, fixed-price contract to NASSCO in the amount of $290,097,944.00 on January 23, 1987. The contract set the delivery date at fifty-one months after contract award, or April 23, 1991. The government later extended the date for delivery.

The contract specifications for the AOE-6 required a computer based steering control subsystem, anchored by an AN/UYK-44 computer. A steering control subsystem of this type was, at that time, unconventional. The AN/UYK-44 computer was a militarized computer, not a commercial computer, de[581]*581signed to function in a stressful environment. A militarized computer was deemed important because the ship was certified to operate while being exposed to explosions of certain magnitudes.

To provide equipment and information for the AN/UYK-^4 computer, the contract included Clause H-58(a), titled “Government-Furnished Property.” The clause required the government to deliver to NASSCO certain equipment and information “described as Government-furnished property and in the Schedule or specifications, together with such related data and information as the Contractor may request and as may reasonably be required for the intended use of such property .... ” The government was required to deliver to NASSCO property suitable for use by set dates. If the government failed to deliver such property in time, the contracting officer would equitably adjust the delivery date, the performance date and/or the contract price.

The contract also included Attachment J-9, “Schedule ‘A’ List of Government Furnished Material for AOE-6 Class Fast Combat Support Ships,” and Attachment J-10, “Fast Combat Support Ship AOE-6 Government Furnished Information Schedule ‘C,’ ” which listed specific government furnished property. The government furnished property listed in the attachments included one AN/UYK-44 computer for the AOE-6 steering control subsystem, one AN/UYK-44 Data Processing Set and nine technical manuals for the Data Processing Set. On July 21, 1987, NASSCO submitted a letter to the government on behalf of JBB requesting the government furnished property listed in Schedules A and C by specific dates. In addition to the government furnished property listed under the schedules, NASSCO also requested additional material and information, not in the contract, which YUSA believed it needed to complete the computer based steering control subsystem.

On July 23, 1987, NASSCO received the technical manuals from the government. However, items of government furnished property remained outstanding. On September 24,1987, NASSCO again requested these items from the government. NASSCO followed up with similar letters to the government on October 14 and October 19 of the same year. On December 3, 1987, NASSCO submitted Contract Problem Report No. 17 (CPR-17)1 to the government, which referenced its previous four letters requesting government furnished property, and repeated its need for the government furnished property.

To address the problems caused by the lack of government furnished property, the government began to consider installing a commercially available computer system in the AOE-6, instead of the militarized AN/ UYK-44. The government described this option in Preliminary Engineering Change Proposal (ECP) H-051, which proposed eliminating all steering control subsystem government furnished property. Subsequently, the government asked NASSCO to prepare a report describing the cost consequences of instituting ECP H-051. NASSCO began preparing ECP C-014 in response. On January 25, 1988, however, the government canceled its request to prepare ECP C-014. As an alternative, the government asked NASSCO to submit it its own proposal for' using commercially available parts for the AOE-6 steering control subsystem. Thus, NASSCO began to prepare ECP C-017.

The government continued to consider other methods of resolving the impact of the lack of government furnished property.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

W & F Building Maintenance Co. v. United States
56 Fed. Cl. 62 (Federal Claims, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
49 Fed. Cl. 579, 2001 U.S. Claims LEXIS 117, 2001 WL 747853, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-steel-shipbuilding-co-v-united-states-uscfc-2001.