Texas Instruments Incorporated v. The United States

922 F.2d 810, 1990 WL 209421
CourtCourt of Appeals for the Federal Circuit
DecidedMarch 19, 1991
Docket90-1194
StatusPublished
Cited by22 cases

This text of 922 F.2d 810 (Texas Instruments Incorporated v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Texas Instruments Incorporated v. The United States, 922 F.2d 810, 1990 WL 209421 (Fed. Cir. 1991).

Opinion

*811 CLEVENGER, Circuit Judge.

Texas Instruments Incorporated (“TI”) appeals the final decision of the Armed Services Board of Contract Appeals (“ASBCA”) that “the amount of $628,069 is determined to be a fair and reasonable price for [Contract] Modification PK0005.” Texas Instruments Inc., 90-1 BCA (CCH) 1122,537, at 113,097, 1989 WL 222693 (ASBCA Sept. 29, 1989) (“TI II”). In an earlier non-final decision, upon cross-motions for partial summary judgment, the ASBCA had determined that TI and the Administrative Contracting Officer (“ACO”) had not reached a final binding agreement on a price of $672,067.86 as reflected in a Price Negotiation Memorandum (“PNM”) signed by the ACO. The ASBCA held that the PNM was not a “final decision on the price of the order” and did not effect a “commitment by the Government to a price on which [TI] could reasonably have relied.” Texas Instruments, Inc., 87-1 BCA (CCH) 1119,394, at 98,079 (ASBCA Sept. 17, 1986) (“TI I”), reh’g denied, 87-2 BCA (CCH) 1119,767 (ASBCA Jan. 14, 1987). Since the ASBCA erred in holding that the ACO lacked authority to enter into a binding agreement, and the unchallenged facts demonstrate the existence of final binding agreement, we reverse.

I

Contract No. F19628-77-C-0126, for the supply of tactical photographic interpretation equipment and supporting materials, was awarded to TI on May 27, 1977, by the U.S. Air Force. The contract provided that unpriced line items were to have their firm fixed price bilaterally negotiated after issuance of an order for the item. The Government issued Provisioned Item Order PK0005 on September 30, 1980, with a “not-to-exceed price” of $672,067.95. Ms. Ruby Hill, the ACO, assigned Mr. Jim Jeppe, to meet with TI’s representative, Mr. Alan Johnson, to negotiate a price. Prior to meeting with Johnson, Jeppe reviewed the price analyst’s report, the audit reports and, along with Hill, defined the Government’s objective. On August 24, 1981, after three days of discussion, the two representatives arrived at a firm fixed price. Johnson wrote a letter to Jeppe stating that, as of August 24, TI “agrees to a firm fixed price of $672,067.86.” Johnson also submitted an executed Certificate of Current Cost or Pricing Data that referred to the negotiated price.

Regulations governing procurement by negotiation require that the “contractor shall be required to submit only one certificate which shall be submitted as soon as practicable after agreement is reached on the contract or modification price.” DAR § 3-807.6(a); 32 C.F.R. § 3-807.6(a) (1982). In the absence of such a certificate, “the contracting officer shall withhold making the award or price adjustment.” DAR § 3-807.5; 32 C.F.R. § 3.807.5 (1982); see also § 3-807.3(b) (“certification is required prior to: (1) the award of any negotiated contract (except for unpriced actions such as letter contracts) expected to exceed $100,000 in amount”); 41 U.S.C. § 254(d) (certification that pricing data in non-bid contracts or modifications are accurate, complete and current).

On September 15, Jeppe prepared a PNM reviewing the events that led to the negotiation of the price. Preparation of a PNM after completion of a price negotiation is required by the Defense Acquisition Regulations. DAR § 3-811; 32 C.F.R. § 3-811 (1982). A PNM is an internal document not transmitted to the contractor. In non-bid, negotiated contracts, the PNM must refer to the contractor’s submitted certificate of cost or pricing data. Id. Jeppe noted that such a certificate had been submitted. The PNM further stated that “[t]he negotiated amount of $672,067.86 is considered fair and reasonable” and that “[fjunds have been obligated as follows” with a reiteration of the negotiated amount. Underneath Jeppe’s name as author, the PNM had a signature block which contains Hill’s signature and which reads:

APPROVED BY:
RUBY L. HILL
Administrative Contracting Officer

The ASBCA found that “[t]he PNM had to be acceptable to Ms. Hill before she would sign it” and that “[t]he PNM was submitted to, and approved and signed by Ms. Hill, the ACO.” At the time they *812 signed the PNM, both Jeppe and Hill considered the amount negotiated to be a fair and reasonable price. TI I at 98,073 (Finding 11). Jeppe and Johnson had negotiated several previous provisioned items. In each instance, the ACO had issued a Standard Form 30 (“SF-30”) confirming the agreed upon price following the negotiation and submittal of an appropriate certificate. Jeppe visited the TI plant on September 28, after preparing the PNM and obtaining the ACO’s approval. Johnson stated in a sworn affidavit not disputed by the Government that during a conversation with Jeppe on September 28, Johnson was told to submit a new Certificate of Current Cost or Pricing Data as the caption had been incorrect on the first one. TI forwarded a second executed certificate on October 2. Unbeknownst to TI, events following this meeting on September 28 succeeded in derailing the issuance of an SF-30 by the ACO. First, Jeppe and other Government personnel examined the electronic equipment provisioned by the order. They believed that the cost was not justified by the apparently simple design, but they were mistaken in believing the design to be simple. TI II at 113,090-091 (Finding 19-21). Second, Jeppe was informed that costs for work on software development of the electronic equipment had been allocated to an earlier contract. This information was also wrong. Id. (Finding 19, 22-23).

Finally, and also unknown to TI, the Department of Defense had established an internal audit procedure whereby all contract administration actions taken by ACO’s were subjected to review by Contract Management Boards of Review (“Review Board”). Neither Jeppe nor Hill had discussed this review procedure with TI. Jeppe later noted that “[tjhis review is required for proposed contracts of this type over $250,000, and is required before the Government and contractor enter into a formal (signed) contract.” ASBCA found that the ACO “was not free ... to utterly ignore the review process.” TI I at 98,079. “She was obliged, instead, to await the [Review] Board’s report and, prior to proceeding with the pricing of the order, to give due and careful consideration to any recommendations made therein.” Id. Review Boards are authorized under two published regulations, DAR § 23-104 and DAR § 8-600, neither of which concern contracts to be negotiated by an ACO. 32 C.F.R. §§ 8-600, 23-104 (1982). Under a non-public directive, their authority was extended to include “examin[ation] and evaluation of] documentation concerned with contract administration actions which have been negotiated or otherwise completed and processed by an ACO.”

On October 2, the Review Board requested supplemental data to answer questions on the price negotiations for this Order. TI I at 98,073 (Finding 12).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bullock v. United States
10 F.4th 1317 (Federal Circuit, 2021)
Sigma Construction, Inc. v. United States
113 Fed. Cl. 13 (Federal Claims, 2013)
Sperient Corporation, Inc. v. United States
113 Fed. Cl. 13 (Federal Claims, 2013)
Sikorsky Aircraft Corp. v. United States
105 Fed. Cl. 657 (Federal Claims, 2012)
Reeves v. Dept. Of Veterans Affairs
682 F.3d 988 (Federal Circuit, 2012)
Boeing Co. v. United States
75 Fed. Cl. 34 (Federal Claims, 2007)
Jaynes v. United States
68 Fed. Cl. 747 (Federal Claims, 2005)
Ahrens v. United States
62 Fed. Cl. 664 (Federal Claims, 2004)
W & F Building Maintenance Co. v. United States
56 Fed. Cl. 62 (Federal Claims, 2003)
Kanag'Iq Construction Co. v. United States
51 Fed. Cl. 38 (Federal Claims, 2001)
National Steel & Shipbuilding Co. v. United States
49 Fed. Cl. 579 (Federal Claims, 2001)
Lamirage, Inc. v. United States
44 Fed. Cl. 192 (Federal Claims, 1999)
Green Management Corp. v. United States
42 Cont. Cas. Fed. 77,412 (Federal Claims, 1998)
McDonnell Douglas Corp. v. United States
41 Cont. Cas. Fed. 77,046 (Federal Claims, 1997)
Thomas Creek Lumber & Log Co. v. United States
41 Cont. Cas. Fed. 76,971 (Federal Claims, 1996)
Marlen C. Robb & Son Boatyard & Marina, Inc. v. the Vessel Bristol
893 F. Supp. 526 (E.D. North Carolina, 1994)
Solar Turbines, Inc. v. United States
37 Cont. Cas. Fed. 76,092 (Court of Claims, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
922 F.2d 810, 1990 WL 209421, Counsel Stack Legal Research, https://law.counselstack.com/opinion/texas-instruments-incorporated-v-the-united-states-cafc-1991.