Franklin Pavkov Construction Co. v. James G. Roche, Secretary of the Air Force

279 F.3d 989
CourtCourt of Appeals for the Federal Circuit
DecidedMarch 22, 2002
Docket01-1010
StatusPublished
Cited by17 cases

This text of 279 F.3d 989 (Franklin Pavkov Construction Co. v. James G. Roche, Secretary of the Air Force) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Franklin Pavkov Construction Co. v. James G. Roche, Secretary of the Air Force, 279 F.3d 989 (Fed. Cir. 2002).

Opinion

GAJARSA, Circuit Judge.

This is an appeal from the Armed Services Board of Contract Appeals (the “Board”). On appeal, Franklin Pavkov Construction Company (“FPC”) seeks an equitable adjustment for claims arising from a fixed-price contract to install four sets of three-story stairs on two dormitory buildings at Shaw Air Force Base, South Carolina (the “Project”). FPC argued that it received defective specifications and defective government-furnished material, and that it was entitled to other adjustments. The Board denied all but one of FPC’s claims. We affirm the Board’s decision.

I. BACKGROUND

On October 26, 1995, the Twentieth Contracting Squadron at Shaw Air Force Base, South Carolina (the “Government”) awarded the Project to FPC. The Project had been previously bid and contracted to a different contractor in 1991-. The previous attempt to implement the project was unsuccessful. In 1995, the Government had the specification, drawings and materials from the incomplete 1991 Project. The Government modified the 1991 specifications and drawings for a second bid process that led to FPC winning the bid for the Project in 1995. These are referred to as the “1995 specifications” and “1995 drawings” in contrast to the “1991 specifications” and “1991 drawings” from the earlier Project. In addition, the Government revised some “shop” drawings generated during the unsuccessful attempt to construct the Project in 1991. These are referred to as the “D & H drawings” (named after the subcontractor who prepared them in 1991).

Mr. Milling, a Government engineer, intended the solicitation for bids to contain (i) the 1995 specifications, (ii) the 1995 drawings (five pages), and (iii) the D & H drawings (six pages). He provided these materials to the Government’s office of contracting for distribution to potential bidders. The Board found that when FPC ordered the bid solicitation package, the Government, for unexplained reasons, sent FPC only (i) the 1991 specifications and (ii) the 1995 drawings. The Government did not send FPC the D & H drawings. The front page of the solicitation delineated the documents and exhibits supposedly attached to the solicitation by including the following language:

a. Specifications for Repair Stairs at Dorms 418 and 430
Project SHA 87-0014, dated 3 March 1995.
b. Drawings for Repair Stairs at Dorms 418 and 430
Project SHA 87-0014, 40 pages.

Thus, this language indicated that forty pages of drawings were included, although the Government intended to include only eleven pages of drawings with the pack *992 age, and only five pages were sent to FPC. The five pages of 1995 drawings sent to FPC, however, were numbered as sheets one through five of five, respectively. The language also indicated that the 1995 specifications were attached, although FPC received the 1991 specifications.

Mark Pavkov of FPC bid the Project, but his brother, Vince Pavkov, was to implement the Project with another company as a subcontractor to FPC. Mark Pavkov had his brother Vince Pavkov visit the job site twice during the bidding process before the Government awarded the contract.

On October 26, 1995, the Government awarded the Project to FPC as a fixed-pl'ice contract for $158,100. The completion date was scheduled for November 26, 1996. At a preconstruction conference held November 16, 1995, the Government gave Vince Pavkov five sets of (i) the 1991 specifications and (ii) the 1995 drawings. In January or February 1996, FPC serendipitously discovered the D & H drawings by hiring an employee who happened to have worked on the unsuccessful 1991 construction of the Project. In mid-September to early October, 1996, when the Project was approximately ninety percent complete, it came to Vince Pavkov’s attention that the Government inspector was making statements contrary to the specifications in FPC’s possession. The parties compared the specifications in FPC’s possession with those in. the Government’s possession. The Government inspector had been using the 1995 specifications while FPC had been using the 1991 specifications. The Government had the materials and components from the earlier contractor’s unsuccessful attempt in 1991 to build the stairs. It listed these in the contract for the Project as material that the Government would furnish. The list included thirty line items, each with an item number, description and quantity. The list had a qualifying statement that the materials were provided “as is and any cleaning, scraping, painting or other forms of reconditioning required to make the material meet specifications shall be the responsibility of the contractor.” The contract for the Project also included a short-form Government Furnished Property (“GFP”) clause. This clause required the Government to supply GFP identified in the list. Federal Acquisition Regulations (“FAR”) Government-Furnished Property (Short Form) § 52.245-4(a); 48 C.F.R. § 52.245-4(a) (2000). However, the contract did not explicitly obligate the government to provide shop drawings as part of the GFP.

Just before FPC started construction, the Government moved the purportedly listed GFP to a fence-enclosed but unlocked location 100 to 200 yards from the job site. The Government made two attempts to meet with Vince Pavkov in November 1995 to take an inventory of the GFP. Vince Pavkov cancelled the first planned meeting. At the second meeting in late November 1995, the parties met at the fenced location and began to take the inventory. However, before completing the inventory, Vince Pavkov had to leave. One of the items that the parties did not inventory were the “stair nosings,” devices that prevent slipping on the steps. The GFP list indicated that the Government was to supply eighty-seven stair nosings, but when Vince Pavkov later went to retrieve them he found only ten in the fence-enclosed area. FPC advised the Government of the missing nosings on May 14, 1996, approximately six months after the GFP was delivered. Fabricating and procuring the missing stair nosings had a long lead-time. In order to avoid delaying the Project, FPC obtained permission from the Government to use a substitute aluminum channel.

*993 FPC recognized another problem with the GFP. The configuration of some of the parts caused FPC to question whether all of the stairs were “typical” as shown on the 1995 drawings. After it discovered the D & H drawings, FPC determined that some stair directions were not typical as indicated. The direction of a set of stairs is the direction in which they rise or fall when viewing the side of the building. A note on the D & H drawings indicated that the stair parts may be matched to stairs running in specific directions. This knowledge made the work go more smoothly for FPC. However, for one of the buildings, FPC had to unexpectedly construct new concrete forms for stairs running in the opposite direction in order to use the GFP because some of the stair railings would only fit stairs running in the reverse direction. FPC did not bring the stair direction problem to the attention of the Government until the claim was filed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sanchez v. DVA
Federal Circuit, 2020
P & K Contracting, Inc. v. United States
108 Fed. Cl. 380 (Federal Claims, 2012)
Caddell Construction Co. v. United States
78 Fed. Cl. 406 (Federal Claims, 2007)
AAB Joint Venture v. United States
75 Fed. Cl. 414 (Federal Claims, 2007)
Southern Comfort Builders, Inc. v. United States
67 Fed. Cl. 124 (Federal Claims, 2005)
R.P. Wallace, Inc. v. United States
63 Fed. Cl. 402 (Federal Claims, 2004)
AFD Fund v. United States
61 Fed. Cl. 540 (Federal Claims, 2004)
L.W. Matteson, Inc. v. United States
61 Fed. Cl. 296 (Federal Claims, 2004)
Turner Construction Co. v. United States
54 Fed. Cl. 388 (Federal Claims, 2002)
W.G. Yates & Sons Construction Co. v. United States
53 Fed. Cl. 83 (Federal Claims, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
279 F.3d 989, Counsel Stack Legal Research, https://law.counselstack.com/opinion/franklin-pavkov-construction-co-v-james-g-roche-secretary-of-the-air-cafc-2002.