Turner Construction Co. v. United States

54 Fed. Cl. 388, 2002 U.S. Claims LEXIS 303, 2002 WL 31526501
CourtUnited States Court of Federal Claims
DecidedNovember 13, 2002
DocketNo. 01-149 C
StatusPublished
Cited by3 cases

This text of 54 Fed. Cl. 388 (Turner Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Turner Construction Co. v. United States, 54 Fed. Cl. 388, 2002 U.S. Claims LEXIS 303, 2002 WL 31526501 (uscfc 2002).

Opinion

OPINION

DAMICH, Chief Judge.

I. Introduction

This case involves a claim of breach of contract, pursuant to the Contract Disputes Act, 41 U.S.C. § 601 et seq., arising out of a contract for the construction of an addition to the VA Medical Center (VAMC) in Boston, Massachusetts. Pending before the Court are Plaintiffs Motion for Partial Summary Judgment and Defendant’s Cross-Motion for Summary Judgment. For the reasons stated below, Plaintiffs Motion is DENIED and Defendant’s Motion is GRANTED.

II. Background

On September 5, 1997, Plaintiff Turner Construction Co., Inc. (Turner), entered into a $24,436,000 contract (“Contract 1179”) with the U.S. Department of Veterans Affairs (VA) for the construction of an ambulatory care addition to the VAMC in Boston. Plaintiffs complaint seeks $321,424 in damages, as a pass-through claim on behalf of its electrical subcontractor Richardson Electric Company (Richardson), for what it contends was an ordered change imposed by the VA Contracting Officer.1

The dispute centers on the extent and type of fire-rated protection required for feeder circuit wiring to, and panelboards in, the operating rooms (ORs) in the medical center addition. The VA maintains that the contract required 2-hour fire-rated protection for the emergency electrical system and that, pursuant to the contract specifications and the National Electrical Code (NEC), the feeders and panelboards in the ORs were part of the emergency system. The VA subsequently directed Turner and Richardson to [390]*390effectuate the required fire protection via mineral-insulated (MI) cable. The legal dispute is two-fold: first, Turner disputes that the contract called for 2-hour fire-rated protection for the OR feeders and panelboards, arguing that the contract drawings evinced a clear intent otherwise. Second, as a paramount issue,2 however, Turner argues that the contract specifications specifically reserved to the contractor the option of utilizing a 2-hour fire-rated conduit-and-wire “enclosure,” instead of the substantially more expensive MI cable, for wiring the elements of the emergency electrical system. In directing the MI cable installation, Plaintiff avers, the VA materially altered the contract and is liable for the additional costs thereof.

Plaintiff is seeking summary judgment on the issue of liability and has reserved the issue of the quantum of damages for further argument.

III. Discussion

This Court possesses jurisdiction over this action pursuant to the Contract Disputes Act and 28 U.S.C. § 1491(a)(1).

Summary judgment is appropriate when there are no genuine issues of material fact and the moving party is entitled to judgment as a matter of law. Rules of the Court of Federal Claims (RCFC) 56(c); Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 247-248, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986). A material fact is one that might affect the outcome of the suit. Id. at 248, 106 S.Ct. 2505. A material fact is genuine if the evidence is such that a reasonable jury or trier of fact could return a verdict in favor of the non-moving party. Id. Initially, the moving party bears the burden of demonstrating the absence of genuine issues of material fact. Celotex Corp. v. Catrett, 477 U.S. 317, 325, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986). The moving party can meet its burden by demonstrating the absence of issues of material fact or showing the absence of evidence to support the non-moving party’s case. Id. If the moving party makes such a showing, the burden shifts to the non-moving party to present such evidence. Id. at 324, 106 S.Ct. 2548. The non-moving party must present a foundation for facts sufficient to support a verdict in its favor, with all reasonable inferences resolved in its favor. Arthur A. Collins, Inc. v. Northern Telecom Ltd., 216 F.3d 1042, 1047-48 (Fed.Cir.2000).

A. Contract 1179 Clearly Required 2-Hour Fire-Rated Protection for the Operating Room Feeders and Panel-boards.

The contract as a whole consisted, inter alia, of the drawings, on which the Plaintiff almost exclusively relies, as well as the specifications.3 The specifications, in turn, incorporated by reference the NEC4 [391]*391(and Massachusetts Electrical Code, for that matter) as well as various Federal Acquisition Regulations (FAR).5 Plaintiff argues, however, that key drawings provided “plain proof of the written intentions of the contract designer” that the OR feeders and panel-boards were not required to be fire protected. Pl.’s Mot. Summ. J. at 8. Contract interpretation, nevertheless, “begins with the plain language of the written agreement,” Hercules, Inc. v. United States, 292 F.3d 1378, 1380 (Fed.Cir.2002), and the drawings are only one part of the contract. “The contract must be construed to effectuate its spirit and purpose giving reasonable meaning to all parts of the contract.” Id. at 1381 (emphasis added). Plaintiff further argues that there was no conflict between the drawings and the specifications, Pl.’s Mot. Summ. J. at 10, or, alternatively, that the specificity of the drawings control over the general terms of the specifications, Pl.’s Mot. Summ. J. at 8-9, or that the contract was ambiguous and should be construed against the VA as the drafter of the contractual documents, Pl.’s Mot. Summ. J. at 16-17. As will be seen below, the contract was not ambiguous and 2-hour fire-rated protection of the OR panelboards and feeders is the only interpretation that gives meaning to all parts of the contract: drawings, specifications, and the NEC. See Gould, Inc. v. United States, 935 F.2d 1271, 1274 (Fed.Cir.1991).

1. Contract 1179 Electrical Drawings

The Court will first address Plaintiffs reliance on the drawings of the contract.6 [392]*392Drawing 1-El,7 titled “Electrical Symbol List,” states, in the legend, “Branch Circuit Wiring Notes,” 111, that “Wiring is shown on drawings only for specific routes or special conditions.” In Drawing 1-El, the “Electrical Panel Key” legend provides that “EP” stands for “Emergency Power,” “CP” stands for “Critical Power,” and “PP” stands for “Power Panel.” In the same drawing’s legend, “Raceways and Wiring,” the hexagon symbol is described as “feeder tag — refer to legend of feeder sizes” (emphasis added). The legend for feeder sizes, in turn, is found on Drawing 1-E37.

On Drawing 1-E17,8

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Turner Construction Co., Inc. v. United States
367 F.3d 1319 (Federal Circuit, 2004)
Indiana Michigan Power Co. v. United States
57 Fed. Cl. 88 (Federal Claims, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
54 Fed. Cl. 388, 2002 U.S. Claims LEXIS 303, 2002 WL 31526501, Counsel Stack Legal Research, https://law.counselstack.com/opinion/turner-construction-co-v-united-states-uscfc-2002.