Blinderman Construction Co., Inc. v. The United States

695 F.2d 552, 30 Cont. Cas. Fed. 70,619, 1982 U.S. App. LEXIS 12555
CourtCourt of Appeals for the Federal Circuit
DecidedDecember 10, 1982
DocketAppeal 53-82
StatusPublished
Cited by100 cases

This text of 695 F.2d 552 (Blinderman Construction Co., Inc. v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Blinderman Construction Co., Inc. v. The United States, 695 F.2d 552, 30 Cont. Cas. Fed. 70,619, 1982 U.S. App. LEXIS 12555 (Fed. Cir. 1982).

Opinion

COWEN, Senior Circuit Judge.

Pursuant to the Contract Disputes Act of 1978, 41 U.S.C. §§ 601, et seq., the appellant (contractor) appeals from a decision of the Armed Services Board of Contract Appeals (Board) which denied, in part, the contractor’s claim in the amount of $45,312, and its request for a time extension of 13 days for the completion of the contract. The case is before us on cross-motions for summary judgment filed in the United States Court of Claims prior to October 1, 1982, and thereafter transferred to this court.

The claim grows out of a contract entered into between the contractor and the Department of the Navy (Navy) for installation of permanent improvements in multifamily housing at the Great Lakes, Illinois Naval Base (Base).

The claim of $45,312, includes three separate items.

The first item was a claim for extra costs in the amount of $803.40, due to a delay resulting from a power outage on July 26, 1978. The Board allowed the contractor an equitable adjustment of $1,476.59 on this claim. The allowance included the direct costs plus additions made by the Board. This claim is not in issue.

The second item was a claim for $617.40 for additional costs allegedly caused by a power outage on August 18, 1978. The contractor appeals from the denial of this claim and we affirm the Board’s decision thereon.

The third and largest item is for damages sought for what the Board refers to as a *554 claim for “access delays,” and a time extension of 13 days. The contractor contends that the additional expense and delay were incurred by reason of the Navy’s failure to discharge its contractual obligation to provide access to apartments occupied by Naval personnel. A summary of the claim of $45,312 shows that it includes an item of $11,579 for “delay costs,” and $33,733 claimed on the ground that the impact of the delays was to extend the completion of the project by 9 working days. 1

The claim for access delays involves an interpretation of the provisions of the contract, and for the reasons to be set forth, we disagree with the Board’s interpretation and reverse its decision on this question of law. However, in view of its holding, the Board did not decide whether or to what extent the Navy’s delay was unreasonable. Also, at oral argument, Government counsel stated that if we disagreed with the Board, the case should be remanded because of concurrent delays attributable to the contractor and its subcontractor. We agree, and therefore we deny both motions for summary judgment, except as stated above, and remand the case to the Board for further proceedings in accordance with this opinion.

I. Factual Background and Prior Proceedings.

By contract dated March 31, 1978, the contractor was required to furnish and install electrical meters, gas meters, hot water meters, hot water heating meters and condensate meters in the apartments housing Naval personnel at the Base. The contract was to have been completed by September 12, 1978, but the completion date was extended by a change order to October 3,1978. The contract was let in conformity with the national policy to conserve energy by metering energy usage in military housing. About 139 buildings and 656 individual apartments were involved in the work to be performed.

The contractor was required to provide a quality control inspection system to insure compliance with the contract plans and specifications. The contract contained the standard clauses for construction contracts including “Changes,” “Suspension of Work,” and “Liquidated Damages”. Since the work was not completed until October 20,1978, the contractor was charged by the Navy with liquidated damages of $2,975 for 17 days of inexcusable delays. On other claims not in issue, the Board found that the contractor was entitled to a time extension of 6 days and remission of liquidated damages in the amount of $1,050; thus the contractor was charged with net liquidated damages of $1,925 for 11 days of inexcusable delays.

Following the adverse decision of the contracting officer, the contractor elected to proceed under the Contract Disputes Act of 1978 and appealed the decision to the Board. The Board denied the claim before us in an initial opinion of November 14, 1980, and then, in an opinion on motion for reconsideration, on February 25, 1981. The cross-motions for summary judgment on the contractor’s appeal from the Board’s decision were thereafter filed in the United States Court of Claims.

II. The Power Outage Claim.

For itself and its subcontractor, the contractor claims it is entitled to recover $617.60 for the time lost by the workmen employed by them during a power outage on August 18, 1978. The Board found that the lost time was caused by rain, rather than by a power outage. The contractor challenges this finding on the ground that it is not supported by the “greater weight of the evidence.”

The statutory standard of review is the substantiality of the evidence. On the basis of the testimony of the contractor’s superintendent and the subcontractor’s superintendent, the Board found that the workmen left the site because of a very heavy rain which prevented them from doing any outside work.

*555 The Board’s decision on this portion of the claim is supported not only by substantial evidence but by a clear preponderance of the evidence. The contractor’s contentions are without merit.

III. The Claim for Delays in Obtaining Access to the Apartments.

This claim presents the only difficult issue in this appeal, because its resolution involves an interpretation of the following provisions of the contract:

SCHEDULING OF WORK: Work shall be scheduled to issue [sic] minimum description [sic] of service to the housing units. The contractor shall notify the occupants of the housing unit * at least 3 days prior to commencing any work in a housing unit. The contractor shall perform his work between the hours of 8:00 A.M. and 5:00 P.M. and having once started work in a housing unit shall work to completion in consecutive work days. * * *
In no case shall a unit be left overnight without a completed meter installation, including testing and resumption of gas service.

PROGRESS CHARTS: The Contractor shall, within 15 days after receipt of notice of award, prepare and submit to the Contracting Officer for approval, a practicable construction schedule in accordance with Clause entitled ‘Progress Charts and Requirements for Overtime Work’ of the General Provisions except as modified herein. Progress chart shall clearly indicate when the contractor will require access to individual buildings and shall further indicate the anticipated durations of all utility outages.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Philips Lighting North American Corporation
Armed Services Board of Contract Appeals, 2024
David Boland, Inc.
Armed Services Board of Contract Appeals, 2024
L.S. Black-Loeffel Civil Constructors JV
Armed Services Board of Contract Appeals, 2023
IMC Construction Group
Armed Services Board of Contract Appeals, 2023
Jemison & Partners, Inc.
Armed Services Board of Contract Appeals, 2022
GSC Construction, Inc.
Armed Services Board of Contract Appeals, 2020
Watts Constructors, LLC
Armed Services Board of Contract Appeals, 2020
Kellogg Brown & Root Services, Inc.
Armed Services Board of Contract Appeals, 2018
Aegis Defense Services, LLC, f/k/a Aegis Defence Services Ltd.
Armed Services Board of Contract Appeals, 2017
Mw Builders, Inc. v. United States
134 Fed. Cl. 469 (Federal Claims, 2017)
K-Con Building Systems, Inc. v. United States
131 Fed. Cl. 275 (Federal Claims, 2017)
Relyant, LLC
Armed Services Board of Contract Appeals, 2016
Hernandez, Kroone and Associates, Inc. v. United States
110 Fed. Cl. 496 (Federal Claims, 2013)
Cleveland Construction, Inc. v. Ellis-Don Construction, Inc.
709 S.E.2d 512 (Court of Appeals of North Carolina, 2011)
Mactec, Inc. v. Bechtel Jacobs Company, LLC
346 F. App'x 59 (Sixth Circuit, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
695 F.2d 552, 30 Cont. Cas. Fed. 70,619, 1982 U.S. App. LEXIS 12555, Counsel Stack Legal Research, https://law.counselstack.com/opinion/blinderman-construction-co-inc-v-the-united-states-cafc-1982.