Baldi Bros, Inc. v. United States

CourtUnited States Court of Federal Claims
DecidedMay 12, 2023
Docket16-536
StatusPublished

This text of Baldi Bros, Inc. v. United States (Baldi Bros, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Baldi Bros, Inc. v. United States, (uscfc 2023).

Opinion

In the United States Court of Federal Claims No. 16-536 (Filed: May 12, 2023)

************************************** BALDI BROS, INC., * * Plaintiff, * Motion for Summary Judgment; * Constructive Suspension of Work; v. * Constructive Change; Contract * Interpretation. THE UNITED STATES, * * Defendant. * **************************************

William J. Braun, Braun & Melucci, LLP, La Jolla, CA, counsel for Plaintiff.

Vijaya Surampudi, U.S. Department of Justice, Civil Division, Washington, DC, counsel for Defendant.

OPINION AND ORDER

DIETZ, Judge.

Construction contractor Baldi Bros, Inc. (“Baldi”) seeks compensation, pursuant to the Contract Disputes Act (“CDA”), for an alleged constructive suspension of work and constructive changes to its contract (“the Contract”) with the United States Department of Navy (“Navy”) for the removal and replacement of an aircraft ramp at Travis Air Force Base (“Travis AFB”). This dispute revolves around the contract requirements for handling and disposing of excess soil excavated at the project site. The Court previously ruled that the Contract did not require the Navy to provide a Clean Soil Holding Area (“CSHA”) for Baldi’s use on Travis AFB and that Baldi was required to haul excess soil off base. See Baldi v. United States, 156 Fed. Cl. 372, 383 (2021). That ruling disposed of Baldi’s first cause of action. The government now argues that it is entitled to summary judgment on the constructive suspension of work and constructive change claims under Baldi’s second cause of action.

For the reasons explained herein, the Court finds that there are no genuine issues of material fact with respect to Baldi’s constructive suspension of work claim and, therefore, the government is entitled to judgment as a matter of law. However, the Court finds that there are genuine issues of material fact with respect to Baldi’s claims that the Navy constructively changed the contract. Accordingly, the government’s motion for partial summary judgment is GRANTED-IN-PART and DENIED-IN-PART. I. BACKGROUND

This case stems from the Contract between Baldi and the Navy for the removal and replacement of an aircraft ramp at Travis AFB. Am. Compl. [ECF 18] ¶ 4; Def.’s App.1 at 2-93.2 The parties entered into the Contract, which had a value of $2,415,958, on December 17, 2012. [ECF 18] ¶ 4. The ramp replacement project called for “demolition of existing runway concrete, excavation of underlying soils, installation of new ramp pavement, storm drainage, under-drain system and incidental work[.]” Id. ¶ 5. The project required Baldi to excavate approximately 11,300 cubic yards of existing soil. Id. ¶ 6. Baldi completed the project on May 28, 2015—178 days after the completion deadline. Id. ¶ 22. As a result of the delayed completion, the Navy assessed liquidated damages against Baldi. Id. Baldi proceeded to file two claims with the Navy under the CDA, alleging constructive change and constructive suspension of work. Id. ¶¶ 26, 32.

In its first claim, which was filed with the Navy on November 13, 2015, Baldi sought $253,424.31. [ECF 18] ¶ 26. Baldi explained that it understood the Contract to require the government to provide Baldi with an on-base CSHA. Id. ¶ 24. When the government failed to provide one, Baldi sought compensation under Federal Acquisition Regulation (“FAR”) 52.243- 2, Changes, for its “increased direct costs of disposing of the contaminated soils off-base.” Id. ¶ 26. The Navy Contracting Officer denied the claim on February 24, 2016. Id. Baldi filed its original complaint in this Court on May 2, 2016. Compl. [ECF 1]. Baldi’s November 13, 2015, CDA claim was the basis of its first cause of action. Id. ¶¶ 5-25.

On January 30, 2017, Baldi filed its second claim with the Navy, seeking $563,424.00 for the “recission of the liquidated damages, a 178 day contract time extension, extended field overhead and general conditions, and under-absorbed home office overhead compensation under FAR 52.243-4, Changes.” [ECF 18] ¶ 32 (alteration in original). Baldi’s second claim was based on the following allegations: the Navy’s refusal to provide a CSHA (“Allegation 1”), the Navy’s constructive suspension of the work based upon its response to Baldi’s Request for Information (“RFI”) (“Allegation 2”), the Navy’s constructive suspension of the work based upon its responses to Baldi’s earthwork submittals (“Allegation 3”), the Navy’s requirement that Baldi use a Soil Tracking Form and comply with the Travis AFB Soil Management Procedures Manual (“Allegation 4”), the Navy’s requirement that additional soil testing be performed prior to hauling contaminated soils on base roads (“Allegation 5”), and the Navy’s delay in issuing a signed manifest to allow for hauling of petroleum-contaminated soils on base (“Allegation 6”). Id. ¶ 31. Once more, the Navy Contracting Officer rejected Baldi’s CDA claim. Id. ¶ 32. Thereafter, Baldi amended its complaint to add its January 30, 2017 CDA claim as the basis of its second cause of action. Id. ¶¶ 30-35.

On January 4, 2018, the government moved for summary judgment, arguing that the Contract does not require the government to provide Baldi with a CSHA and that this issue, if resolved in the government’s favor, is dispositive of both causes of action alleged by Baldi. Def.’s Mot. for Summ. J. [ECF 26] at 1. On October 25, 2021, the Court granted the

1 The Court cites to the Appendix filed by the government in support of its motion for summary judgment at [ECFs 78-1, 78-2, 78-3,78-4 78-5, 78-6, 78-7, 78-8, and 78-9] as “Def.’s App. at __.” 2 All page numbers in the parties’ filings refer to the page numbers generated by the CM/ECF system.

2 government’s motion for partial summary judgment. Baldi, 156 Fed. Cl. at 375. The Court found that “the plain language of the Contract does not obligate the government to provide Baldi with a CSHA” and that “[t]he Contract is clear that there was no CSHA at Travis AFB at the time of contract formation and that the contractor was required to dispose of excess soil.” Id. at 380. However, the Court disagreed that resolution of the CSHA issue—whether the Navy was obligated to provide Baldi with a CSHA—disposed of both causes of actions. The Court explained that the allegations underlying Baldi’s second cause of action are arguably independent of the finding that the Navy had no obligation under the Contract to provide a CSHA and that further proceedings may be required to reach full resolution. Id. at 383-84. Accordingly, the Court ordered the parties to confer on further proceedings regarding Baldi’s second cause of action. Id. at 385.

Following the Court’s opinion, the parties filed a joint status report. [ECF 69]. Therein, the parties stated that they could not agree on further proceedings in this case. Id. After a status conference, the Court ordered the parties to meet and confer on which causes of action remained after the Court’s opinion. Dec. 16, 2021, Order [ECF 71]. The parties filed another joint status report on January 7, 2022, stating that they agree that the Court’s opinion “dispense[d] of [Allegation 1] contained in Baldi’s second [cause] of action . . . but [that they] continue to disagree with the extent to which the Court’s ruling affect[ed] the remaining allegations contained in the second cause of action and accordingly what discovery is relevant to the remaining allegations.” [ECF 72] at 1. After considering the parties’ positions, the Court ordered the government to file a motion for summary judgment addressing Allegations 2 through 6 of Baldi’s second cause of action. [ECF 73, 75]. The government filed its motion for partial summary judgment on March 31, 2022, with respect to Allegations 2 through 5.3 [ECF 78]. Baldi filed its opposition on May 1, 2022, [ECF 79], and the government filed its reply on June 17, 2022. [ECF 84].

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Zenon Environmental, Inc. v. United States Filter Corp.
506 F.3d 1370 (Federal Circuit, 2007)
International Data Products Corp. v. United States
492 F.3d 1317 (Federal Circuit, 2007)
Blinderman Construction Co., Inc. v. The United States
695 F.2d 552 (Federal Circuit, 1982)
Ford Motor Company v. United States
157 F.3d 849 (Federal Circuit, 1998)
P.R. Burke Corp. v. United States
277 F.3d 1346 (Federal Circuit, 2002)
The Hunt Construction Group, Inc. v. United States
281 F.3d 1369 (Federal Circuit, 2002)
bell/heery v. United States
739 F.3d 1324 (Federal Circuit, 2014)
Kiewit Infrastructure West Co. v. United States
972 F.3d 1322 (Federal Circuit, 2020)
Csi Aviation, Inc. v. Dhs
31 F.4th 1349 (Federal Circuit, 2022)
Arrañaga v. United States
103 Fed. Cl. 465 (Federal Claims, 2012)
Beauchamp Construction Co. v. United States
34 Cont. Cas. Fed. 75,453 (Court of Claims, 1988)
CCM Corp. v. United States
36 Cont. Cas. Fed. 75,876 (Court of Claims, 1990)
Fruehauf Corp. v. United States
587 F.2d 486 (Court of Claims, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
Baldi Bros, Inc. v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/baldi-bros-inc-v-united-states-uscfc-2023.