K-Con Building Systems, Inc. v. United States

131 Fed. Cl. 275, 2017 U.S. Claims LEXIS 333, 2017 WL 1382973
CourtUnited States Court of Federal Claims
DecidedApril 18, 2017
Docket05-914C
StatusPublished
Cited by8 cases

This text of 131 Fed. Cl. 275 (K-Con Building Systems, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
K-Con Building Systems, Inc. v. United States, 131 Fed. Cl. 275, 2017 U.S. Claims LEXIS 333, 2017 WL 1382973 (uscfc 2017).

Opinion

Trial; Contract to Design and Build Prefabricated Metal Building; RCFC 15; Futility of Supplemental Complaint; Contract Disputes Act of 1978; Remission of Liquidated Damages; Counterclaim for Liquidated ■ Damages; Contractual Notice Requirement; Abandoned Claim; Excusable Delay; Critical Path; Affirmative Defenses

OPINION AND ORDER

SWEENEY, Judge

Plaintiff K-Con Building Systems, Inc. contracted with the United States Coast Guard (“Coast Guard”) to design and construct a prefabricated metal building in Elizabeth City, North Carolina. Because plaintiff did not complete construction by the contract completion date, the Coast Guard assessed liquidated damages and, eventually, terminated the contract for default. Plaintiff filed suit challenging the default termination and the liquidated damages assessment, and defendant filed a counterclaim to recover the liquidated damages still owed by plaintiff. After the court held a trial, the parties attempted — unsuccessfully—to reach a settlement. Plaintiff then filed a motion seeking to resolve certain issues raised during the settlement discussions. The court ruled on that motion, dismissing plaintiffs challenge to the default termination for lack of jurisdiction. The parties thereafter submitted posttrial briefs, and plaintiff filed a motion for leave to amend its complaint. As set forth below, the court denies plaintiffs motion for leave to amend its complaint, and concludes that defendant is entitled to recover liquidated damages in the amount of $199,611.

I. FACTS

This section contains the court’s findings of fact as required by Rule 52(a)(1) of the Rules of the United States Court of Federal Claims (“RCFC”). 1

*279 A. The Contracts

1. The Federal Supply Schedule Contract

Plaintiff is a “design-build general contractor” headquartered in Charleston, South Carolina whose business is focused on the federal government. Tr, 86 (Reitmeier); accord Tr. 1268-69 (Combs). Specifically, plaintiff has fulfilled over 4000 delivery orders for the federal government throughout the United States and its territories. Id. at 1268,1271 (Combs); see also id. at 3643 (Kieman) (indicating that plaintiff has “had over 3000 delivery orders from the federal government and over 400 of those have been specifically for pre-engineered metal buildings”).

In April 2001, the United States General Services Administration (“GSA”) awarded plaintiff a Federal Supply Schedule contract for Prefabricated Structures and Outdoor Smoking Shelters. Jt. Stip. ¶ 1; JX 2. That contract contained a number of clauses from the Federal Acquisition Regulation (“FAR”), including FAR 52.212-4, Contract Terms and Conditions — Commercial Items (May 1999). 2 JX 2.9; Pl.’s App. SJ0001-90. Several paragraphs from that clause are relevant here. First, paragraph (d) provided:

Disputes. This contract is subject to the Contract Disputes Act of 1978, as amended .... Failure of the parties to this contract to reach agreement on any request for equitable adjustment, claim, appeal or action arising under or relating to this contract shall be a dispute to be resolved in accordance with the clause of FAR 52.233-1, Disputes, which is incorporated herein by reference.

JX 2.9. Second, paragraph (f) provided:

Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence such as, acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. The Contractor shall notify the Contracting Officer in writing as soon as it is reasonably possible after the commencement of any excusable delay, setting forth the full particulars in connection therewith, shall remedy such occurrence with all reasonable dispatch, and shall promptly give written notice to the Contracting Officer of the cessation of such occurrence.

Id. Third, paragraph (m) provided:

Termination for cause. The Government may terminate this contract, or any part hereof, for cause in the event of any default by the Contractor, or if the Contractor fails to comply with any contract terms and conditions, or fails to provide the Government, upon request, with adequate assurances of future performance. In the event of termination for cause, the Government shall not be liable to the Contractor for any amount for supplies or services not accepted, and the Contractor shall be liable to the Government for any and all rights and remedies provided by law. If it is determined that the Government improperly terminated this contract for default, such termination shall be deemed a termination for convenience.

Pl.’s App. SJ0014. Finally, paragraph (t) incorporated by reference Federal Supply Schedule contract clause I-FSS-249-B; Default (May 2000), id., which provided: 3

*280 In addition to any other clause contained herein related to termination, the following is applicable to orders placed under Federal Supply Schedule contracts.
Any ordering office may, with respect to any one or more orders placed by it under the contract, exercise the same right of termination, acceptance of inferior articles or services, and assessment of excess costs as might the Contracting Officer, except that when failure to deliver articles or services is alleged by the Contractor to be excusable, the determination of whether the failure is excusable shall be made only by the Contracting Officer of the General Services Administration, to whom such allegation shall be referred by the ordering office and from whose determination appeal may be taken as provided in the clause of this contract entitled “Disputes.”

2. The Coast Guard’s Solicitation

On September 2, 2003, the Coast Guard, through its Facilities, Design, and Construction Center (Atlantic) (“FDCC LANT”), 4 solicited proposals under the Federal Supply Schedule for Prefabricated Structures and Outdoor Smoking Shelters for the design and construction of a prefabricated metal building to house an Aviation Repair and Supply Center (“AR&SC”) component repair shop at the Coast Guard Support Center in Elizabeth City, North Carolina. Jt. Stip. ¶¶ 3-4,10; JX 1.1; JX 2.1; JX 20.3; see also Tr. 2454 (Schmitt) (explaining that the AR&SC is a command that maintains and repairs aircraft). Specifically, the Coast Guard sought a 4700-square-foot building to house a hydraulic test lab, a workshop, office space, and storage space. Jt. Stip. ¶¶ 4-5. The contractor was to design the building based on the drawings and specifications included in the request for proposals (“RFP”).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
131 Fed. Cl. 275, 2017 U.S. Claims LEXIS 333, 2017 WL 1382973, Counsel Stack Legal Research, https://law.counselstack.com/opinion/k-con-building-systems-inc-v-united-states-uscfc-2017.