Santa Fe Engineers, Inc. v. The United States

818 F.2d 856, 34 Cont. Cas. Fed. 75,285, 1987 U.S. App. LEXIS 277
CourtCourt of Appeals for the Federal Circuit
DecidedMay 13, 1987
DocketAppeal 87-1013
StatusPublished
Cited by49 cases

This text of 818 F.2d 856 (Santa Fe Engineers, Inc. v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Santa Fe Engineers, Inc. v. The United States, 818 F.2d 856, 34 Cont. Cas. Fed. 75,285, 1987 U.S. App. LEXIS 277 (Fed. Cir. 1987).

Opinion

DAVIS, Circuit Judge.

The questions are whether (a) appellant contractor proved (before the Armed Services Board of Contract Appeals (Board)) the amount of additional costs chargeable to three specific changes made by the Government and (b) appellant had improperly presented to the Board claims broader than the three particular claims that had been certified to the contracting officer. On each issue the Board held against the contractor. We affirm.

I.

In June 1976 Santa Fe Engineers, Inc. (Santa Fe) entered into a contract with the Government for an addition and alterations to Ireland Army Hospital, Fort Knox, Kentucky, for a lump sum price of $28,664,649. The work to be done under the contract included additions to and renovation of the existing hospital buildings, as well as additions to the parking facilities and other work at the site. The contract required completion of the work within four years from the date (July 26, 1976) Santa Fe acknowledged receipt of the Government’s notice to proceed. The work was to be done in phases and was completed in July 1981.

This case started with three changes issued by the Government, designated “AD,” “CD” and “HK.” Santa Fe ultimately certified to the contracting officer a claim for these three changes of over ten million dollars for increased impact costs due to the changes (later reduced to about five million dollars). The contracting officer allowed only slightly over $166,000 on the three claims.

Santa Fe appealed to the Board asserting that the labor impact of the three changes was far more extensive (amounting to almost five million dollars) than the contracting officer had allowed. The Board held a hearing, made extensive findings, and then determined that (1) appellant had made only a “total labor cost presentation” to the Board, acknowledging that it could not identify any particular impact associated with the three particular changes, (2) the Board thus had no basis for awarding any additional sum on any of the three specific changes before it, and (3) the Board had no jurisdiction over Santa Fe’s additional general claim for its total increase in costs because that general claim had never been presented or certified to the contracting officer. Santa Fe Engineers, Inc., ASBCA Nos. 28058 and 29362, 86-3 BCA (CCH) 1119,092 at 96,496. Petitioner’s major contention before us is that it did not urge, before the Board, any different claim than the one it had certified to the contracting officer.

II.

The record clearly sustains the Board’s determination that Santa Fe made no effort to prove the additional impact costs due to the three particular change orders appealed to the Board, but instead sought to show its total labor costs. Finding 39 finds: “Evidence was submitted by appellant to the Board as to the labor costs incurred for the entire work, and as to the amounts to be deducted from such expenditures on account of ‘bid estimate labor,’ payments made for ‘change order labor’ and ‘extended overhead labor,’ and other credits” (emphasis added). 86-3 BCA at 96,507. Above all, Santa Fe’s proposed findings of fact (before the Board) stated (under the heading “NATURE OF THE CLAIM — TOTAL JOB DISRUPTION”):

The claim of Santa Fe Engineers and its subcontractors is a total cost impact claim for a loss of labor efficiency. This is a claim which represents the total impact to the project from both Change *858 Orders “CD” and “HK” and from the collective nature of all the problems, changes and directives that were issued on the project. (Tr. 1-140) A multiplicity of change orders were issued at Fort Knox to resolve and to correct problems, and the problems are what the claim is based on. (Tr. 11-65) Santa Fe and its subcontractors submitted a total labor cost claim for inefficiencies because there was no way to quantify the impact from any individual change on the project. (Tr. 2-135, 136, 187) (Emphasis added.)

86-3 BCA at 96,507.

Later on in its proposed findings, appellant explicitly said: “It was not possible to identify any particular impact associated with any particular change. That is why Santa Fe Engineers ended up utilizing a total labor cost approach to its impact claim.” Id.

Obviously, there was more than substantial evidence sustaining the Board’s findings as to the deficiencies of Santa Fe’s case before the Board on the extra costs attributable to the three specific change orders.

III.

The next, and more significant, issue is whether Santa Fe’s general presentation was beyond the claims certified to the contracting officer and therefore beyond the Board’s authority to consider. It is now elementary that, for claims (such as those now before us) brought under the Contract Disputes Act of 1978, 1 the claim must be in writing and submitted to the contracting officer for a decision. 41 U.S.C. § 605(a). If for more than $50,000 (like those we are now considering), the claim must also be certified. 41 U.S.C. § 605(c). “Lack of proper certification, where required, deprives the contracting officer, the board of contract appeals, and this court (on review) of jurisdiction to proceed on the claim.” Tecom, Inc. v. United States, 732 F.2d 935, 937 (Fed.Cir.1984). To the same effect are W.M. Schlosser Co. v. United States, 705 F.2d 1336, 1338-39 (Fed.Cir.1983) and United States v. Johnson Controls, Inc., 713 F.2d 1541, 1556-57 (Fed.Cir.1983). On appeal to the Board or in a direct access action in the Claims Court, a contractor may increase the amount of his claim, Te-com, 732 F.2d at 937-38, but may not raise any new claims not presented and certified to the contracting officer. J.F. Shea Co. v. United States, 4 Cl.Ct. 46, 54 (1983) (cited with approval in Tecom, supra). This is because “the certification requirement applies to submission of claims to the contracting officer____” Tecom, 732 F.2d at 937 (emphasis in original).

Here, the Board expressly found that Santa Fe had improperly urged a new claim on appeal to the Board. 2 There is ample record support for this determination. To show this support, we deal first with the claim Santa Fe actually presented to the contracting officer. That written claim (dated March 11, 1981) sought $10,-259,624.72 “for delay and impact costs emanating from Change Order Nos. 37 (“AD”) and 102 (“CD”)____” The contracting officer’s response (dated July 27, 1981) starts out by stating “you claim additional money for delay in impact costs resulting from changes ‘AD’ and ‘CD’ under the above referenced contract,” and then proceeds to set forth his view of the facts concerning those particular changes.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tanana Chiefs Conference v. Azar
District of Columbia, 2022
Blanchard's Contracting, LLC
Armed Services Board of Contract Appeals, 2021
Constellation NewEnergy, Inc.
Armed Services Board of Contract Appeals, 2020
Lee's Ford Dock, Inc. v. Secretary of the Army
865 F.3d 1361 (Federal Circuit, 2017)
Benjamin Medina
Armed Services Board of Contract Appeals, 2017
K-Con Building Systems, Inc. v. United States
131 Fed. Cl. 275 (Federal Claims, 2017)
Monica Walker
Armed Services Board of Contract Appeals, 2016
Al-Juthoor Contracting Co. v. United States
129 Fed. Cl. 599 (Federal Claims, 2016)
E & E Enterprises Global, Inc. v. United States
120 Fed. Cl. 165 (Federal Claims, 2015)
K-Con Building Systems, Inc. v. United States
778 F.3d 1000 (Federal Circuit, 2015)
Affiliated Construction Group, Inc. v. United States
115 Fed. Cl. 607 (Federal Claims, 2014)
Kellogg Brown & Root Services, Inc. v. United States
115 Fed. Cl. 46 (Federal Claims, 2014)
Simulation Technology, LLC v. United States
103 Fed. Cl. 105 (Federal Claims, 2012)
Kenney Orthopedic, LLC v. United States
88 Fed. Cl. 688 (Federal Claims, 2009)
M.A. DeAtley Construction, Inc. v. United States
75 Fed. Cl. 575 (Federal Claims, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
818 F.2d 856, 34 Cont. Cas. Fed. 75,285, 1987 U.S. App. LEXIS 277, Counsel Stack Legal Research, https://law.counselstack.com/opinion/santa-fe-engineers-inc-v-the-united-states-cafc-1987.