Affiliated Construction Group, Inc. v. United States

115 Fed. Cl. 607, 2014 U.S. Claims LEXIS 226, 2014 WL 1493195
CourtUnited States Court of Federal Claims
DecidedApril 16, 2014
Docket1:10-cv-00444
StatusPublished
Cited by19 cases

This text of 115 Fed. Cl. 607 (Affiliated Construction Group, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Affiliated Construction Group, Inc. v. United States, 115 Fed. Cl. 607, 2014 U.S. Claims LEXIS 226, 2014 WL 1493195 (uscfc 2014).

Opinion

MEMORANDUM OPINION AND ORDER

VICTOR J. WOLSKI, Judge

Plaintiff Affiliated Construction Group, Inc. (ACG or Affiliated) alleges that the government breached a construction contract and that it is entitled to an equitable adjustment for increased costs and delays due to changes ordered by defendant. Compl. ¶ 2. The government has moved to dismiss two of Affiliated’s claims under Rule 12(b)(6) of the Rules of the United States Court of Federal Claims (RCFC), arguing that plaintiff has failed to state claims upon which relief can be granted. Affiliated concedes that one claim should be dismissed, but defends the other. As discussed below, in opposing the motion for partial dismissal the plaintiff has advanced a version of a claim that departs from that presented to the contracting officer and would thus be outside our subject-matter jurisdiction under the Contract Disputes Act (CDA), 41 U.S.C. §§ 7101-7109. Since the claim presented would not entitle plaintiff to relief, and its alternative version is not ripe for our review, the Court GRANTS the government’s motion to dismiss two of the claims in the complaint.

I. BACKGROUND 1

Affiliated contracted to perform construction work for the Department of Defense at *610 Ft. Meade, Maryland, under a design-build, fixed-price contract to renovate a 4,800 square-foot, power-distribution room. Compl. ¶¶ 1, 9-11, 13. The renovations included walls and finishes, lighting, air conditioners, piping, new power distribution/UPS (uninterrupted power source) systems and batteries, a new fire alarm system, and upgrades to the existing sprinkler system. Id. ¶ 10. Plaintiff alleged that because of changes in both the design requirements and in the work, ACG had to perform “a substantially different project than was originally contracted,” which caused it to incur additional expenses. Id. ¶ 2. Plaintiff filed with the contracting officer a certified claim for an equitable adjustment, and, after the government denied the request, then filed a lawsuit under the CDA in our court. Id. ¶¶ 5, 7. Plaintiff requests judgment against the government in the amount of $644,629 and a 136-day extension of the contract duration. Id. ¶ 3.

The government initially filed a motion for partial dismissal of Affiliated’s complaint for failure to state claims upon which relief can be granted. The claim that remains at issue concerns the cost of additional fire-mitigation items. 2 See Def.’s Mot. for Partial Dismissal (Def.’s Mot) at 1, 4. Plaintiff seeks reimbursement for costs of $50,199 and a seven-day extension of contract time for having to install increased quantities of smoke dampers, access doors, registers, grills, and diffusers beyond what it had estimated when pricing its bid. Compl. ¶¶ 36-38. In its bid, plaintiff had estimated that it would need to install six smoke dampers; twenty-three registers, grills, and diffusers; seventeen access doors; and eleven fire dampers. Id. ¶36. After ACG began the renovations, the required quantities increased to thirty-four smoke dampers; thirty-one registers, grills, and diffusers; and thirty-eight access doors, while the quantity of fire dampers decreased to four. Id. The government contended that this claim should be dismissed for failure to state a claim upon which relief can be granted because ACG entered into a firm-fixed-price contract for design/build services, and thus under 48 C.F.R. § 16.202-1, plaintiff assumed the “maximum risk” and full responsibility for all costs, including unexpected expenses if it underestimated the cost of the project. Def.’s Mot. at 4-8 (quoting 48 C.F.R. § 16.202-1).

Regarding the fire-mitigation equipment, the complaint alleges:

These quantities represent a substantial increase in costs. ACG could not have anticipated the final quantities of the equipment and materials required for this project without the drawings during the bidding phase. The final quantities were based on code requirements and as such were not the design team’s requirements. The quantities that were included in the original pricing allowed for a reasonable number of each item for this type of room. It was impossible to determine the amount of existing duets and equipment that traversed and transversed this space prior to a complete and thorough site survey. The additional quantities represent a large difference in costs to the Project.

Compl. ¶ 3 7.

In its motion to dismiss, the government argued that plaintiffs contention amounted to a claim that plaintiff had underestimated the costs of performance, and in a firm-fixed-price contract the risk of such error was borne by the contractor. Def.’s Mot. at 4-8. In its initial response, and at oral argument, plaintiffs position was that the increase in the quantity of fire-mitigation devices was caused by the changes the government ordered in the UPS system from the 35 percent submission to the 75 percent submission, and thus the government was responsible for the increase in the costs. PL’s Br. in Opp’n to Mot. (PL’s Br.) at 4-9; Tr. 13-17.

During the hearing, the Court instructed plaintiff to file a supplemental brief addressing how the code requirements linked *611 the UPS changes to the additional fire-mitigation equipment, and whether the contracting officer had the opportunity to consider that claim. Tr. at 24-26, 37; Order, ECF No. 13. In its supplemental brief, ACG stated that “[contrary to what was previously argued in open court, it was not the UPS change that affected the increased fire smoke damper quantities.” Pl.’s Supp’l Br. at 1. Plaintiff now argued that the reason for the increased quantities was that the existing duet work did not meet the code requirements, and therefore, ACG had had to upgrade the room to make it code-compliant. Id. at 1-2. Plaintiff further contended that because neither the use nor the square footage of the area changed during renovation, it was reasonable for it to assume that the existing duets would already be code-compliant. Id. at 2, 5, 7. Affiliated argued that it “could not have anticipated” the lack of compliance, and the unexpected need to upgrade constituted a change for which ACG can claim an equitable adjustment. Id. at 7. Regarding the question of jurisdiction, plaintiff argued that because the claim presented to the contracting officer stated that the increased quantities were due to code requirements rather than design changes, the contracting officer had been given an opportunity to consider the basis of plaintiffs claim. Id. at 2, 4, 6. In response, the government argues that the ground articulated in ACG’s supplemental paper constitutes a new claim within the meaning of the CDA, and would thus be beyond our jurisdiction. 3 Resp. to Pl.’s Supp’l Br. (Def.’s Supp’l Br.) at 8-12.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tanana Chiefs Conference v. Azar
District of Columbia, 2022
Kansas City Power & Light Co. v. United States
124 Fed. Cl. 620 (Federal Claims, 2016)
Itility, LLC v. United States
124 Fed. Cl. 452 (Federal Claims, 2016)
Ogunniyi v. United States
124 Fed. Cl. 525 (Federal Claims, 2015)
Dms Imaging, Inc. v. United States
123 Fed. Cl. 645 (Federal Claims, 2015)
Woodruff v. United States
122 Fed. Cl. 761 (Federal Claims, 2015)
Nielsen Co. v. Success Systems, Inc.
112 F. Supp. 3d 83 (S.D. New York, 2015)
United States Enrichment Corporation v. United States
121 Fed. Cl. 532 (Federal Claims, 2015)
E & E Enterprises Global, Inc. v. United States
120 Fed. Cl. 165 (Federal Claims, 2015)
Quimba Software, Inc. v. United States
120 Fed. Cl. 107 (Federal Claims, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
115 Fed. Cl. 607, 2014 U.S. Claims LEXIS 226, 2014 WL 1493195, Counsel Stack Legal Research, https://law.counselstack.com/opinion/affiliated-construction-group-inc-v-united-states-uscfc-2014.