Northrop Grumman Systems Corporation v. United States

CourtUnited States Court of Federal Claims
DecidedOctober 31, 2018
Docket12-286
StatusPublished

This text of Northrop Grumman Systems Corporation v. United States (Northrop Grumman Systems Corporation v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Northrop Grumman Systems Corporation v. United States, (uscfc 2018).

Opinion

In the United States Court of Federal Claims No. 12-286C (Filed: October 17, 2018) (Re-Filed: October 31, 2018)1

**********************

NORTHROP GRUMMAN SYSTEMS Contracts; Contract CORPORATION, Disputes Act, 41 U.S.C. §§ 7101-7109 (2012); Plaintiff, motions to dismiss; variance between claim v. and complaint; motions for summary judgment; THE UNITED STATES, contract interpretation.

Defendant.

John W. Chierichella, Washington, DC, with whom were Anne B. Perry, David S. Gallacher, and Christopher M. Loveland, for plaintiff. Maureen Del Duca and Linda T. Maramba, of counsel.

Cameron Cohick, Senior Trial Counsel, United States Department of Justice, Civil Division, Commercial Litigation Branch, Washington, DC, with whom were Barbara E. Thomas, Jeffrey D. Klingman, Rebecca S. Kruser, Trial Attorneys, for defendant. Michael F. Kiely, United States Postal Service, Law Department, of counsel.

OPINION

BRUGGINK, Judge.

United States Postal Service (“the Postal Service”) entered into a contract with Northrop Grumman Systems Corporation (“Northrop”) pursuant to which Northrop would produce and deliver a number of a mail-

1 This opinion was originally issued under seal. The parties agree that no redactions are necessary and thus this opinion is reissued without redactions. processing machines known as the Flats Sequencing System machine (“FSS machine”) for a fixed price of approximately $874 million. The contract was eventually performed, but Northrop has filed suit pursuant to Contract Disputes Act, 41 U.S.C. §§ 7101-7109 (2012) (“CDA”), claiming that the Postal Service breached the contract in a number of ways. The Postal Service has counter-claimed, asserting that Northrop breached its own contractual obligations.

Pending are the parties’ motions to dismiss and motions for partial summary judgment. Northrop’s motion to dismiss seeks dismissal of the Postal Service’s counterclaim counts one and four for lack of subject matter jurisdiction. Plaintiff also moves for summary judgment on the majority of the counts in the Postal Service’s counterclaim.

The Postal Service moves to dismiss Northrop’s count one for lack of subject matter jurisdiction. Defendant also moves for partial summary judgment on Northrop’s count five, summary judgment on count seven, and partial summary judgment on elements of the claims imbedded in counts three through five. The court allowed the parties to submit briefing far in excess of the rule limits. Northrop’s motion was fully briefed on June 29, 2018, and defendant’s motion was fully briefed on July 20, 2018. We held oral argument on both parties’ motions on September 12 and 14, 2018.

BACKGROUND

The Postal Service took its first steps toward ending manual flat mail (bulk mail) sorting on July 10, 2003, when it issued a solicitation seeking proposals to provide research and development for a flat mail sequencing system machine. On October 28, 2003, Northrop and the Postal Service entered into a pre-production contract for Northrop to design a prototype of a machine to sort flat mail. While the pre-production contract was ongoing, the Postal Service issued on May 8, 2006, a non-competitive solicitation to Northrop for the production of 100 FSS machines. On February 23, 2007, well before the research and development contract had been fully performed, Northrop entered into a production contract with the Postal Service to design, deliver, and install the FSS machines.

Shortly after entering the production contract and continuing through the end of both contracts, the parties experienced delays and disagreements regarding the design and installation of the FSS machines. The Postal Service’s need for flat mail sorting evolved as well. Nevertheless, despite the difficulties, Northrop installed the last of the FSS machines by August 2011.

2 From 2007 through 2009, the parties were consistently negotiating the scope of the work required by the contract, which resulted in the generation of the Puts and Takes List2 by Northrop and a series of equitable adjustments memorialized in modifications to the production contract.

On March 31, 2009, Northrop submitted a request for equitable adjustment, referred to by the parties as the Program REA, claiming approximately $63 million for a large number of alleged constructive changes and delay and disruption claims. On April 28, 2010, the contracting officer denied the vast majority of Northrop’s request, but on a number of specific claims he directed Northrop to submit a cost proposal so that the parties could negotiate the equitable adjustment.

Northrop submitted its first certified claim to the Postal Service in July 2010, asserting claims largely related to the Program REA. In May 2011, the contracting officer issued a decision denying the majority of Northrop’s claim.

Northrop submitted its second certified claim on August 4, 2011, asserting entitlement to approximately $71 million in damages dating from June 2009 forward. On October 28, 2011, Northrop submitted its third certified claim for approximately $63 million in invoices that it alleged the Postal Service had improperly failed to pay. The contracting officer issued his final decision on April 12, 2012, largely denying the second certified claim, and asserting the Postal Service’s claims against Northrop totaling approximately $410 million. Against this he offset the value of the unpaid Northrop invoices plus the amount to which Northrop was entitled based upon one portion of the second certified claim against the counterclaim damages netting a total amount owed the Postal Service of $341 million.

Northrop filed suit in this court on May 4, 2012. The Postal Service filed a counterclaim, which was amended in 2018.

DISCUSSION

Although both parties have filed motions to dismiss and for partial summary judgment, neither party cross-moved for summary judgment on any of the counts put at issue by their opponent, arguing, in substance, that

2 Northrop created the Puts and Takes List to identify work that it believed was beyond the scope of the contract and submitted this list along with other report deliverables. The Postal Service was aware of the list and the contracting officers appear to have reviewed some version of the list.

3 disputed issues prevent granting the motions for summary judgment. We begin our discussion with the parties’ motions to dismiss.

I. Motions to Dismiss

Both parties argue that certain of their opponent’s claims are outside this court’s subject matter jurisdiction. The party bringing an affirmative claim bears the burden of establishing the court’s jurisdiction over it. McNutt v. Gen. Motors Acceptance Corp. of Ind., 298 U.S. 178, 189 (1936). On a motion to dismiss for lack of subject matter jurisdiction, the court generally “considers the facts alleged in the complaint to be true and correct,” but when a party challenges the jurisdictional facts, the court may consider relevant evidence to resolve whether it has jurisdiction. Reynolds v. Army & Air Force Exch. Serv., 846 F.2d 746, 747 (Fed. Cir. 1988). If the non-moving party does not establish jurisdiction, the court must dismiss the claim. Rules of the United States Court of Federal Claims 12(h)(3) (“RCFC”).

Because Northrop has not established jurisdiction over its count one, we grant the Postal Service’s motion to dismiss that count.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Precision Pine & Timber, Inc. v. United States
596 F.3d 817 (Federal Circuit, 2010)
United States v. Beebe
180 U.S. 343 (Supreme Court, 1901)
McNutt v. General Motors Acceptance Corp.
298 U.S. 178 (Supreme Court, 1936)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
M. Maropakis Carpentry, Inc. v. United States
609 F.3d 1323 (Federal Circuit, 2010)
Ace Constructors, Inc. v. United States
499 F.3d 1357 (Federal Circuit, 2007)
Leonardo v. United States
163 Fed. Appx. 880 (Federal Circuit, 2006)
Flexfab, L.L.C. v. United States
424 F.3d 1254 (Federal Circuit, 2005)
Centex Corp. v. United States
395 F.3d 1283 (Federal Circuit, 2005)
CIGNA Corp. v. Amara
131 S. Ct. 1866 (Supreme Court, 2011)
H. Landau & Company v. The United States
886 F.2d 322 (Federal Circuit, 1989)
Placeway Construction Corporation v. The United States
920 F.2d 903 (Federal Circuit, 1990)
Holmes v. United States
657 F.3d 1303 (Federal Circuit, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
Northrop Grumman Systems Corporation v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/northrop-grumman-systems-corporation-v-united-states-uscfc-2018.