Ets-Hokin Corporation and Bank of America National Trust and Savings Association, Third-Party v. The United States

420 F.2d 716, 190 Ct. Cl. 668, 1970 U.S. Ct. Cl. LEXIS 108
CourtCourt of Appeals for the Third Circuit
DecidedJanuary 23, 1970
Docket103-67
StatusPublished
Cited by26 cases

This text of 420 F.2d 716 (Ets-Hokin Corporation and Bank of America National Trust and Savings Association, Third-Party v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ets-Hokin Corporation and Bank of America National Trust and Savings Association, Third-Party v. The United States, 420 F.2d 716, 190 Ct. Cl. 668, 1970 U.S. Ct. Cl. LEXIS 108 (3d Cir. 1970).

Opinion

PER CURIAM:

This case was referred to Trial Commissioner Mastín G. White with directions to prepare and file his opinion on the issues raised by plaintiff’s motion and defendant’s cross-motion for summary judgment under the order of reference and Rule 99(c) [since September 1, 1969, Rule 166(c)]. The commissioner has done so in an opinion and report filed on May 16, 1969, wherein such facts as are necessary to the opinion are set forth. Defendant filed exceptions (request for review by the court) to the commissioner’s opinion and report. Plaintiff urged adoption by the court of the commissioner’s opinion and recommended conclusions of law or, in accordance with the alternate grounds for relief, that the contract should be reformed to increase the contract price for furnishing and installing the ionization-type fire-detection systems. The case has been submitted to the court on oral argument of counsel, and briefs, of plaintiff and defendant. Since the court agrees with the commissioner’s opinion, report and recommended conclusion, with minor modifications, it hereby adopts the same, as modified, as the basis for its judgment in this case as hereinafter set forth. Therefore, plaintiff is entitled to recover and judgment is entered to that effect. The plaintiff’s motion for summary judgment is allowed and defendant’s cross-motion for summary judgment is denied. The amount of the recovery, and the respective rights of the plaintiff and the third-party plaintiff in such amount will be determined in subsequent proceedings under Rule 131(e), with the Corps of Engineers Board of Contract Appeals being allowed a period of 90 days, or such further period as the commissioner may determine, within which to make an initial determination concerning the amount of the equitable adjustment to which the plaintiff is entitled (unless such administrative determination is waived by the parties).

Commissioner WHITE’S opinion, with minor modifications by the court, is as follows:

This case involves a Wunderlich Act (41 U.S.C. §§ 321, 322) review of a decision that was rendered by the Corps of Engineers Board of Contract Appeals (“the Board”) on November 7, 1966 (ENG BCA No. 2578) under the “disputes” provision of contract No. DA-41-443-ENG (NASA)-24 (“the contract”).

The plaintiff, Ets-Hokin Corporation, and the defendant have filed cross-motions for summary judgment. Each relies on the administrative record to sustain its position.

It is my opinion that the Board’s decision was erroneous, and that the plaintiff is entitled to recover in the present action. 1

The contract was entered into between the plaintiff, a California corporation, and the defendant (represented by a contracting officer of the Corps of Engineers, Department of the Army) on *719 March 26, 1963. 2 It provided for the construction by the plaintiff of the Integrated Mission Control Center, Phase II, at the Manned Spacecraft Center of the National Aeronautics and Space Administration (“NASA”) located in Clear Lake, Harris County, Texas, for a total contract price of $7,879,401.32. The Integrated Mission Control Center is the building from which the astronauts are controlled while in space.

In making and administering the contract, the Corps of Engineers acted as construction agent for NASA.

Included among the work to be accomplished by the plaintiff under the contract was the installation of an automatic fire detection and alarm system in the new building. This phase of the work was governed by section 64 of the contract’s specifications. From the standpoint of the present litigation, the crucial portion of section 64 was paragraph 64-10, which provided in pertinent part as follows:

64-10 FIRE-DETECTING UNITS shall be a type that detect the presence of the products of combustion. The units shall be specifically designed to detect burning of the material that will be installed in the area to be protected. They shall be capable of detecting the airborne products of combustion that are given off during the start of a fire before smoke is formed. Means shall be provided for adjusting the sensitivity of the unit after installation. * * *

The standard “changes” and “disputes” provisions which are customarily found in Government construction contracts were set out in paragraphs 3 and 6, respectively, of the contract’s general provisions.

While the work under the contract was in progress, the plaintiff proposed to install a fire detection system consisting of Spurling 31 fire detecting units, supplemented by Gamewell smoke detectors. The Spurling 31 detector is activated either by a temperature rise of 15 degrees (or more) per minute or when the temperature reaches a predetermined point, usually 135 degrees Fahrenheit. The Gamewell smoke detector, as the name indicates, is activated by the presence of smoke. In this connection, it is relevant to note that the fire detection systems installed in the earlier buildings at the Manned Spacecraft Center consisted of Spurling fire detecting units.

However, representatives of the contracting officer took the position that the fire detection system which the plaintiff proposed to install under the contract would not meet the requirements set out in paragraph 64-10 of section 64 of the contract’s specifications. After extensive correspondence, which began in the spring of 1963 and ultimately involved the contracting officer, the contracting officer rendered his final decision on July 11, 1963. The decision stated in part as follows:

The detector proposed by you was disapproved * * * because of its failure to meet the specifications. The fire detecting units submitted for approval were a smoke detection system and a heat riser, which are not “capable of detecting the airborne products of combustion that are given off during the start of a fire before smoke is formed” as required by the contract specifications. * * * ******

It is my interpretation that an ionization type detector is required by the contract. You have indicated * * * that you have been able to locate only one supplier of an ironization type detector, namely, Pyrotron-ics, Inc. * * * if y0U cannot locate another ionization type detector, you should submit the Pyrotronics detector for my consideration.

The foregoing is the final decision of the Contracting Officer. Decisions *720 on disputed questions of fact and on other questions that are subject to the procedures of the Disputes Clause may be appealed in accordance with the provisions thereof. * * *

* * * I cannot tolerate any further delaying tactics on your part while you try to force the use of a system which is unacceptable. If you fail to immediately proceed with submission of an acceptable system, I must take the action available to me under Clause 5, “Termination for Default — Damages for Delay — Time Extensions”.

At the time in question, the Pyrotron-ics Division of Baker Industries was the only manufacturer of an ionization-type fire detecting unit. Such a unit is capable of detecting the gaseous products of combustion which form and are present before visible smoke results from the combustion.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bgt Holdings LLC v. United States
984 F.3d 1003 (Federal Circuit, 2020)
Laboratory Corp. of America v. United States
108 Fed. Cl. 549 (Federal Claims, 2013)
Bell/Heery v. United States
106 Fed. Cl. 300 (Federal Claims, 2012)
Retirement Communities LLC v. United States
92 Fed. Cl. 587 (Federal Claims, 2010)
LB&B Associates Inc. v. United States
91 Fed. Cl. 142 (Federal Claims, 2010)
Jay Cashman, Inc. v. United States
88 Fed. Cl. 297 (Federal Claims, 2009)
Metric Construction Co. v. United States
81 Fed. Cl. 804 (Federal Claims, 2008)
Information Systems & Networks, Corp. v. United States
81 Fed. Cl. 740 (Federal Claims, 2008)
International Data Products Corp. v. United States
492 F.3d 1317 (Federal Circuit, 2007)
C.D. Hayes, Inc. v. United States
74 Fed. Cl. 699 (Federal Claims, 2006)
M.A. DeAtley Construction, Inc. v. United States
71 Fed. Cl. 370 (Federal Claims, 2006)
International Data Products Corp. v. United States
70 Fed. Cl. 387 (Federal Claims, 2006)
Engineered Demolition, Inc. v. United States
70 Fed. Cl. 580 (Federal Claims, 2006)
Navcom Defense Electronics, Inc. v. England
53 F. App'x 897 (Federal Circuit, 2002)
Faust v. United States
33 Fed. Cl. 807 (Federal Claims, 1995)
Miller Elevator Co. v. United States
39 Cont. Cas. Fed. 76,635 (Federal Claims, 1994)
Gardner-Zemke Co. v. State
790 P.2d 1010 (New Mexico Supreme Court, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
420 F.2d 716, 190 Ct. Cl. 668, 1970 U.S. Ct. Cl. LEXIS 108, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ets-hokin-corporation-and-bank-of-america-national-trust-and-savings-ca3-1970.