Gholson, Byars and Holmes Construction Company v. The United States

351 F.2d 987, 173 Ct. Cl. 374, 1965 U.S. Ct. Cl. LEXIS 171
CourtUnited States Court of Claims
DecidedOctober 15, 1965
Docket349-63
StatusPublished
Cited by45 cases

This text of 351 F.2d 987 (Gholson, Byars and Holmes Construction Company v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gholson, Byars and Holmes Construction Company v. The United States, 351 F.2d 987, 173 Ct. Cl. 374, 1965 U.S. Ct. Cl. LEXIS 171 (cc 1965).

Opinion

PER CURIAM.

This case was referred pursuant to Rule 57(a) to Trial Commissioner Herbert N. Maletz, with directions to make findings of' fact and recommendation for conclusions of law. The commissioner has done so in an opinion and report filed on June 29, 1965. Plaintiff filed no exceptions or brief to the report. On July 28, 1965, defendant filed a brief excepting in part to the commissioner’s opinion and recommendation for conclusions of law. On August 16, 1965, plaintiff filed remarks on commissioner’s report under Rule 58 which, by order of August 19, 1965, were allowed as a statement submitted and filed pursuant to Rule 62. The case is now submitted to the court without oral argument as provided by Rule 62.

The court notes that defendant’s brief filed July 28, 1965, asserts that defendant does not except to that portion of the commissioner’s opinion and conclusions of law which deals with plaintiff’s claim for additional costs incurred in the washing of plaster surfaces. Since the court agrees with the commissioner’s findings, his opinion and his recommended conclusions of law, as hereinafter set forth, it hereby adopts the same as the basis for its judgment in this case. Plaintiff is therefore entitled to judgment under the “Changes” clause of the contract for the additional expenses incurred in washing with soap and water those plaster surfaces which could have been cleaned by wiping to accomplish the results required by the specifications and for the expenses incurred in painting those surfaces which had a baked enamel or hammertone finish. The amount of recovery will be determined pursuant to Rule 47(c). Such facts as are necessary to the decision of the case are found in the commissioner’s opinion.

OPINION OF COMMISSIONER

In June 1957, plaintiff entered into a contract with the General Services Administration (GSA) to furnish all labor and materials and perform all work required for lighting and painting improvements at the United States Post Office and Courthouse in Pittsburgh, Pennsylvania. It asserts three claims totaling $14,724.52 on behalf of its painting subcontractor, Charles Picoult, for work performed allegedly beyond the scope of the contract. The first claim in the amount of $8,250 arises from an alleged demand by a GSA representative that the subcontractor wash down all plaster wall and ceiling surfaces with soap and water before painting them. The second and third claims amounting to $6,350.74 and $123.78, respectively, arise from defendant’s directions requiring painting of (i) metal doors and counters, including par *989 titions, having a baked enamel finish and (ii) air units having a hammertone finish, which work, plaintiff says, was not required by the contract specifications. The claims were denied by the contracting officer, whose decision was affirmed on an appeal under the disputes clause by the GSA Board of Contract Appeals, and the case is here on an Assignment of Errors filed by plaintiff challenging the Board’s decision as arbitrary, capricious, contrary to the evidence and erroneous in law. The task is to review the administrative record before the Board to determine (1) whether its factual determinations meet the standards of the Wunderlich Act, 41 U.S.C. § 321, and (2) whether its interpretation of the contract specifications is correct. 1 It is in chis context that each of these claims is considered below.

Claim 1 — Washing of Wall and Ceiling Surfaces

Paragraph 5-18 of the specifications provided in part:

PREPARATION OF SURFACES, ETC. — Surfaces specified to be painted or enameled shall be clean and dry and free from dust, grease, soot, etc., at the time any coating is applied. * * * The cleaning shall be undertaken as a separate operation and shall be completed in its entirety in the areas designated by Government Representative. Surfaces that are required to be cleaned shall be inspected and approved by Government Representative before any painting of surfaces is begun. * * *

On December 11, 1957, the painting subcontractor addressed a letter to plaintiff (which the latter forwarded on the same day to the contracting officer for decision) stating that the GSA construction engineer at the job site interpreted paragraph 5-18 as requiring washing of plaster surfaces before repainting. The subcontractor said he disagreed with this interpretation because the provision did not cite any specific method by which a cleaning operation was to be conducted but merely specified that the surface required to be painted or enameled “shall be clean and dry and free from dust, grease, soot, etc.” Accordingly, the subcontractor continued, if a plaster area to be repainted was in such condition, no cleaning would be required and he could proceed with the painting. On the other hand, he declared, if dust, grease or soot was present in a particular plaster area, it was up to him to remove the condition by a cleaning method of his own choosing. The subcontractor added that it was not the intention of the specifications that plaster surfaces be washed as evidenced by the fact that where washing was required it was stated in plain terms, as in paragraph 5-46, which specifically provided that all previously varnished woodwork specified to be re-vamished shall be “cleaned with an approved wash.”

On December 16, 1957, the GSA construction engineer wrote the contracting officer stating that paragraph 5-18 of the specifications called for all surfaces to be cleaned before painting and that surfaces were to be “clean and dry and free from dust, grease, soot, etc.” He said that certain areas were brushed with a mop but the grease, soot, etc. remained on the wall and approval was not given until the grease, soot, etc. was removed. He indicated that it was up to the contractor to use any method he desired, within good practice, to clean walls as required by the specifications *990 to meet inspection approval by the government representative before any painting was done, adding that the surfaces submitted for inspection were not approved because soot, grease, etc. was not removed and that the contractor found it necessary to remove grease, soot, etc., after which approval was given to paint the surfaces. He stated that the “Contractor’s statement that Construction Engineer required plaster surface to be washed prior to painting is in error, however, surfaces must be cleaned to the approval of the Government Representative before it is painted.” 2

On January 29, 1958, the contracting officer replied to plaintiff’s letter of December 11, 1957, and stated that while paragraph 5-18 did not specifically mention washing, it required removal of dust, grease, soot, etc. prior to application of paint, and also included a provision that “Surfaces that are required to be cleaned shall be inspected and approved by a Government Representative before any painting of surfaces is begun.” “Accordingly”, the contracting officer wrote, “all surfaces to be treated must be cleaned by any appropriate means to the entire satisfaction of the Engineer-in-Charge of the work.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tidewater Contractors, Inc. v. United States
131 Fed. Cl. 372 (Federal Claims, 2017)
Jowett, Incorporated v. United States
234 F.3d 1365 (Federal Circuit, 2000)
PCL Construction Services, Inc. v. United States
47 Fed. Cl. 745 (Federal Claims, 2000)
M.A. Mortenson Co. v. United States
39 Cont. Cas. Fed. 76,555 (Federal Claims, 1993)
Western States Construction Co. v. United States
38 Cont. Cas. Fed. 76,376 (Court of Claims, 1992)
Olympic Marine Services, Inc. v. United States
792 F. Supp. 461 (E.D. Virginia, 1992)
Sterling Millwrights, Inc. v. United States
38 Cont. Cas. Fed. 76,316 (Court of Claims, 1992)
Craft Machine Works, Inc. v. United States
36 Cont. Cas. Fed. 75,861 (Court of Claims, 1990)
Ralph Larsen & Son, Inc. v. United States
35 Cont. Cas. Fed. 75,662 (Court of Claims, 1989)
Big Chief Drilling Co. v. United States
15 Cl. Ct. 295 (Court of Claims, 1988)
Boyd International Ltd. v. United States
33 Cont. Cas. Fed. 74,501 (Court of Claims, 1986)
Tibshraeny Bros. Construction, Inc. v. United States
32 Cont. Cas. Fed. 73,017 (Court of Claims, 1984)
McGrew Bros. Sawmill
27 Cont. Cas. Fed. 80,577 (Court of Claims, 1980)
Alfred A. Altimont, Inc. v. United States
579 F.2d 622 (Court of Claims, 1978)
Kenneth Reed Construction Corp. v. United States
475 F.2d 583 (Court of Claims, 1973)
Astro-Space Laboratories, Inc. v. United States
470 F.2d 1003 (Court of Claims, 1972)
John McShain, Inc. v. United States
462 F.2d 489 (Court of Claims, 1972)
Chris Berg, Inc. v. United States
455 F.2d 1037 (Court of Claims, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
351 F.2d 987, 173 Ct. Cl. 374, 1965 U.S. Ct. Cl. LEXIS 171, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gholson-byars-and-holmes-construction-company-v-the-united-states-cc-1965.