Chris Berg, Inc. v. United States

455 F.2d 1037, 197 Ct. Cl. 503, 1972 U.S. Ct. Cl. LEXIS 25
CourtUnited States Court of Claims
DecidedFebruary 18, 1972
DocketNo. 231-68
StatusPublished
Cited by57 cases

This text of 455 F.2d 1037 (Chris Berg, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chris Berg, Inc. v. United States, 455 F.2d 1037, 197 Ct. Cl. 503, 1972 U.S. Ct. Cl. LEXIS 25 (cc 1972).

Opinion

Pee Curiam:

This case was referred to Trial Commissioner Joseph V. Colaianni with directions to prepare and file his opinion on the issues of plaintiff’s motion and defendant’s cross-motion for summary judgment under the order of reference and Buie 166(c). The commissioner has done so in [506]*506an opinion and report filed on March. 10, 1971, Avherein such facts as are necessary to the opinion are set forth. A request for review of the commissioner’s opinion and recommendations was filed by plaintiff, defendant urged the court to adopt the commissioner’s opinion and the case has been submitted to the court on oral argument of counsel and the briefs of the parties. Since the court agrees with the opinion and recommended conclusions of the trial commissioner, it hereby adopts the same as hereinafter set forth as the basis for its judgment in this case. Therefore, as to Claims I and III plaintiff’s motion for summary judgment is denied, defendant’s cross-motion is granted and the petition is dismissed. As to Claim II, with respect to the painting of one stairway and certain N.I.C. areas, plaintiff’s motion for summary judgment is granted and defendant’s cross-motion is denied. Further proceedings as to this claim are stayed pursuant to Buie 167 for a period of 90 days to afford the parties an opportunity to obtain an agency resolution of the amount of equitable adjustment to which plaintiff is entitled.

OPINION OP COMMISSIONER

Colaianni, Commissioner: Plaintiff’s claims arise out of a January 12, 1965, contract with the Corps of Engineers for the repair of earthquake caused damage to a hospital at Elmendorf Air Force Base in Alaska. The claims are made and presented for and on behalf of Warren Painting Company Inc. of Anchorage, Alaska, plaintiff’s subcontractor.

BacJegrovmd Facts

On March 27, 1964, portions of Alaska were heavily damaged by a severe earthquake. The multi-story, 400-bed Air Force Base Hospital, outside of Anchorage, Alaska, was among the buildings that suffered extensive damage. The damage was of such a nature and severity that it was necessary to completely deactivate the hospital.

To enable repairs to be made to the hospital, and other Alaskan facilities, emergency funds were made available by the United States Government pursuant to Title 42 U.S.C. § 1855e. Because of the necessity that the hospital be re[507]*507activated as quickly as possible, a th.ree-pb.ase repair and restoration program, under the auspices of the Alaska District of the Corps of Engineers, United States Army Engineers, was decided upon.

A contract to conduct Phase I repair and restoration work was negotiated between the United States Army Corps of Engineers and M-B Contracting Company. The Phase I work concentrated on the critical areas that needed immediate attention to enable the most basic of hospital services to be performed. The work on Phase I commenced shortly after the earthquake and continued through May 15,1964.

The Phase II repair and restoration contract was also awarded to M-B Contracting Company, and work under this contract commenced immediately after termination of Phase I work and continued until late December 1964. The repair and restoration work under Phase II also concentrated on the more essential and critical areas of the hospital.

The emergency repairs conducted during Phases I and II were not only generally limited to the most critical of areas in the hospital, but were also substantially of an incomplete or temporary nature.

Furthermore, while the Phase I and II contracts were primarily concerned with structural type repairs, the testimony shows that painting to select areas also occurred. There is no dispute that during April and early May 1964, clinical laboratory areas, obstetric delivery areas, and surgical areas were given a touch-up and one finish coat of paint. Similarly, there is no question that just prior to Christmas day 1964, during the Phase II contract, the main lobby of the hospital was painted in anticipation of holiday visitations.

The claims with which we are here concerned arose out of contract No. DA 95-507-ENC — 2070, awarded to plaintiff for interior and exterior repair and rehabilitation work to be performed during Phase III. The $1,044,7861 contract included an estimate of $12,9,500 for the painting called for by the contract. This painting estimate was based on the low job basis bid of Warren Painting Company, Inc. (hereinafter referred to as Warren) for Item 21 of the unit price schedule. [508]*508In turn, Warren’s bid2 breaks down into estimates of $113,000 for painting of tbe interior,3 and $16,500 for painting of the exterior.

Plaintiff seeks equitable adjustments, by way of a standard “Disputes” clause in the contract, for increased costs allegedly occasioned by constructive changes.

Plaintiff originally requested a contracting officer’s decision with respect to five claims of compensation for extra painting work performed on the Elmendorf Base Hospital. Four of plaintiff’s claims were denied by the contracting officer’s decision of February 14, 1966. However, plaintiff’s fifth cause of action, which sought an equitable adjustment to the contract price for the cost of painting built-in metal cabinets, was not decided since the parties were attempting to settle it through negotiations. By way of Modification No. 49 to the contract, the parties on June 29,1966, agreed to a contract increase of $11,800.26 for painting of the prefinished items covered by plaintiff’s fifth cause of action. On appeal, the Armed Services Board of Contract Appeals (hereinafter referred to as Board) denied three of plaintiff’s remaining four claims, but sustained plaintiff’s claim of $35,092.45 for extra labor and material costs incurred for stippling of interior walls and ceilings.4

Plaintiff seeks review of the Board’s adverse determina tions, urging that the Board committed reversible error» both in its findings of fact and conclusions of law. 3h this instance, the issues are presented by cross-motions for summary judgment and must be resolved in accordance with Wunderlich Act standards.5

The separate and distinct claims for equitable adjustments which plaintiff wants this court to review are:

(I) The Board’s determination that the application of a [509]*509fill-coat and finish, coat on the entire building exterior was a contract requirement;

(II) The Board’s determination that additional work on the interior of the building was a contract requirement; and

(III) The Board’s factual determination that plaintiff was not subjected to excessive workmanship standards.

The basis for each of plaintiff’s claims is the “Changes” clause of the contract. The Board in denying each of the above listed claims, held that the work required of plaintiff, to both the interior and exterior, was clearly called for by the contract, and that the standards of the workmanship to which plaintiff’s subcontractor was held did not substantially exceed those warranted by the contract.

Each of plaintiff’s three claims are herein discussed separately.

CLAIM I

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mw Builders, Inc. v. United States
134 Fed. Cl. 469 (Federal Claims, 2017)
Magnus Pacific Corporation v. United States
133 Fed. Cl. 640 (Federal Claims, 2017)
Shaw v. United States
131 Fed. Cl. 181 (Federal Claims, 2017)
Mata v. United States
114 Fed. Cl. 736 (Federal Claims, 2014)
Laboratory Corp. of America v. United States
108 Fed. Cl. 549 (Federal Claims, 2013)
Public Service Co. v. United States
88 Fed. Cl. 250 (Federal Claims, 2009)
West Bay Builders, Inc. v. United States
85 Fed. Cl. 1 (Federal Claims, 2008)
Rotech Healthcare Inc. v. United States
71 Fed. Cl. 393 (Federal Claims, 2006)
International Data Products Corp. v. United States
70 Fed. Cl. 387 (Federal Claims, 2006)
ACE Constructors, Inc. v. United States
70 Fed. Cl. 253 (Federal Claims, 2006)
Conner Brothers Construction Co. v. United States
65 Fed. Cl. 657 (Federal Claims, 2005)
Flink/Vulcan v. United States
63 Fed. Cl. 292 (Federal Claims, 2004)
CEMS, Inc. v. United States
59 Fed. Cl. 168 (Federal Claims, 2003)
Ryco Construction, Inc. v. United States
55 Fed. Cl. 184 (Federal Claims, 2002)
PCL Construction Services, Inc. v. United States
47 Fed. Cl. 745 (Federal Claims, 2000)
ITT Federal Services Corp. v. United States
45 Fed. Cl. 174 (Federal Claims, 1999)
Metric Constructors, Inc. v. United States
44 Fed. Cl. 513 (Federal Claims, 1999)
Inslaw, Inc. v. United States
42 Cont. Cas. Fed. 77,302 (Federal Claims, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
455 F.2d 1037, 197 Ct. Cl. 503, 1972 U.S. Ct. Cl. LEXIS 25, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chris-berg-inc-v-united-states-cc-1972.