Allied Contractors, Inc. v. The United States

381 F.2d 995, 180 Ct. Cl. 1057, 1967 U.S. Ct. Cl. LEXIS 110
CourtUnited States Court of Claims
DecidedJuly 20, 1967
Docket256-61
StatusPublished
Cited by14 cases

This text of 381 F.2d 995 (Allied Contractors, Inc. v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Allied Contractors, Inc. v. The United States, 381 F.2d 995, 180 Ct. Cl. 1057, 1967 U.S. Ct. Cl. LEXIS 110 (cc 1967).

Opinion

OPINION

PER CURIAM:

This case was referred to Trial Commissioner Saul Richard Gamer with directions to make findings of fact and *996 recommendation for conclusions of law. The commissioner has done so in a report and opinion filed on April 19, 1967. Plaintiff has filed no exceptions to or brief on this report and the time for so filing pursuant to the Rules of the court has expired. On June 8, 1967, defendant filed a motion that the court adopt the commissioner’s opinion. Since the court agrees with the commissioner’s findings, opinion and recommended conclusion of law, as hereinafter set forth, it hereby adopts the same as the basis for its judgment in this case without oral argument. Plaintiff is, therefore, not entitled to recover and the petition is dismissed.

OPINION OF COMMISSIONER *

GAMER, Commissioner:

Plaintiff entered into a contract with the Army Corps of Engineers for the construction of a “Nike Launching Area” at a site near Davidsonville in Anne Arundel County, Maryland. During construction, two walls collapsed. Plaintiff contends that these walls were constructed by it in strict compliance with the plans and specifications and that their collapse was due only to their erroneous design, for which defendant was responsible. This issuance by defendant of defective plans and specifications, plaintiff argues, amounts to a breach of contract entitling it to recover the additional costs it incurred resulting from the collapse of the walls and their reconstruction, as required by defendant.

On the basis of the record of the trial proceedings herein, 1 it is concluded that plaintiff is not entitled to recover because, even if it is correct in its contention that the walls were erroneously designed, it was obvious, and plaintiff therefore knew or should have known that, considering their nature and character, they would, unless properly supported, collapse under certain conditions, which here materialized. Accordingly, it was plaintiff’s clear obligation to take appropriate protective or precautionary *997 measures to prevent this from happening.

These walls were unusual. They were so-called block masonry walls located on only two sides of a rectangular underground pit. This pit was below, and of smaller dimensions than, another pit. The walls were to be constructed according to a specified planned sequence. First, even prior to the excavation of the pit, wood sheet piling or shoring was to be driven into the earth at the boundary of the pit. After the pit would be excavated up to the sheeting, the block wall (concrete blocks held together with mortar) was then to be built flush against the sheeting. However, the wall extended about 9 inches above the sheeting, the top of the wall thus being in direct contact with earth during such period of construction. The wall was 6 feet, 6 inches, in height, 60 feet long, and only 4 inches thick. A 2-inch subfoundation concrete base was then to be poured. A heavy waterproofing membrane (5 plies) was then to be applied on such base and all the way up the inside height of the walls. A 2-foot foundation concrete floor slab was then to be poured on the waterproofed 2-ineh subfoundation base, and a 2-foot concrete wall also poured against the waterproofed 4-inch block wall. There was to be nothing between the smooth surfaces of the waterproofed block wall and the 2-foot concrete wall. When completed, the 4-inch block wall and the 2-foot concrete wall together were to form a one-wall-like (i. e., a “monolithic”) structure, with the waterproofing material incorporated within the structure.

Only two of these block walls, located on the opposite sides of the pit, were to be constructed. Thus, during the above-described construction sequence and until the 2-foot wall would be poured against it (and the 2-foot floor slab, which would supply partial support), the walls would stand unsupported by connecting side walls, as in the conventional 4-wall-ed structure, or by any structure on top, or by anything on the waterproofing membrane side facing the pit. Except for the sheeting and earth on the back side, these long thin walls would thus simply stand without any support.

In the pit in question, plaintiff had by August 4, 1954, completed driving the sheet piling, excavating the pit, laying the 4-inch block walls, pouring the 2-inch concrete base, and applying the waterproofing. Heavy rainfall occurred in the area on August 2, 3, 5, 9, and 10. On the night of August 10, while the south wall was standing in the above-described unsupported position, i. e., prior to the pouring of the 2-foot concrete wall and the 2-foot floor slab, the wall collapsed, falling into the open pit and onto the sub-foundation base.

Heavy rain occurred again on the night of August 19. During that night, the wall on the north side of the pit, similarly standing in the same unsupported condition, also collapsed into the pit.

Both walls had collapsed due to the hydrostatic or water pressure exerted behind them and which had been built up as a result of the rains. The pressure simply served to push the walls into the pit, there being no counteracting force of any kind. Although the walls were built against the sheeting, the sheeting was not watertight, nor was it designed to be. It consisted of wood boards driven alongside of each other, with % to 14-inch spaces between the boards, permitting water and silt to penetrate. In addition, since the sheeting did not extend to the top of the wall, the rear of the wall was directly exposed to wet earth. 2

*998 Plaintiff says it built the walls exactly as called for by the plans and specifications, and that if they were not strong enough to withstand hydrostatic pressure, then it was simply a matter of improper design for which defendant alone was responsible. It contends that a contract drawing contained a “Structural Note” which, properly interpreted, stated that the walls were designed to withstand hydrostatic pressure, 3 a statement upon which it had a right to rely. It points out that the pertinent “Protection” section of the specifications (TP sec. 6-08j (finding 9)) made no provision for the temporary buttressing or supporting of the walls against hydrostatic pressure due to rain or snow during the course of construction, and that plaintiff fully complied with all of the affirmative requirements which were specified by such section. Thus, attributing its damages solely to defendant’s improperly designed walls, it seeks recovery upon the principles enumerated in such cases as United States v. Spearin, 248 U.S. 132, 39 S.Ct. 59, 63 L. Ed. 166 (1918), Steel Products Engineering Co. v. United States, 71 Ct.Cl. 457 (1931), Stapleton Constr. Co. v. United States, 92 Ct.Cl. 551 (1940), and Warren Bros. Roads Co. v. United States, 105 F.Supp. 826, 123 Ct.Cl. 48 (1952), to the effect that the Government is liable for damages resulting from the issuance of faulty or inadequate plans, specifications,

or designs, or for misleading the contractor by erroneous statements contained therein.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

PCL Construction Services, Inc. v. United States
47 Fed. Cl. 745 (Federal Claims, 2000)
Wickham Contracting Co. v. United States
546 F.2d 395 (Court of Claims, 1976)
City of Philadelphia v. Page
363 F. Supp. 148 (E.D. Pennsylvania, 1973)
Merando, Inc. v. United States
475 F.2d 598 (Court of Claims, 1973)
Chris Berg, Inc. v. United States
455 F.2d 1037 (Court of Claims, 1972)
Nordin Construction Company v. City of Nome
489 P.2d 455 (Alaska Supreme Court, 1971)
Whittaker Corporation v. The United States
443 F.2d 1373 (Court of Claims, 1971)
Maurice Mandel, Inc. v. United States
424 F.2d 1252 (Eighth Circuit, 1970)
L. W. Foster Sportswear Co., Inc. v. The United States
405 F.2d 1285 (Court of Claims, 1969)
J. A. Jones Construction Company v. The United States
395 F.2d 783 (Court of Claims, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
381 F.2d 995, 180 Ct. Cl. 1057, 1967 U.S. Ct. Cl. LEXIS 110, Counsel Stack Legal Research, https://law.counselstack.com/opinion/allied-contractors-inc-v-the-united-states-cc-1967.