Central Ohio Joint Vocational School District Board of Education v. Peterson Construction Co.

716 N.E.2d 1210, 129 Ohio App. 3d 58, 1998 Ohio App. LEXIS 3207
CourtOhio Court of Appeals
DecidedJuly 13, 1998
DocketCA97-05-024 and CA97-05-026
StatusPublished
Cited by8 cases

This text of 716 N.E.2d 1210 (Central Ohio Joint Vocational School District Board of Education v. Peterson Construction Co.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Central Ohio Joint Vocational School District Board of Education v. Peterson Construction Co., 716 N.E.2d 1210, 129 Ohio App. 3d 58, 1998 Ohio App. LEXIS 3207 (Ohio Ct. App. 1998).

Opinion

*61 Walsh, Judge.

Plaintiff-appellant Central Ohio Joint Vocational School District Board of Education (“the board”) appeals a jury verdict rendered in the Madison County Court of Common Pleas in favor of appellees, Peterson Construction Company (“Peterson”) and George J. Igel and Company (“Igel”), in a dispute arising out of the expansion of the Tolies Technical Center (“the school”). We affirm.

On March 26, 1994, the board entered into a construction contract (“the contract”) with Peterson for a nine million dollar expansion of the school. Peterson subcontracted with Igel to perform soil excavation at the school expansion site. Before construction began, the board separately hired Dunbar Geotechnical Engineers (“Dunbar”) to test the soil subsurface and to act as the soil engineer throughout the construction. Ultimately, the school expansion was built on a peat bog, an underground deposit of weak, organic soil. Once construction was completed, the school building “settled,” causing extensive damage. Peterson and the board agreed that Peterson would repair the damage under a supplemental Interim Reconstruction Funding Agreement (“IRFA”). The IRFA reserved issues of liability until the construction was completed.

On July 24, 1995, the board sued Dunbar and Peterson for breach of contract and negligence. On September 20, 1995, Peterson answered the complaint, filed a counterclaim against the board for breach of contract, and a cross-claim against Dunbar for negligence and breach of contract. 1 Before trial, all claims against Dunbar were dismissed and the claims of negligence were dismissed. Following a two-week jury trial that ended August 24, 1996, the jury found against the board. On Peterson’s counterclaim, the jury awarded $323,436.82. On May 14, 1997, the court entered final judgment, amending the award on the counterclaim to $390,190.36. The board filed a timely notice of appeal, and Peterson filed a notice of cross-appeal. This court consolidated the appeals on or about June 17, 1997. Peterson moved to dismiss the cross-appeal, which motion was granted by this court on or about March 19, 1998. The board presents two assignments of error for our review:

“The trial court erred by allowing the jury to decide the meaning of the key contract provision at issue, Section 2100-3.02(A).
“The trial court erred to the prejudice of the school board by improperly instructing the jury on the ‘Spearin doctrine’ over the school board’s objections.”

*62 Introduction

Before construction ever began, the board hired Dunbar to perform soil analysis of the site and to recommend a solution to any inadequate subsurface conditions. The testing revealed that very soft, organic soil existed in the northwest corner of the construction site. On October 19, 1993, November 28, 1993, and February 4, 1994, Dunbar issued preconstruction reports on the site. Due to those reports, the board included specific contractual requirements for the excavation of the material in the northwest corner of the site. These requirements were largely contained in Section 2100, Paragraph 3.02(A).

The parties regularly at the site included Alan Stechschulte, who acted as project superintendent for Peterson, and Ben Backus, a soil engineer from Dunbar. On June 4, 1994, excavation began on the northwest corner of the site, and Igel excavated to an elevation of nine hundred thirty-three feet. However, at that depth, the bottom of the excavation was still too soft and wet. On June 8, 1994, a meeting took place to discuss the organic soil problem. At the meeting, representatives of Dunbar, the board, and Peterson discussed possible solutions.

The board and Peterson dispute the outcome of the meeting. Peterson claims the agreement was to excavate as far as Dunbar deemed necessary and use a three-foot layer of stones at the bottom of the excavation. According to Peterson, the other suggestion, ultimately not adopted, was to excavate all the soft, organic soil. After the meeting, a change order to the construction contract was written and signed by representatives of Peterson and the board. The change order required Peterson to “[fjurnish all material and perform all labor to deliver, place and compact additional stone base material to stabilize bottom of excavated area where unsuitable soil was removed * * *. Place stone material as directed by Dunbar Geotechnical Engineers, Inc.” The board insists that the change order was not an alternative approach, but represented an additional requirement of the contract.

Is the Term “FULL DEPTH” Unambiguous?

In the first assignment of error, the board asserts that the trial court erred in allowing the jury to interpret the contract provision that is at the center of this dispute. The provision is Section 2100-3.02(A), which states:

“Within limits of new building and pavement construction and to a line at least 5’ — 0” beyond, remove to FULL DEPTH all topsoil, fill material and zones of organic soil. Soil borings within the Academic Building indicate the presence of unsuitable fill material to the approximate elevations indicated on drawings, sheet C2.01. At the west side of the building, within the limits indicated on Sheet C2.01, remove existing soils to an average elevation of approximately 933.0’. Slope, shore or brace excavation walls as required by conditions encountered. Within limits of *63 new pavements north and west of the academic building, within the limits indicated on Sheet C2.01, remove existing soils to an average elevation of approximately 949.0’. Extend excavation to additional depths as required at points where existing drainage swale crosses new drive. Extent of removal of existing fill materials will be closely monitored by Soils Engineer.”

The board alleges that the first sentence of the above contract provision is “clear and unambiguous” and should have been interpreted by the trial judge. “If a contract is clear and unambiguous, then its interpretation is a matter of law and there is no issue of fact to be determined.” Inland Refuse Transfer Co. v. Browning-Ferris Industries of Ohio, Inc. (1984), 15 Ohio St.3d 321, 322, 15 OBR 448, 449, 474 N.E.2d 271, 272. “However, if a term cannot be determined from the four corners of a contract, factual determination of intent or reasonableness may be necessary to supply the missing term.” Id. The board argues that the term “FULL DEPTH” clearly required all organic soil to be removed by Peterson. Appellees insist that the provision, taken in proper context, is either ambiguous or contradicts the board’s interpretation.

Expert witness David Breitfeller, a civil engineer, testified that “FULL DEPTH” meant to dig as far as the soil engineer required. Breitfeller’s interpretation is bolstered by the final sentence of Section 2100-3.02(A), which required excavation to be closely monitored by the soil engineer.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Plains Commerce Bank v. Long Family Land & Cattle Co.
910 F. Supp. 2d 1188 (D. South Dakota, 2012)
Moonscoop SAS v. American Greetings Corporation
489 F. App'x 95 (Sixth Circuit, 2012)
Alltank Systems v. Grant Systems Inc.
2011 Ohio 5453 (City of Cleveland Municipal Court, 2011)
Brakefire, Inc. v. Overbeck
2007 Ohio 6464 (Clermont County Court of Common Pleas, 2007)
Muhlfelder v. Rieth & Antonelli Co.
2005 Ohio 5936 (City of Cleveland Municipal Court, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
716 N.E.2d 1210, 129 Ohio App. 3d 58, 1998 Ohio App. LEXIS 3207, Counsel Stack Legal Research, https://law.counselstack.com/opinion/central-ohio-joint-vocational-school-district-board-of-education-v-ohioctapp-1998.